Presentation outline
Overview of Plant Controls Functions of ATRS Structure of ATRS
24 December 2013
PMI Revision 00
MAN-MACHINEINTERFACE
OPERATOR
PLANT
24 December 2013 3
BOILER
TURBINE
GENERATOR
24 December 2013
MEASUREMENT
MONITORING
CLOSE-LOOP CONTROL
OPEN-LOOP CONTROL
PROTECTION
24 December 2013 5
ADVANTAGES OF AUTOMATION
OPERATING PERSONNEL FREED FROM ROUTINE TASKS. INCORRECT INTERVENTIONS IN THE PROCESS AVOIDED. STRESS ON EQUIPMENT REDUCED. PLANT OPERATIONS GEARED FOR MAXIMUM EFFICIENCY. INCIPIENT FAULTS RECOGNISED QUICKLY. ON FAULT OCCURRENCE, IMMEDIATE AND LOGICAL INTERVENTION POSSIBLE.
24 December 2013
PMI Revision 00
A.
CONTROL SYSTEM:
ANALOG (CLOSE LOOP) - ELECTROHYDRAULIC CONTROLLER (EHC)
- TURBINE STRESS EVALUATOR (TSE) - LOW PRESSURE BYPASS CONTROLLER (LPBPC) - GLAND STEAM PRESSURE CONTROLLER (GSPC)
BINARY (OPEN LOOP) - AUTOMATIC TURBINE RUN UP SYSTEM (ATRS) - AUTOMATIC TURBINE TESTER (ATT)
B.
C.
PROTECTION SYSTEM
7
24 December 2013
HIERARCHY OF CONTROL
SUB-GROUP CONTRL-1
SUB-GROUP CONTRL-2
CONTROL INTERFACE
LOGS
CONTROL ROOM
UNIT CONTROL
AUTOMATION
CLOSED LOOP
FUNCTIONAL GROUP
PROTIVE
EQUIPMENT
CONTROL
SIGNAL CONDITIONING ALALOG, BINARY
CONTROL
LOGICS
ANNUNCIATION
PLANT INTERFACE EQUIPMENT
PLANT (FIELD)
SIGNAL TRANSMITTER 24 December 2013
DRIVES
PMI Revision 00 9
FEATURES :
BASED ON FUNCTIONAL GROUP CONTROL PHILOSOPHY EACH FUNCTIONAL GROUP ORGANISED AND ARRANGED IN SUB-GROUP CONTROL, SUB-LOOP CONTROL, AND CONTROL INTERFACE OPERATING MODES AVAILABLE: - MANUAL MODE ( OPERATOR GUIDE) - AUTOMATIC MODE - STEP BY STEP MODE
24 December 2013
PMI Revision 00
10
ATRS STRUCTURE
OIL SYSTEM, VACUUM SYSTEM, TURBINE etc.
GC
SGC SLC
24 December 2013
SGC SLC
PMI Revision 00
SGC
SLC CI
CI
11
GROUP CONTROL: Decides WHEN, HOW MANY & WHICH SGC shall be operating and stopped. SUB GROUP CONTROL: Contains the sequential logics for switching drives ON and OFF. Perform sequence in STEPS, issue commands and get Checkbacks. SUB LOOP CONTROL: can be switched ON & OFF manually. Receive commands from GC, SGC and also Manual CONTROL INTERFACE: Standard Interface between the command transmitters and receivers in the plant, undertakes all necessary signal processing and monitoring.
ADVANTAGES OF ATRS
ELIMINATES HUMAN ERROR PROVIDES MAXIMUM PROTECTION AGAINST MALFUNCTIONS OPERATORS TASK LESS ARDUOUS ENABLES SAFE, SMOOTH, STRESS CONSISTANT AND OPTIMUM WARM-UP, ROLLING AND SYNCHRONISATION OF TURBINE IN LEAST POSSIBLE TIME INCREASES PLANT AVAILABILITY REDUCES STARTING TIME WITHOUT IMPAIRING LIFE MEETS EMERGENCIES AUTOMATICALLY ALL PLANT OPERATING CONDITIONS CATERED TO BY CRITERIA DEPENDANT PROGRAMMING INCREASED OPERATING FLEXIBILITY, SAFETY AND RELIABILITY
24 December 2013
PMI Revision 00
13
ATRS
24 December 2013
PMI Revision 00
14
STEP 01
START DRIVE A
DRIVE A ON
& MONITOR & BLOCKING TIME
STEP 02
OPEN DMPR A
24 December 2013
PMI Revision 00
15
SGC executes commands to bring the equipment upto a particular defined status. The commands are executed in a predefined sequence in the form of steps. Desired number of criteria act as preconditions before the SGC can take off or execute its defined sequence. The functional group continues to function automatically all the time demanding enabling criteria based on the process requirements and from other FGs, if required. In case the desired criteria is not available, the system would automatically act in such a manner as to ensure the safety of the main equipment. The sequence is programmed in the processor. The process signals are acquired through the input modules and are available on the bus.
24 December 2013 PMI Revision 00 16
Waiting Time : It implies that the subsequent step will not be executed unless the specified time elapses. If no waiting time is specified, the next step gets executed as soon as the enabling criteria are fulfilled. Monitoring Time : It is the time required for executing the command of any step as well as the time required for appearance of criteria for the next step. Under healthy conditions it should happen within the specified time, otherwise an alarm is initiated. Whenever there is uncertainty regarding the time required for completing a particular task, such as warming-up, pulling vacuum etc., the monitoring time is blocked.
