Sei sulla pagina 1di 60

Chapter 15

Resource Planning

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Material Requirements Planning


Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed to produce a product MRP provides time scheduling information specifying when each of the materials, parts, and components should be ordered or produced Dependent demand drives MRP It is most valuable in industries where a number of products are made in batches using the same productive equipment. The theme of MRP is getting the right materials to the right place at the right time.

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Demand Patterns
2000
2000 1500 Bicycles 1500

1000

Rims

1000

500

500

| 1

| | 5 Day

| 10 (b)

| 1

| | 5 Day

| 10

(a) Figure 15.2

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Demand Patterns
2000
2000 1500 Bicycles 1500

1000

Rims Reorder point | | | | | | | | 5 10 Day

1000

500

500

| 1

0
(b)

| 1

| | 5 Day

| 10

(a) Figure 15.2

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Demand Patterns
2000
2000 1500 Bicycles Order 1000 on day 3 Rims Reorder point | | | | | | | | 5 10 Day (b)
To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

1500

1000

1000

500

500

0 (a)

| 1

| 1

| | 5 Day

| 10

Demand Patterns
2000
2000 1500 Bicycles Order 1000 on day 3 Rims Reorder point | | | | | | | | 5 10 Day (b)
To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

1500

1000

1000

500

500

0 (a)

| 1

| 1

| | 5 Day

| 10

Demand Patterns
2000
2000 1500 Bicycles Order 1000 on day 3

Order 1000 on day 8


Rims

1500

1000

1000

500
Reorder point | | | | | | | | 5 10 Day

500

0 (a)

| 1

0
(b)

| 1

| | 5 Day

| 10

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Demand Patterns
2000
2000 1500 Bicycles Order 1000 on day 3

Order 1000 on day 8


Rims

1500

1000

1000

500
Reorder point | | | | | | | | 5 10 Day

500

0 (a)

| 1

0
(b)

| 1

| | 5 Day

| 10

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Demand Patterns
2000
2000 1500 Bicycles Order 1000 on day 3

Order 1000 on day 8


Rims

1500

1000

1000

500
Reorder point | | | | | | | | 5 10 Day

500

0 (a)

| 1

0
(b)

| 1

| | 5 Day

| 10

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Material Requirements Plan Inputs

Bills of materials

Engineering and process designs

Figure 15.4
To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Material Requirements Plan Inputs


Authorized master production schedule
Other sources of demand

Bills of materials

Engineering and process designs

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Material Requirements Plan Inputs


Authorized master production schedule
Other sources of demand

Inventory transactions

Inventory records

Bills of materials

Engineering and process designs

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Material Requirements Plan Explosion


Authorized master production schedule
Other sources of demand

Inventory transactions

Inventory records

MRP explosion

Bills of materials

Engineering and process designs

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Material Requirements Plan Output


Authorized master production schedule
Other sources of demand

Inventory transactions

Inventory records

MRP explosion

Bills of materials

Engineering and process designs

Material requirements plan

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Bill of Materials (BOM)


Indicates all the raw materials, components, subassemblies, and assemblies required to produce an item A structured list of all components, parts, and materials of an item Shows way a finished product or parent item is put together from individual components

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Bill of Materials
Back slats Seat cushion

Leg supports

Seat-frame boards

Back legs

Front legs

A Ladder-back chair

Figure 15.5
To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Bill of Materials
A Ladder-back chair

B (1) Ladder-back subassembly

C (1) Seat subassembly

Back slats

D (2) Front legs

Seat cushion

E (4) Leg supports

Leg supports
F (2) Back legs G (4) Back slats H (1) Seat frame I (1) Seat cushion

Seat-frame boards

Back legs

Front legs
J (4) Seat-frame boards

A Ladder-back chair

Figure 15.5
To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Master Production Schedule


Based on actual customer orders and predicted demand Indicates when each ordered item will be produced Time-phased plan specifying how many and when the firm plans to build each end item

