Sei sulla pagina 1di 75

CONSTRUCTION TECHNOLOGY

CEM 571

CHAPTER 2 STAGES FOR CONSTRUCTION


1. 2. 3. 4. Building Retaining walls, Drainage Road, Highway, Bridges Airports, Offshore/Marine structure

BUILDING

LESSON OUTCOME
At the end of lectures, student will be able to : Identify setting out works involve in building construction, i.e., site clearing, setting out and establish the building datum level. (CO1:PO2)

identify the accommodations, storage and security requirements during the building construction stage. (CO1:PO2) describe the detail building stages involved during the building construction process. (CO1:PO2)

BUILDING
Any man-made structure used or intended for supporting or sheltering any use or continuous occupancy.
1.
2. 3.

Site works and setting out


Accommodation, storage and security Detail building stages

CONSTRUCTION SITE
A building or construction site can be considered as a temporary factory employing the necessary resources to successfully fulfill a contract.

1. SITE WORKS AND SETTING OUT

Contractors responsibility after being given possession and site layout plan and detail drawings necessary Commencing tasks:a.
b. c.

Clearing the site


Setting out the building Establishing a datum level

Construction documents
ARCHITECT DRAWING ENGINEERS DRAWING SCHEDULES/ PLANNING

SPECIFICATION

BILL OF QUANTITIES

CONTRACT DOCUMENT

CONSTRUCTION PROCESS
SITE INVESTIGATION SETTING OUT AND TEMPORARY WORKS TEMPORARY WORKS (ACCOMMODATION, STORAGE AND SECURITY) DETAIL CONSTRUCTION STAGES

HANDOVER

SITE INVESTIGATION
Soil investigation include the following:a) Land surveying Boundaries determination and set up Establishing a datum level (TBM)

b) Assessment and testing Sampling of media such as soil, water or air.


c) Availability of materials and basic supply Construction materials Available road and drainage systems Electrical and water supply Environments

Clearing the Site

May involve:

Demolition of existing buildings (by experienced contractor)


Grubbing out bushes and trees (by manual or mechanical means, or by specialist for the large trees)

Removal of soil to reduce levels following to Building Regulation C1 (sterilize the top 300 mm to contain plant life and decaying vegetation)

Topography of the site and some common material on site

Removal of tree trunks

Grubbing of trees, shrubs and roots

Site clearing work carried out

Excavator heaping up top soil

Earthwork operation

Setting Out the Site


1.

Establish a base line from which the whole of the building can be set out.

Marked on site clearly so that it can be re-established at any time Using steel tape (30 meters and not stretchable is more suitable) Marked each corner with a stout peg Check on the right angle and correct lengths (advisable using different method)

Setting out & setting boundary

a) SITE BOUNDARY
The surveyor must to determine the site boundary of the construction area to avoid trespass to the another construction area.

The boundary had determine

b) LEVELING
The land surveyor will determine the original ground level for the land and mark a survey peg for drain, pipes, cables and main sewerage treatment plant (MSTP), also the road complying with the Jabatan Pengairan dan Saliran (JPS).

Land surveyor determine the OGL

Setting Out the Site


2.

2.0

Set up profile board-after the main building lines

Should set up clear of the foundations trench positions to locate the trench, foundations and walls Required at all trench and wall intersections

Typical profile board

Establishing a Datum Level


All levels in a building are taken from a fixed point called a datum Should establish after the setting out and related to ordnance benchmark

An arrow with a horizontal mark above the arrow


The centerline of the horizontal being the actual level indicated on an ordnance survey maps

Principles of levelling

Rise and fall method:


Staff reading at A = 2.500 m Staff reading at B = 0.750 m

Ground level at A = 100 m above ordinance datum (AOD)


Level at B = 100 m + rise ( fall if declining) Level at B = 100 m + (2.500 0.750) = 101.750 m.

Alternative height of collimation (HC) method:

HC at A = Reduced level (RL) + staff reading

= 100 m + 2.500 = 102.500 (AOD)


Level at B = HC at A staff reading at B = 102.500 0.750 = 101.750 m

Sloping Sites
Three methods in reducing levels:1. Cut and Fill - usual method, the amount of cut will equal the amount of fill 2. Cut Advantages of having undisturbed soil over the site, but having disadvantages of cost of removing the spoil from the site 3. Fill Not to be recommended, deep foundation would be needed, the risk of settlement and the amount of fill should be limited to 600 mm

Sloping sites

Accommodation, Storage and Security

SITE OFFICE HOARDING PROJECT SIGNBOARD

Accommodation
Regulations 1996 (Health, safety and welfare) Requirements defers due to numbers of site workers and duration of contract

Staff accommodations usually: semi-portable mobile

units

caravans or cabins

Facilities provided: First aid, stretcher ambulance, first aid room, shelter and clothing, meals room, washing facilities and sanitary facilities

