Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
CEM 571
BUILDING
LESSON OUTCOME
At the end of lectures, student will be able to : Identify setting out works involve in building construction, i.e., site clearing, setting out and establish the building datum level. (CO1:PO2)
identify the accommodations, storage and security requirements during the building construction stage. (CO1:PO2) describe the detail building stages involved during the building construction process. (CO1:PO2)
BUILDING
Any man-made structure used or intended for supporting or sheltering any use or continuous occupancy.
1.
2. 3.
CONSTRUCTION SITE
A building or construction site can be considered as a temporary factory employing the necessary resources to successfully fulfill a contract.
Contractors responsibility after being given possession and site layout plan and detail drawings necessary Commencing tasks:a.
b. c.
Construction documents
ARCHITECT DRAWING ENGINEERS DRAWING SCHEDULES/ PLANNING
SPECIFICATION
BILL OF QUANTITIES
CONTRACT DOCUMENT
CONSTRUCTION PROCESS
SITE INVESTIGATION SETTING OUT AND TEMPORARY WORKS TEMPORARY WORKS (ACCOMMODATION, STORAGE AND SECURITY) DETAIL CONSTRUCTION STAGES
HANDOVER
SITE INVESTIGATION
Soil investigation include the following:a) Land surveying Boundaries determination and set up Establishing a datum level (TBM)
May involve:
Removal of soil to reduce levels following to Building Regulation C1 (sterilize the top 300 mm to contain plant life and decaying vegetation)
Earthwork operation
Establish a base line from which the whole of the building can be set out.
Marked on site clearly so that it can be re-established at any time Using steel tape (30 meters and not stretchable is more suitable) Marked each corner with a stout peg Check on the right angle and correct lengths (advisable using different method)
a) SITE BOUNDARY
The surveyor must to determine the site boundary of the construction area to avoid trespass to the another construction area.
b) LEVELING
The land surveyor will determine the original ground level for the land and mark a survey peg for drain, pipes, cables and main sewerage treatment plant (MSTP), also the road complying with the Jabatan Pengairan dan Saliran (JPS).
2.0
Should set up clear of the foundations trench positions to locate the trench, foundations and walls Required at all trench and wall intersections
All levels in a building are taken from a fixed point called a datum Should establish after the setting out and related to ordnance benchmark
Principles of levelling
Sloping Sites
Three methods in reducing levels:1. Cut and Fill - usual method, the amount of cut will equal the amount of fill 2. Cut Advantages of having undisturbed soil over the site, but having disadvantages of cost of removing the spoil from the site 3. Fill Not to be recommended, deep foundation would be needed, the risk of settlement and the amount of fill should be limited to 600 mm
Sloping sites
Accommodation
Regulations 1996 (Health, safety and welfare) Requirements defers due to numbers of site workers and duration of contract
units
caravans or cabins
Facilities provided: First aid, stretcher ambulance, first aid room, shelter and clothing, meals room, washing facilities and sanitary facilities
Semi-portable Units
Storage
Examples.. Cement and plaster (in bag form) dry store free from moist air Aggregates and sand clean firm base, separate different materials and grade, watch on moisture content Bricks and blocks stacked in stable piles, covered adequately
To defines limit of site and acts as a deterrent to trespasser or thief To provide a physical barrier or visual barrier Should start at the beginning of construction Type depend on degree of security, cost, neighborhood and duration of contract At least 1.8m high Minimum number of access and with lockable barrier Standard fences BS 1722
Protection fencing
Hoardings
hoardings
series of closed boarded panels securely fixed to resist wind load and accidental impact load be free standing or fixed by stays by the external walls of an existing building
Can
Fan
hoardings
protect persons from falling objects
To
Place
at a level above the normal traffic height and ensure any falling debris is directed back towards the building or scaffold
BUILDING STAGES
Order of construction Excavation and timbering Foundations Concrete floors Reinforced concrete frames Roofs Brickwork Internal fixtures and fittings Insulation Plumbing and wiring Painting and decorating
Before a foundation can be laid, it is necessary to excavate a trench of the required depth and width (by hand or mechanical excavator)
Timbering term used to cover temporary supports to the sides of excavations and is sometimes called planking and strutting
Type and amount depend on the depth, nature of subsoil, weather conditions and duration
Trench excavation
FOUNDATIONS
Foundation is the base on which a building rests and its purpose is to safely transfer the load of a building to suitable subsoil Building regulations : Safely
sustain and submit to the ground the combined dead and imposed loads so as not to imposed any settlement or other movement in any part of the building or of any adjoining buildings or works Be a such a depth, or be so constructed, as to avoid any damage by swelling, shrinkage or freezing of the subsoil Be capable of resisting attack by deleterious material, such as sulphates, in the subsoil
Foundation
Shallow foundations transfer loads to subsoil at a point near to the ground floor of the buildingpad footing, strip, rafts , combinations.. Deep foundations transfer the loads to a subsoil some distance below the ground floor of the building..pile foundations
PROBLEM
Underground
water Pipe line.electrical, water, sewerage, drainage Sink hole Ground settlement
CONSTRUCTION FOUNDATION
BEAM
A beam is a structural element that is capable of withstanding load primarily by resisting bending. The bending force induced into the material of the beam as a result of the external load, own weight and external reactions to these loads is called a bending moment (wikipedia). Beam can be:
Suspended Non
suspended..cantiliver @ on ground.
BEAM.
SLAB
A broad flat square or rectangular piece of wood, stone or other solid material used to construct buildings, pavements, patios, paths in horizontal plane Can be suspended or non suspended Method of construction depends on type of materials used
SLAB
COLUMN
A column in structural engineering is a vertical structural element that transmits, through compression, the weight of the structure above to other structural elements below. For the purpose of wind or earthquake engineering, columns may be designed to resist lateral forces
COLUMN
WALL
A wall is a usually solid structure that defines and sometimes protects an area. Most commonly, a wall delineates a building and supports its superstructure, separates space in buildings into rooms, or protects or delineates a space in the open air.
There are three principal types of structural walls: building walls, exterior boundary walls, and retaining walls.
WALL
BRICKWORK
ROOF
A roof is the covering on the uppermost part of a building. A roof protects the building and its contents from the effects of weather. Structures that require roofs range from a letter box to a cathedral or stadium, dwellings being the most numerous . The elements in the design of a roof are : the the the
ROOF CONSTRUCTION.
Types of roof
Flat Roofs
Types of roof
Sloping Roofs
Types of roof
Gable Roofs
Types of roof
Salt Box
Types of roof
Gambrel Roof
Types of roof
Mansard Roof
Types of roof
Pyramid Roof
Types of roof
Hip Roof
END OF LECTURE
ANY QUESTIONS ..
the setting out works involve in building construction, i.e., site clearing, setting out and establish the building datum level. (CO1) the accommodations, storage and security requirements during the building construction stage. (CO1)
describe the detail building stages involved during the building construction process. (CO1)
END..
THANK YOU