SUMMARY OF PILE

REMEDIAL WORKS
27 September 2013
Red River Bridge Construction Project
Package 1

Method I

Method II

Sound Pile

Defective Pile

Group A

Summary
of
Constructed Piles
Before
25th Nov, 03

Pier No.
P1
P2
P3
P4
P7bL
P7R

Total
584
Sound 410
Defect 174

Gia Lam

River

Thnah Tri

P8
P9
P10
P11
P12
P15
P16
P17
P18
P19
P20
P21
P23
P24
P25
P28
P29
P30
P31
P32
P33
P34
P43
P44
P45

Pile
No. of
Length
Piles
(m)
43.0
44.5
47.0
45.5
47.0
47.0
L45.0
R44.5
46.85
47.35
52.0
52.0
49.0
53.5
54.5
54.0
56.35
37.5
34.85
25
29.8
32.5
29.0
41.5
42.0
42.0
43.0
39.0
39.0
34.5
35.0
32.5

Before
25
Nov/2003

16
16
16
16
8
8

9
16
2
2
1
5

40
40
32
16
16
24
16
16
16
16
32
32
64
49
64
32
18
18
18
18
24
18
16
32
40

After
25
Nov/2003

Group B

Group C

Group D

Group E

DL<1.0m

1.0<DL<3.0

3.0<DL<5.0

DL>5.0m

Injection
Grout

Total of
Defective

Column Jet Grout

2
-

1
2

4
-

7
3

35
1
9
10
3

1
5

3
10
3
2

6
2

1
10
4
1

3
8
5
6
8

5
8
4
4
2
3

8
1
0
7
16

5
31
7
6
1
16
16
12
11
9
30

14
14

4
5
15
2
64
49
48
20
11
9
7
8
9
1
15
29
35

No. of
Additional
Piles

16
12
7
9
9
9
15
17

1
1
2
1
3

16

8
8

8
16

2
-

1
3
5

2
1

1
3
5

Summary of Piles constructed before 25th Nov., 03

E 52 (8.9%)
D 38 (6.5%)
C 51 (8.7%)
B 33 (5.7%)

Total
584 piles

A 410
(70.2%)

Pressure Grouting
(50 to 60 kg/cm2)

METHOD I
(Injection Grout)

Valve to close Outlet

Sand Layer

Detail A

Gravel Layer

Sonic Tube

BORED PILE

Gravel Layer

DETAIL A

Non-Homogeneous Portion

METHOD II (Column Jet Grout)

Step 1

Boring

Step 2

Jet Testing

Step 3

Jet Grouting

Step 4 Grouting Finish


Pull up Tube

High Pressure Water = 400 kgf/cm2


Compressed Air Pressure = 7 kgf/cm2

Cement Milk Grout Pressure = 20 kgf/cm2


Lifting up of Triple Tube

Suspected Unconformance Section

Rotating of Triple Tube

Improved Section

Remedial Method by Additional Piling


FRONT VIEW
L-PIER

R-PIER

P16 and P17


PILE ARRANGEMENT

Value

Grout
Mixer

Sonic Tube

Bored Pile

Bottom Opened

Trial Improvement of Pile by Injection Grout

Pressure Grouting
(50 to 60 kg/cm2)

Valve to close Outlet

Sand Layer

Injection Grout
using 4 tubes

Detail A

Gravel Layer

Sonic Tube

BORED PILE

Gravel Layer

DETAIL A

Non-Homogeneous Portion

Column Jet Ground

Calculation of Effective Bearing Capacity after Remedial Works

Suspected Length

Ls

Original Length: Lo

Le

Effective Length

Original Bearing Capacity


Qu= Qt + Qsi
Qt = A x qt, Qsi = fi x Lo

Bearing Capacity without remedy


Qu= 0 x Qt + Qsi
Qsi = fi x Le
Bearing Capacity after remedy
Qu= Qt + Qsi

Original Area: A

Qt = 0.7 x A x qt, Qsi = fi x Le

Effective Area
0.7 x A
Deduction Area
0.3 x A

Following Construction control, maximum deduction area


is to be 30%, usually less than 30 %

Typical Arrangement of Improvement by Jet Grouting

Step 1

Boring

Step 2

Jet Testing

High Pressure Water = 400 kgf/cm2


Compressed Air Pressure = 7 kgf/cm2

Cement Milk Grout Pressure = 20 kgf/cm2

Suspected Unconformance Section

Step 3

Jet Grouting

Step 4 Grouting Finish


Pull up Tube

Lifting up of Triple Tube


Improved Section

Rotating of Triple Tube

Each Function of Jet Grouting

Structure Model of Triple Tube

Slime
Guide Hole (Dia. 140mm)

High Pressure
Water
Compressed Air
Cement Milk
Slime
Triple Tube (Dia. 90mm)

Compressed Air (7 kg/cm2)


High Pressure Water
(400 kg/cm2)

Cement Milk (20kg/cm2)

Compressed Air
High Pressure
Water
Compressed Air
Cement Milk

Slime

Slime
Slime
Guide Hole (Dia. 140mm)
Slime

Slime
Slime
Triple Tube (Dia. 90mm)

Compressed Air (7 kg/cm2)


High Pressure Water
(400 kg/cm2)

Cement Milk (20kg/cm2)

Summary of Result of Remedial Works


Method - I
23 piles (13%)

Total
174 piles
By Additional Pile
110 piles (63%)

Method - II
41 piles (24%)