Sei sulla pagina 1di 18

SCHEDULING & SEQUENCING BY JOHNSONS RULE

GROUP MEMBERS Rajendra kumar Pratik Puneet Pintu

DEFINATION

Establishing the timing of the use of equipment, facilities and human activities in an organization Effective scheduling can produce:1) Cost savings
2) Increases in productivity

Scheduling Difficulties

Variability in

Setup times Processing times Interruptions Changes in the set of jobs

No method for identifying optimal schedule Scheduling is not an exact science Ongoing task for a manager

Minimizing Scheduling Difficulties


Set realistic due dates Focus on bottleneck operations

Consider lot dividing of large jobs

SEQUENCING

JOHNSONS RULE

SEQUENCING

Sequencing: Determine the order in which jobs at a work center will be processed. Workstation: An area where one person works, usually with special equipment, on a specialized job. Priority rules: Simple hierarchy used to select the order in which jobs will be processed. Job time: Time needed for setup and processing of a job.
Everything is #1 Priority

Priority Rules

FCFS - first come, first served

LTR - Least time required


LAR/LOR Least activity required/Fewest operations required EDD - earliest due date
Top Priority

CRS - critical ratio scheduling

JOHNSONS RULE
Technique for minimizing completion time for a group of jobs to be processed on two machines or at two work centers.

Minimizes total idle time

Several conditions must be satisfied

Johnsons Rule Conditions


Job time must be known and constant Job times must be independent of sequence Jobs must follow same two-step sequence Job priorities cannot be used All units must be completed at the first work center before moving to second

Example Of Johnsons Rule (Two Machines)


Job No. A B C D E F G H I J
Time on M1
Time on M2

MC1
St. Time End Time

MC2
St. Time End Time

Sequence

15 17 9 12 14 12 12 13 15 13

11 10 13 15 14 10 14 15 14 13

0 15 15 32 32 41 41 53 53 67 67 79 79 91 91 104 104 119 119 132

15 26 32 42 42 55 55 70 70 84 84 94 94 108 108 123 123 137 137 150

C G D H E I J A B F

Sequence
(By Johnson's Rule)

MC1
St. Time End Time

MC2
St. Time End Time

C G D H E I J A B F

0 9 9 21 21 33 33 46 46 60 60 75 75 88 88 103 103 120 120 132

9 22 22 36 36 51 51 66 66 80 80 94 94 107 107 118 120 130 132 140

So we can say that by using Johnsons rule of scheduling Time saved in this case is :150 140 = 10

Johnsons Rule for Three Machines

Condition:-Largest time on M2 should be less than or equal to smallest time on M1 or M2 or both. If condition satisfied then we calculate:R1 = M1 + M2 R2 = M2 + M3 This whole can be understand by the help of following example:-

Job No. A B C D E F G H TOTAL

Time on M1

Time on M2

Time on M3

MC1
St. Time End Time

MC2
St. Time End Time

16 15 12 13 14 15 13 12

12 11 10 9 11 10 9 12 84

11 12 13 15 17 16 14 17 115

0 16 16 31 31 43 43 56 56 70 70 85 85 98 98 110

16 31 43 56 70 85 98 110

28 42 53 65 81 95 107 122

MC3
St. Time End Time

R1
M1+M2

R2
M2+M3

SEQUENCE
(BY JOHNSON'S RULE)

28 42 54 67 82 99 115 129

39 54 67 82 99 115 129 146

28 26 22 22 25 25 22 24

23 23 23 24 28 26 23 29

C G D H F E A B

Idle time on Machine-2 is:122 84 = 38 Idle time on machine-3 is:146 115 = 31

SEQUENCE
(BY JOHNSON'S RULE)

MC1
St. Time End Time

MC2
St. Time End Time

MC3
St. Time End Time

C G D H F E A B

0 12 12 25 25 38 38 50 50 65 65 79 79 95 95 110

12 22 22 25 34 35 38 47 49 50 62 64 65 75 81 79 90 97 95 107 114 110 121 125

35 49 64 81 97 114 125 137

Total time saved by Using Johnsons rule Is:146 137 = 06

CONCLUSION
Thus we can say that by using Johnsons rule we can do more better sequencing of machines and can save the time of production.

Potrebbero piacerti anche