Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
ON
TEAMWORK
ACKNOWLEDGEMENT
Project Supervisor
Prof. Dr.- Ing. Ramesh Kumar Maskey
Department of Civil and Geomatics Engineering
Project co-supervisor
Dr. Hari Prasad Neopane
Associate Prof. & EnPe-MPPOES
Department of Mechanical Engineering
Project Co-ordinator
Mr. Anup K.C.
Department of Mechanical Engineering
Project overview
Background
Objectives
Ultra low head(ULH) turbine : Introduction
Scope of work
Methodology
Operational principle
Work accomplished
Problem faced
Conclusion
BACKGROUND
Hydropower
Status of Nepal
Project concern
Sites of
possibility
OBJECTIVES
Applicable in
even natural or
man-made
rivers and
canals with
little or no
water storage
capacity
Reaction
principle
METHODOLOGY
Literature review
Consultation
Site visit
Model preparation
Web search
Panauti canal
First model
(discharge
measurement and Second model
posibility of
Third model
applicationn)
Books
Model testing
Test at irrigation canal
nearby roshi khola
(panauti)
CONTD..
Counteracting force due to
acceleration
F = (2 1 )
(22 12 )
2
2 1
Q= flow rate
v2=(d1/d2)v1
v2= downstream velocity
V1= upstream velocity
= (1 2 ) (2 1 ) 2
(1 2 )
WORKS ACCOMPLISHED
Visit to Rossi khola Canal
CONTD..
Third Model
Second Model
First Model
Fig :Successful modification of our model
Second Model
o Deviation corrected by putting hub in
it and blades attached to it
o Expected to test it in front of Fluid
Mechanics Lab and assembly for
testing was done
o But not tested
Testing of model :
Consultation with Associate. Prof. Dr.
Dimitar Kisliakov ,Dept. of Hydraulic
engg,Bulgaria about design parameter.
Inability to test due to the problem of:
1. Presence of side plate that block
water passage.
2. Inaccurate ratio of blade and the hub
3. Also, leakage problem
CONTD..
Third Model:
o Small model was prepared with some design considerations
o Both hub and blades made up of PVC pipe
o Slots was made on hub to attach blades to increase strength
o Sealing done by M-seal
o Geometric specifications:
Consists of 8 curved blades with a preferred angle of 20
degrees.
The blade depth, T = 10.6 cm
The hub diameter, D =15.24 cm
The projected blade length (L) parallel to the axis of hub
=23 cm [to maintain the relation (L<2D) ]
CONTD..
Also following assumptions are to be made while testing it
Hub diameter = 1.2 to 1.25 times head
difference (to reduce the turbulence losses
during blade entry upstream)
d2= blade depth T but not less than 0.7 T (to
make significant efficiency)
The projected blade length parallel to hub axis
not less than 0.7 times the canal width to allow
water from sides.
pump
THEN
Planning of fabrication of
own canal for the purpose
of testing (in the canal
nearby Roshi khola )
CANAL SEPCIFICATION
Use of wooden plank.
Width of base of the canal= 35 cm
Height of the side planks of the canal= 42 cm
Length of each wooden planks= 220 cm
TURBINE HUB
TEST SETUP
SIDEWAYS LOSS BLOCKAGE
INTAKE WATER
LEVEL
TURBINE BLADE
OUTLET WATER
LEVEL
SHAFT
BEARING
No torque measureent
(due to difficulty in
arrangement in natural
flowing canal)
Data analysis
v2
d1
Fp
Fa
Po
Pi
efficiency
0.14
0.07
0.016
12.8
5.2
5.0
11.00
45.14
0.70
0.15
0.08
0.017
14.4
6.4
5.6
13.47
41.81
0.75
0.16
0.09
0.018
16.0
7.7
6.2
16.15
38.48
0.79
0.17
0.10
0.019
17.5
9.1
6.7
19.07
35.15
0.84
0.18
0.11
0.021
19.0
10.6
7.1
22.20
31.82
0.89
0.19
0.12
0.022
20.4
12.2
7.3
25.56
28.49
0.93
0.2
0.13
0.023
21.7
13.9
7.3
29.15
25.16
0.98
0.21
0.14
0.024
23.0
15.7
7.2
32.96
21.83
Po
1.03
0.22
0.15
0.025
24.3
17.6
6.8
36.99
18.50
gHQ
= 39.71 Nm
output power
0.65
8.000
7.000
6.000
5.000
4.000
3.000
2.000
1.000
0.000
5.6
6.2
6.7
7.1
7.3
7.3
7.2
6.8
Problems Faced
Very few source of
information
Insufficient discharge at the
planned cannel to test
Solutions
Design of own canal
selecting the testing site.
Testing at the irrigation
canal near Roshi khola
GANTT CHART
S.N
1.
2.
3.
4.
5.
6.
7.
8.
Activity
Concept
development
Literature review
Model preparation
for testing
Site Selection for
testing
Progress
report
and
midterm
presentation
Material
collection and test
rig preparation
Testing of the
model and data
analysis
Final
Presentation
March
April
May
June
July
THANK
YOU