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Master Production Schedule


April
1 2 3 4 5 6 150 120 200 200 200 120 200

May
7 8

Ladder-back chair
Kitchen chair Desk chair Aggregate production plan for chair family

150

670

670

Figure 15.6
To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Inventory Record
Detailed information regarding the quantity of each item, on hand, on order committed to use in various time periods MRP system using inventory master file to determine the quantity available for use in a given period If sufficient items are not available, the system includes the item on the planned order release report
To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Inventory Record
Item: C Description: Seat subassembly Week 1 Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 150 2 0 3 0 4 120 5 0 6 150 7 120

Figure 15.11
Lot Size: 230 units Lead Time: 2 weeks

8 0

230

37

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Inventory Record
Item: C Description: Seat subassembly Week 1 Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 150 2 0 3 0 4 120 5 0 6 150 7 120 8 0 Lot Size: 230 units Lead Time: 2 weeks

230

37

Explanation: Gross requirements are the total demand for the two chairs. Projected on-hand inventory in week 1 is 37 + 230 150
To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Inventory Record
Item: C Description: Seat subassembly Week 1 Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 150 2 0 3 0 4 120 5 0 6 150 7 120 8 0 Lot Size: 230 units Lead Time: 2 weeks

230

37

117

Explanation: Gross requirements are the total demand for the two chairs. Projected on-hand inventory in week 1 is 37 + 230 150 = 117 units.
To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Inventory Record
Item: C Description: Seat subassembly Week 1 Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 150 2 0 3 0 4 120 5 0 6 150 7 120 8 0 Lot Size: 230 units Lead Time: 2 weeks

230

37

117

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Inventory Record
Item: C Description: Seat subassembly Week 1 Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts 150 2 0 3 0 4 120 5 0 6 150 7 120 8 0 Lot Size: 230 units Lead Time: 2 weeks

230

37

117

Projected on-hand inventory balance Planned order releases at end of week t

Inventory on hand at end of week t - 1

Scheduled or planned receipts in week t

Gross requirements in week t

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Inventory Record
Item: C Description: Seat subassembly Week 1 Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts 150 2 0 3 0 4 120 5 0 6 150 7 120 8 0 Lot Size: 230 units Lead Time: 2 weeks

230

37

117

117

117

153

273

273

Projected on-hand inventory balance Planned order releases at end of week t

Inventory on hand at end of week t - 1

Scheduled or planned receipts in week t

Gross requirements in week t

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Planned Orders
Explanation: Item: C Description: Seat subassembly Without a new order in week 4, there will be a shortage of three units: 117 + 0 + 0 120 = 3 units. 1 2
Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 150 0 Lot Size: 230 units Lead Time: 2 weeks Week 3 0 4 120 5 0 6 150 7 120 8 0

230

37

117

117

117

153

273

273

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Planned Orders
Item: C Description: Seat subassembly Week 1 Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 150 2 0 3 0 4 120 5 0 6 150 7 120 8 0 Lot Size: 230 units Lead Time: 2 weeks

230

37

117

117

117

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Planned Orders
Explanation: Item: C Description: Seat subassembly Adding the planned receipt brings the balance to 117 + 0 + 230 120 = 227 units.
1 Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 150 2 0 3 0 4 120 Lot Size: 230 units Lead Time: 2 weeks Week 5 0 6 150 7 120 8 0

230

37

117

117

117

227

230

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Planned Orders
Explanation: Item: C Description: Seat subassembly Adding the planned receipt brings the balance to 117 + 0 + 230 120 = 227 units.
1 Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 150 2 0 3 0 4 120 Lot Size: 230 units Lead Time: 2 weeks Week 5 0 6 150 7 120 8 0

230

37

117

117

117

227

230

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Planned Orders
Explanation: Item: C Description: subassembly Offsetting for Seat a two-week lead time puts the corresponding planned order release back to week 2.
1 Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 230 150 2 0 3 0 4 120 Lot Size: 230 units Lead Time: 2 weeks Week 5 0 6 150 7 120 8 0