24 December 2013
PMI Revision 00
17
&
BYPASS CRITERION
EXAMPLE
1
&
02
PROGRAM LOOP
WAIT
50s
MO TIME
20s
COMMAND
1 2
&
STEP 2 ( START UP PROGRAM) WITH 2 STEP CRITERIA, 2 COMMAND OUTPUTS AND A MONITORING & WAITING TIME . WITH ADDITIONAL PROGRAM LOOP CONTROL AND A BYPASS CRITERIA FOR STEP 1 WAITING OR MO TIME CAN BE PROGRAMMED FOR 0.1 SEC TO 999 MIN. NOS. 1-49 USED FOR START-UP, PMI Revision 00 51 TO 99 FOR SHUTDOWN PROGRAM.
24 December 2013
18
ATRS can be switched on at any stage after completing certain tasks manually, if so desired. In such cases, the SGC program quickly scans through the steps and starts executing from the stage upto which the tasks have been completed manually. This is achieved by incorporating suitable overflow /bypass conditions in the logic.
24 December 2013
PMI Revision 00
19
1. ATRS is organised in the following four Sub-Groups : Oil supply Evacuation Turbine HP CONTROL FLUID
2. SGC issues commands either to the SLC or directly to the drive through the Control Interface.
3. Each of these SGCs has its subordinate SLCs and CI modules. These SGCs in conjunction with the turbine governing system , TSE and the auto-synchroniser accomplish the function of start-up of the TG set.
24 December 2013
PMI Revision 00
20
24 December 2013
PMI Revision 00
21
24 December 2013
PMI Revision 00
22
24 December 2013
PMI Revision 00
23
1. SGC-TURBINE :
Sub-loop Control (SLC) Drains. Warm up Controller. Starting Device of turbine governing system. Speed & Load Setpoint devices of turbine governing system. Auto-synchroniser.
24 December 2013 PMI Revision 00 24
Sub-loop control (SLC) turning gear. SLC auxiliary oil pump 1. SLC auxiliary oil pump 2. SLC emergency oil pump. SLC jacking oil pump.
24 December 2013
PMI Revision 00
25
Sub-loop Control (SLC) condensate extraction pumps. Starting ejector, if provided. Main ejectors / vacuum pumps (as applicable). Vacuum breaker.
24 December 2013
PMI Revision 00
26
Sub-loop Control (SLC) HPCF SLC HPCF pumps HPCF pumps HPCF re-circulation pumps LPCF temp control valve
24 December 2013
PMI Revision 00
27
24 December 2013
LP WATER INJECTION
AUTOMATIC SYNCHRONIZER
MANUAL OPEN/CLOSE
MANUAL ON/OFF
DRAIN VALVES
29
SGC-DISPLAY
4 6 8 7 5
1. PUSHBUTTON SHUTDOWN 2.PUSHBUTTON STARTUP OR OPERATION 3.PUSHBUTTON AUTOMATIC ON/OFF 4.LAMP SHUTDOWN PROGRAM 5.LAMP STARTUP OR OPERATION PROGRAM 6.LAMP AUTOMATIC OFF 7.LAMP AUTOMATIC ON 8.LAMP FAULT
24 December 2013 PMI Revision 00 30
SLC-DISPLAY
2 3 4
1
1. PUSHBUTTON MANUAL ON/OFF 2.LAMP SLC OFF 3.LAMP FAULT 4.LAMP SLC ON
24 December 2013 PMI Revision 00 31
DRIVE INTERFACE-DISPLAY
3 4 5
1. PUSHBUTTON OFF (CLOSE) 2. PUSHBUTTON ON (OPEN) 3. LAMP OFF (CLOSE) 4. LAMP FAULT 5. LAMP ON (OPEN)
24 December 2013 PMI Revision 00 32
1
NAAANN 1MAJ15
2
AANNN AP001
3
AANN XB01
SIGNAL IDENTIFICATION
CONSECUTIVE NO. OF EQUIPMENT
TYPE OF EQUIPMENT NO. OF SUBGROUP PLANT GROUP (FUNCTIONAL GROUP) NO. OF UNIT
24 December 2013
PMI Revision 00
33
24 December 2013
PMI Revision 00
35
24 December 2013
PMI Revision 00
36
HYDRAULIC
ELECTRICAL
EXTENDED
PROT. CRITERIA
TRIP SYSTEM
- OVER SPEED TRIP DEVICE 1/2 - VACUUM TRIP DEVICE - HAND TRIP LEVER(LOCAL) 1/2
TRIP SYSTEM
- MANUAL REMOTE TRIP ( UCB) - LOW VACUUM TRIP - LOW LUBE OIL - FIRE PROT. TRIP -BRG METAL TEMP -AXIAL SHIFT -HP/IP TOP/BOT DIFF TEMP HI
TURBINE PROT.
- LP EXH. STM. TEMP. > MAX
24 December 2013
PMI Revision 00
37
24 December 2013
PMI Revision 00
38
24 December 2013
PMI Revision 00
39
24 December 2013
PMI Revision 00
40
24 December 2013
PMI Revision 00
41
24 December 2013
PMI Revision 00
42
i)
Fire protection switch, either in unit control room or in machine hall, operated. ii) Level in main oil tank falls to a very low value, indicating substantial leakage of oil from the system.
The command signal under condition (ii) is initiated from three level transmitters in 2-out-of-3 logic cofiguration.
24 December 2013 PMI Revision 00 43
24 December 2013
PMI Revision 00
44
6. TRIP COMMAND INITIATED FROM ATRS : The protection acts when the trip command signal is initiated from the Automatic Turbine Run-up System .
24 December 2013
PMI Revision 00
45
24 December 2013
PMI Revision 00
46
THANK YOU