Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Business
Management of Projects
What is a project?
Deadline
Management
Manage to
Plan
Costs of Project
Failure
Standish Group survey of US IT Systems Projects:
17%
Met Target
50%
33%
Cancelled
Separating Objectives
Project Scoping
What do you want to do? - Understand the deliverable
How do you want to do it? Project Planning Assumptions
Project Planning
Program
Project
Task
Sub Task
Work Package
Activity
Work Breakdown
Structures
www.picassodlcf..com.uk/lecture
Interior Trim
Rear Seats
Wide Access
Controls
Change Speed
Engine
9 gm NoX
Brakes
ABS
Chassis
Framesides/Xmbr
Springs & Dampers
Concept Investigation
Concept Approval D2
Programme Definition
Programme Approval D4
Engineering Release Stage IV
Methods Review
Build/Sign off Mock-up
Prototype Build
Test/Development
Stage V Sign off
Procure pre-prod materials
Sample Approval
Pre-Production build
Issue material to lineside
Proof build
Job 1
Estimating Resources
An exact estimate is impossible
The more experience there is of an
activity the easier it is to estimate.
If people are punished for failure they
will pad estimates.
Project
estimating assumes 50%
probability estimates are used unless
specified otherwise.
X
Time
Estimate 3
Estimate 3
Estimate 4
XX
XX
X
X X
Estimate 5
Estimate 1
Estimate 2
Situation A
Estimate 4
Estimate 2
Estimate 1
Consensual
Estimating
Time
Situation B
Logical
Dependencies
Start/Start
Start/Finish
Finish/Finish
Activity Network
(Activity on Node)
100
200
300
400
500
700
800
900
1100
1200
1300
600
1000
1400
1500
1600
Days Early
Days Late
PERT
for a Task
a = optimistic duration
b = likely duration
c = pessimistic duration
Expected Time = a + 4 x b + c
6
PERT
for a Project:
Expected Project Duration is the sum of the expected
durations of the activities on the critical path.
for an activity:
The standard deviation = a - c
6
for a Project:
Standard deviation = s12+s22+s32.
Gantt Chart
Resource Histogram
Schedule Computations
(fixing the plan to a point in time)
Forward Scheduling
Backward Scheduling
Resource Constraining
Effect of Slippage
Critical
Bottleneck
Float
Slip
Critical
Bottleneck
Float
Buffer
Project Deliverable
Review
Design
Does it Work?
Can we make it?
Is it still viable?
Risk
Project Management
Review
Current Project Status
Future Status
Status of Critical Tasks
Risk Assessment
Information Relevant to other
Projects
Limitations of Review
Final Messages
Project management challenge
increases with number of
communication interfaces
Estimating is difficult
Software tools help to establish an
achievable plan beware GIGO
Plan to Manage Manage the Plan
Appendix 1 1/2
Appendix 1 2/2
Appendix 2
Review Questions
CASE STUDY
The North West Rail Link will deliver savings of up to 3 hours a week
in journey times to the Sydney CBD as well as frequent,
reliable, direct rail services between the North West and Macquarie Park,
Chatswood, North Sydney and the city. The rail link includes 15km of
tunnels between Bella Vista and Epping - the longest and deepest rail
tunnels ever built in Australia.
InfraSol Group was appointed by Transport for NSW in May 2011 to
work as part of their inhouse project management team to deliver the
following Services for the Business Case Stage of the $9 Billion project.
CASE STUDY
The National Gallery of Australia,
Canberra - Stage 1 Extensions
A $100 million Stage 1 Extension to the National
Gallery of Australia was under construction on site
while the design was still being completed.
1. Project Leadership
The InfraSol Group principal, John Barrow, was
brought in to resolve the problems with the
project delivery.
John tackled the problem head on by doing the
following:
Meeting with the building committee
The
result
of
InfraSol
Group's
project
leadership was the successful delivery of the
project to meet the construction programme and to
the required quality and completeness.
Cost to complete
Time to complete