An overview of Formwork systems used for High rise building at L&T Omkar site

Presented By Vijay Bhilwade Roll No : 134047002

CONTENT
1. Project Overview. 2. Formwork. 3. Requirements of good Formwork. 4. Why ACS and Mivan 4. Mivan 4 days cycle. 5. Automatic Climbing system (ACS) operation.

D
72 Floors

C
61 Floors

B
61 Floors

A
53 Floors

1. Project Overview
M i

Mi

AC S
M i

M i
Mi

Tower D

Mi

AC S
Mi

Tower C

Mi

Mi

Tower A
Mi

AC Mi S
Mi Mi

AC S
Mi

Tower B

2.FORMWORK
Formwork system is the key factor determining the success of a project in terms of

Speed
Quality Safety Cost Sustainability

3.REQUIREMENTS OF GOOD FORMWORK


Quick , Easy and Precise formwork alignment. Flawless concrete surface finish. Maximum adaptation. Optimum work force. Integrated safety Economical

4. Why ACS and MIVAN ?

February 6, 2014

5. MIVAN :FOUR DAY CYCLE


Day 1: erection of vertical reinforcement bars and one side of the vertical formwork Day 2: erection of the second side of the vertical formwork and formwork for the slab Day 3: fixing reinforcement bars for slabs and casting of walls and slabs Day 4: removal of vertical form work panels after

24hours, props after 7 days, floor slab formwork after 2.5


days
8

February 6, 2014

February 6, 2014

10

February 6, 2014

11

February 6, 2014

12

5. ACS CLIMBING OPERATION

5. ACS CLIMBING STAGE

5.ACS CLIMBING STAGE

February 6, 2014

5.ACS CLIMBING STAGE ( Explained)


Stage 1:Tying of reinforcement, fixing of climbing cone, fixing of wall shutter and concreting Stage 2: Fixing of climbing cone at 1st level and fixing shoe, lifting wall panel with all 1st level assembly by towercrane, tying of reinforcement, fixing of wall shutter, casting Stage 3: Deshuttering of wall panel, fixing shoe on

climbing cone at 2nd level


Stage 4: Fixing of hydraulic pump at 1st level.
16

February 6, 2014

ACS CLIMBING STAGE : CONTD


Stage 5: Climbing the wall panel by hydraulic pump. Fixing all the second level assembly of ACS. Tying of reinforcement/fixing of cone/wall shuttering/concreting.

Stage 6: Deshutteing panel/fixing shoes of 3rd level.


Stage 7: Climbing the wall. Tying the

reinforcement/fixing of cone/wall
shuttering/concreting.
17

References.
1.www.mivan.com 2.www.doka.com 3.www.lntecc.com