230

37

117

117

117

227

230

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Planned Orders
Explanation: Item: C Description: subassembly Offsetting for Seat a two-week lead time puts the corresponding planned order release back to week 2.
1 Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 230 150 2 0 3 0 4 120 Lot Size: 230 units Lead Time: 2 weeks Week 5 0 6 150 7 120 8 0

230

37

117

117

117

227

230

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Planned Orders
Explanation: Item: C Seat order subassembly TheDescription: first planned lasts until week 7, when projected inventory would drop to 43.
1 Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 230 150 2 0 3 0 4 120 Lot Size: 230 units Lead Time: 2 weeks Week 5 0 6 150 7 120 8 0

230

37

117

117

117

227

227

77

43

230

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Planned Orders
Explanation: Item: C Description: Seat subassembly Adding the second planned receipt brings the balance to 77 + 0 + 230 120 = 187.
1 Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 230 150 2 0 3 0 4 120 Lot Size: 230 units Lead Time: 2 weeks Week 5 0 6 150 7 120 8 0

230

37

117

117

117

227

227

77

230

230

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Planned Orders
Explanation: Item: C Description: Seat subassembly Adding the second planned receipt brings the balance to 77 + 0 + 230 120 = 187.
1 Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 230 150 2 0 3 0 4 120 Lot Size: 230 units Lead Time: 2 weeks Week 5 0 6 150 7 120 8 0

230

37

117

117

117

227

227

77

187

230

230

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Planned Orders
Explanation: Item: C Seat subassembly TheDescription: corresponding planned order release is for week 5.
1 Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 230 150 2 0 3 0 4 120 Lot Size: 230 units Lead Time: 2 weeks Week 5 0 6 150 7 120 8 0

230

37

117

117

117

227

227

77

187

230

230

230

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Planned Orders
Item: C Description: Seat subassembly Week 1 Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 230 150 2 0 3 0 4 120 5 0 6 150 7 120 8 0 Lot Size: 230 units Lead Time: 2 weeks

230

37

117

117

117

227

227

77

187

187

230

230

230

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Additional MRP Scheduling Terminology


Gross Requirements-total requirements for a component or end product Scheduled receipts-when a purchase or product order that has already been placed will be available Planned order release-how many and when to produce to meet gross requirements
To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Lot Sizing in MRP Programs


Lot-for-lot (L4L) (producing as much as required) Fixed order quantity (ordering same quantity each time an order is issued) Periodic order quantity (allows a different order quantity for each order issued, but tends to issue the order at predetermined time intervals such as every two weeks) Economic order quantity (EOQ)
To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Lot-Sizing Rule Comparison



The FOQ rule generates high average inventory because it creates remnants. The POQ rule reduces average on-hand inventory because it does a better job of matching order quantity to requirements.

The L4L rule minimizes inventory investment but maximizes the number of orders placed.
To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

MRP Outputs
MRP explosion

Figure 15.16
To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

MRP Outputs
MRP explosion

Material requirements plan


Action notices Releasing new orders Adjusting due dates Priority reports Dispatch lists Supplier schedules Capacity reports Capacity requirements planning Finite capacity scheduling Input-output control

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

MRP Outputs
MRP explosion

Material requirements plan


Action notices Releasing new orders Adjusting due dates
Routings and time standards

Priority reports Dispatch lists Supplier schedules

Capacity reports Capacity requirements planning Finite capacity scheduling Input-output control

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

MRP Outputs
MRP explosion

Material requirements plan


Action notices Releasing new orders Adjusting due dates
Routings and time standards

Priority reports Dispatch lists Supplier schedules

Capacity reports Capacity requirements planning Finite capacity scheduling Input-output control

Manufacturing resources plan


Performance reports

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

MRP Outputs
MRP explosion

Material requirements plan


Action notices Releasing new orders Adjusting due dates
Routings and time standards

Priority reports Dispatch lists Supplier schedules

Capacity reports Capacity requirements planning Finite capacity scheduling Input-output control

