GET/DET Training Program

Date: 16 September 2005


L&T - Sargent & Lundy Limited

PLOT PLAN
PLANT DATA

Size and capacity of the unit


Type of Plant (Indoor / Outdoor)
Hazardous Classification
Overall operating philosophy
Raw material receipt / dispatch Philosophy
Storage Philosophy
Effluent Plant Capacity, Discharge Points
Fire Hydrant System

PLOT PLAN
METEROLOGICAL DATA

Minimum, Maximum and normal Temperature

Rainfall

Intensity and direction of the Wind (Wind rose)

Seismic Zone

Wet and Dry Bulb Temperature

Flood Level

PLOT PLAN
CIVIL

Plane Table Survey Map

Showing extent of plot with overall area


Showing existing constraints like transmission lines,
structures, ponds, place of worship if any etc.
Survey covers 20 to 30 meters beyond extent of plot
Showing geographical north, location of power and
water connections

Contour Survey Map

Showing level of the plot w.r.t. mean sea level


Generally levels are taken at 10 M grids
Gives the co-ordinate system (N-S, E-W or X-Y)
Showing bench marks indicating MSL

Soil Survey Map


Gives bearing capacity of the soil
Gives nature of the soil for its expansiveness,
corrosiveness properties

PLOT PLAN
ELECTRICAL

Supply voltage level

Voltage levels required within Plant

Fault levels to establish the power distribution


system

Location of the supply point

PLOT PLAN
NON PLANT FACILITY

Administrative Block
Canteen
Workshop / Contractors Shed
Laboratory / R&D
Gate House / Time office
Security Arrangements
Vehicle Parking
Medical Centre
Ware House (Covered, Open, Solid, Liquid)
Steel / Scrap Yard
Fire Station
Weigh Bridge
Staff Colony

PLOT PLAN
UTILITIES DATA

Source and Supply point of Raw Water

Source of Fuel

Quality of water and Fuel available

Water consumption

Requirement of different types of utilities like


steam, air, N2, DM water, Cooling water etc.

Capacity and grouping philosophy such as


common utility / dedicated utility

PLOT PLAN
STATUTORY REQUIREMENTS

Green Belt

Floor area occupation,

Floor space index

Width of the roads

Free area to be maintained along plot boundary

Floor to Floor distances

Distance to be maintained between the units

Petroleum / Gas Storages

Fire Fighting

Height of Stack

PLOT PLAN
STATUTORY NORMS BY
ORGAINSATION

STATE INDUSTRIAL DEVELOPMENT


CORPORATION

POLLUTION CONTROL BOARD

FACTORY INSPECTORATE

STATE ELECTRICITY BOARD

CHIEF CONTROL OF EXPLOSIVE

TARIFF ADVISORY COMMITTEE

AVIATION LAWS

CHIEF INSPECTOR OF BOILERS

MINISTRY OF ENVIORNMENT AND FOREST

PLOT PLAN
EXPANSION PHILOSOPHY

Expansion within the Unit

Expansion for additional Units

Near Future Expansion

Far Future Expansion

PLOT PLAN
Based on the data collected about the various
facilities of the plant, block dimensions for the

following are worked out


Turbine
Gas

building

turbine area

Boiler

/ HRSG space requirement

Chimney

Fuel

storage and pumping area

Water

storage and Pumping area

Electrical

receiving stations and substation Cont

PLOT PLAN
Effluent

treatment area

Cooling

tower

CW

pump house

CW

treatment building

DM

plant area

Control room

Administrative

building, workshop, canteen,

laboratories, stores
Roads,

storm water drain

Tentative

details of pipe rack

Site, Property and Plant Development Dwgs.

Plant North and true north directions to be


identified on plan drawings
Graphical scale to be indicated
Elevations referenced to both MSL and plant
datum to be identified
Plant Ground floor
Plant Grade
High Water Level
Mean Water level
Low Water Level
CONTD...

Site, Property and Plant Development Dwgs.

Evaluate the for Potential Flooding (if the plant is


located near to sea or river)
Locate the structures and facilities on the
drawing
Main power block building
HRSG stack
CW pump house
Service, administration and shop buildings ( as
applicable)
Water treatment building

Site, Property and Plant Development


Drawings

Identify the piping and electrical duct runs


Identify the construction laydown areas, parking
lots, construction buildings and ware house
Identify the prefabricated buildings
Identify space for equipment maintenance
Roads and Tracks for both permanent facilities
and construction period
Identify the plant security (fence, gates, guard
house
Identify the drainage and run off basins

Plant Arrangements- Power Block

Identify the major plant levels (Ground floor,


mezzanine, main operating floor)
Plant North and True north direction
Graphical scale
Identify the column rows lines with dimension
Vertical bracing lines to be identified
Identify the all equipment and space for future
equipment (if any)
Identify the maintenance and dismantling
requirements

Plant Arrangements- Power Block(contd.)

Identify the nearest facilities


Identify the HAVC requirements
Identify the Turbine room crane travel limits to
cater all equipment
Identify the access to turbine carne control
cabinet
Identify the noise generating equipment and their
placement
Identify the Turbine generator foundation
Identify the main steam, reheat and low pressure
steam piping
Reserve the space for CW piping
Reserve the area for turbine gland steam and
lube oil piping

Plant Arrangements- Power Block(contd.)

General access galleries stairways and doors per


local codes
Permanent Elevators and construction elevators(
if any)
Identify the mat foundation and individual footing
foundation
Identify the control room, electrical equipment
room, UPS room
Identify the Toilets, locker room, office area
Control room of HAVC equipment
Generator bus duct and potential transformer
cubicles
Reserve the area for the cable tray
Oil and Process water drainage

LAYOUTS FOR OIL INSTALLATIONS

Based on OISD-STD-118 Rev 1


Class A Petroleum : Liquids which have
flash point below 23 deg C
Class B Petroleum : Liquids which have
flash point of 23 deg C and above but below
65 deg C
Class C Petroleum : Liquids which have
flash point of 65 deg C and above but below
93 deg C

LAYOUTS FOR OIL INSTALLATIONS

PLOT PLAN
Salalah Power System Privatization Project

GT AREA LAYOUT
Salalah Power System Privatization Project

DYKE AREA
Salalah Power System Privatization Project

FUEL OIL PUMP HOUSE


Salalah Power System Privatization Project

COOLING TOWER AREA


Haldia CCPP

CW PUMP HOUSE
Haldia CCPP

DEARATOR AREA
Haldia CCPP

STATION BUILDING
Haldia CCPP

STATION BUILDING
Haldia CCPP

STATION BUILDING
Haldia CCPP

STATION BUILDING
Haldia CCPP

POWER BLOCK
XIAMEN COMBINED CYCLE PLANT

PLOT PLAN
XIAMEN COMBINED CYCLE PLANT

POWER BLOCK
XIAMEN COMBINED CYCLE PLANT

POWER BLOCK
XIAMEN COMBINED CYCLE PLANT

POWER BLOCK
XIAMEN COMBINED CYCLE PLANT