Semi-portable Units

Mobile Caravans Or Cabins

Storage

Type of storage depend on:

Durability Vulnerability to damage Vulnerability to theft

Examples.. Cement and plaster (in bag form) dry store free from moist air Aggregates and sand clean firm base, separate different materials and grade, watch on moisture content Bricks and blocks stacked in stable piles, covered adequately

Security and Protectionfencing


To defines limit of site and acts as a deterrent to trespasser or thief To provide a physical barrier or visual barrier Should start at the beginning of construction Type depend on degree of security, cost, neighborhood and duration of contract At least 1.8m high Minimum number of access and with lockable barrier Standard fences BS 1722

Protection fencing

Typical fencing details Cleft chestnut pale fencing

Chain link fence with concrete posts

Close boarded fence with concrete post

Security and Protectionfencing- Hoardings

Close boarded fences of barriers erected adjacent to a highway or public footpath


Prevent unauthorized persons obtaining access to site and protect public from dust and noise Necessary to obtain written permission from the local authority to erect a hoarding (Highways Act 1980)

Hoardings

Two forms: Vertical


a

hoardings

series of closed boarded panels securely fixed to resist wind load and accidental impact load be free standing or fixed by stays by the external walls of an existing building

Can

Fan

hoardings
protect persons from falling objects

To

Place

at a level above the normal traffic height and ensure any falling debris is directed back towards the building or scaffold

Typical free standing vertical hoarding

Typical fan hoarding

BUILDING STAGES
Order of construction Excavation and timbering Foundations Concrete floors Reinforced concrete frames Roofs Brickwork Internal fixtures and fittings Insulation Plumbing and wiring Painting and decorating

Excavation and Timbering

Before a foundation can be laid, it is necessary to excavate a trench of the required depth and width (by hand or mechanical excavator)

Timbering term used to cover temporary supports to the sides of excavations and is sometimes called planking and strutting

Type and amount depend on the depth, nature of subsoil, weather conditions and duration

Typical example of trench excavations

Trench excavation

FOUNDATIONS

Foundation is the base on which a building rests and its purpose is to safely transfer the load of a building to suitable subsoil Building regulations : Safely

sustain and submit to the ground the combined dead and imposed loads so as not to imposed any settlement or other movement in any part of the building or of any adjoining buildings or works Be a such a depth, or be so constructed, as to avoid any damage by swelling, shrinkage or freezing of the subsoil Be capable of resisting attack by deleterious material, such as sulphates, in the subsoil

Foundation

Shallow foundations transfer loads to subsoil at a point near to the ground floor of the buildingpad footing, strip, rafts , combinations.. Deep foundations transfer the loads to a subsoil some distance below the ground floor of the building..pile foundations

PROBLEM
Underground

water Pipe line.electrical, water, sewerage, drainage Sink hole Ground settlement

CONSTRUCTION FOUNDATION

BEAM

A beam is a structural element that is capable of withstanding load primarily by resisting bending. The bending force induced into the material of the beam as a result of the external load, own weight and external reactions to these loads is called a bending moment (wikipedia). Beam can be:
Suspended Non

beamsimply @ fixed support.

suspended..cantiliver @ on ground.

Method of construction depends on type of materials used.

BEAM.

SLAB

A broad flat square or rectangular piece of wood, stone or other solid material used to construct buildings, pavements, patios, paths in horizontal plane Can be suspended or non suspended Method of construction depends on type of materials used

SLAB

COLUMN

A column in structural engineering is a vertical structural element that transmits, through compression, the weight of the structure above to other structural elements below. For the purpose of wind or earthquake engineering, columns may be designed to resist lateral forces

COLUMN

WALL

A wall is a usually solid structure that defines and sometimes protects an area. Most commonly, a wall delineates a building and supports its superstructure, separates space in buildings into rooms, or protects or delineates a space in the open air.

There are three principal types of structural walls: building walls, exterior boundary walls, and retaining walls.

WALL

BRICKWORK

ROOF

A roof is the covering on the uppermost part of a building. A roof protects the building and its contents from the effects of weather. Structures that require roofs range from a letter box to a cathedral or stadium, dwellings being the most numerous . The elements in the design of a roof are : the the the

material construction durability

ROOF CONSTRUCTION.

Types of roof

Flat Roofs

Types of roof

Sloping Roofs

Types of roof

Gable Roofs

Types of roof

Salt Box

Types of roof

Gambrel Roof

Types of roof

Mansard Roof

Types of roof

Pyramid Roof

Types of roof

Hip Roof

END OF LECTURE

ANY QUESTIONS ..

CAN YOU IDENTIFY AND BRIEFLY EXPLAIN.

the setting out works involve in building construction, i.e., site clearing, setting out and establish the building datum level. (CO1) the accommodations, storage and security requirements during the building construction stage. (CO1)

describe the detail building stages involved during the building construction process. (CO1)

END..

THANK YOU

Potrebbero piacerti anche