Manufacturing resources plan


Performance reports Cost and price data

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

MRP Explosion
Item: Seat subassembly Lot size: 230 units Week Lead time: 2 weeks Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 230 1 150 2 0 3 0 4 120 5 0 6 150 7 120 8 0

230

37

117

117

117

227

227

77

187

187

230

230

230

Figure 15.18
To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

MRP Explosion
Item: Seat subassembly Lot size: 230 units Week Lead time: 2 weeks 1 150 2 0 3 0 4 120 5 0 6 150 7 120 8 0

Gross requirements
Planned receipts Planned order releases

230

230

230

230

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

MRP Explosion
Item: Seat subassembly Lot size: 230 units Week Lead time: 2 weeks 1 150 2 0 3 0 4 120 5 0 6 150 7 120 8 0

Gross requirements
Planned receipts Planned order releases

230

230

230

230

Item: Seat frames Lot size: 300 units Week Lead time: 1 week Gross requirements Scheduled receipts Projected on-hand 40 inventory Planned receipts Planned order releases 1 2 3 4 5 6 7 8

Item: Seat cushion Lot size: L4L Week Lead time: 1 week Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 1 2 3 4 5 6 7 8

300

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

MRP Explosion
Item: Seat subassembly Lot size: 230 units Week Lead time: 2 weeks 1 150 2 0 3 0 4 120 5 0 6 150 7 120 8 0

Gross requirements
Planned receipts Planned order releases

230

230

230

230

Usage quantity: 1
Item: Seat frames Lot size: 300 units Week Lead time: 1 week Gross requirements Scheduled receipts Projected on-hand 40 inventory Planned receipts Planned order releases 1 0 2 230 3 4 5 6 7 8 Lead time: 1 week Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 1 0 2 230 3 Item: Seat cushion Lot size: L4L

Usage quantity: 1

Week 4 5 6 7 8

300

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

MRP Explosion
Item: Seat subassembly Lot size: 230 units Week Lead time: 2 weeks 1 150 2 0 3 0 4 120 5 0 6 150 7 120 8 0

Gross requirements
Planned receipts Planned order releases

230

230

230

230

Usage quantity: 1
Item: Seat frames Lot size: 300 units Week Lead time: 1 week Gross requirements Scheduled receipts Projected on-hand 40 inventory Planned receipts Planned order releases 1 0 2 230 3 0 4 0 5 230 6 7 8 Lead time: 1 week Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 1 0 2 230 3 0 Item: Seat cushion Lot size: L4L

Usage quantity: 1

Week 4 0 5 230 6 7 8

300

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

MRP Explosion
Item: Seat subassembly Lot size: 230 units Week Lead time: 2 weeks 1 150 2 0 3 0 4 120 5 0 6 150 7 120 8 0

Gross requirements
Planned receipts Planned order releases

230

230

230

230

Item: Seat frames Lot size: 300 units Week Lead time: 1 week Gross requirements Scheduled receipts Projected on-hand 40 inventory Planned receipts Planned order releases 300 1 0 2 230 3 0 4 0 5 230 6 0 7 0 8 0

Item: Seat cushion Lot size: L4L Week Lead time: 1 week Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 230 1 0 2 230 3 0 4 0 5 230 6 0 7 0 8 0

300

40

110

110

110

180

180

180

180

300

230

230

230

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

MRP Explosion
Item: Seat frames Lot size: 300 units Week Lead time: 1 week Gross requirements Planned receipts Planned order releases 300 1 0 2 230 3 0 4 0 5 230 6 0 7 0 8 0 300

Item: Seat cushion Lot size: L4L Week Lead time: 1 week Gross requirements Planned receipts Planned order releases 230 1 0 2 230 3 0 4 0 5 230 6 0 7 0 8 0

230

230

230

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

MRP Explosion
Item: Seat frames Lot size: 300 units Week Lead time: 1 week Gross requirements Planned receipts Planned order releases 300 1 0 2 230 3 0 4 0 5 230 6 0 7 0 8 0 300

Item: Seat cushion Lot size: L4L Week Lead time: 1 week Gross requirements Planned receipts Planned order releases 230 1 0 2 230 3 0 4 0 5 230 6 0 7 0 8 0

230

230

230

Item: Seat-frame boards Lot size: 1500 units Week Lead time: 1 week Gross requirements Scheduled receipts Projected on-hand 200 inventory Planned receipts Planned order releases 1 2 3 4 5 6 7 8

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

MRP Explosion
Item: Seat frames Lot size: 300 units Week Lead time: 1 week Gross requirements Planned receipts Planned order releases 300 1 0 2 230 3 0 4 0 5 230 6 0 7 0 8 0 300

Item: Seat cushion Lot size: L4L Week Lead time: 1 week Gross requirements Planned receipts Planned order releases 230 1 0 2 230 3 0 4 0 5 230 6 0 7 0 8 0

230

230

230

Usage quantity: 4
Item: Seat-frame boards Lot size: 1500 units Week Lead time: 1 week Gross requirements Scheduled receipts Projected on-hand 200 inventory Planned receipts Planned order releases 1 0 2 0 3 0 4 1200 5 0 6 0 7 0 8 0

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

MRP Explosion
Item: Seat frames Lot size: 300 units Week Lead time: 1 week Gross requirements Planned receipts Planned order releases 300 1 0 2 230 3 0 4 0 5 230 6 0 7 0 8 0 300

Item: Seat cushion Lot size: L4L Week Lead time: 1 week Gross requirements Planned receipts Planned order releases 230 1 0 2 230 3 0 4 0 5 230 6 0 7 0 8 0

230

230

230

Item: Seat-frame boards Lot size: 1500 units Week Lead time: 1 week Gross requirements Scheduled receipts Projected on-hand 200 inventory Planned receipts Planned order releases 1500 1 0 2 0 3 0 4 1200 5 0 6 0 7 0 8 0

200

200

200

500

500

500

500

500

1500

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Solved Problem 1
A LT = 1 B (3) LT = 2 D (1) LT = 3 E (2) LT = 6 F (1) LT = 1 G (1)
Figure 15.21

C (1) LT = 3 D (1) LT = 3

LT = 3
To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Solved Problem 2
B (1)
Table 12.1

A LT = 2 C (2) LT = 2 D (1)
D FOQ = 500 units 3 weeks None 425

LT = 1
Inventory Record Data

DATA CATEGORY Lot-sizing rule Lead time Scheduled receipts Beginning (on-hand) inventory

B POQ (P=3) 1 week None 20

ITEM C
L4L 2 weeks 200 (week 1) 0

LT = 3

Figure 15.22
To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Solved Problem 2
Item: B Description: Week 1 Gross requirements Scheduled receipts Projected on-hand 20 inventory Planned receipts Planned order releases 280 2 100 3 4 200 5 6 120 7 180 8 60 9 10 Lot size: POQ (P = 3) Lead time: 1 week

20

200

200

240

60

280

360

360

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Solved Problem 2
Item: C Description: Week 1 Gross requirements Scheduled receipts Projected on-hand 0 inventory Planned receipts Planned order releases 400 2 200 3 4 400 5 6 240 7 360 8 120 9 10 Lot size: L4L Lead time: 2 weeks

200

200

400

240

360

120

240

360

120

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Solved Problem 2
Item: D Description: Week 1 Gross requirements Scheduled receipts Projected on-hand 425 inventory Planned receipts Planned order releases 500 500 2 400 3 4 240 5 360 6 120 7 8 9 10 Lot size: FOQ = 500 units Lead time: 3 weeks

425

25

25

285

425

305

305

305

360

305

500

500

To Accompany Ritzman & Krajewski Foundations of Operations Management, 2003 Prentice Hall, Inc. All rights reserved.

Potrebbero piacerti anche