Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
EXCAVATION
EMBANKMENT
Broad Categories
Earthmoving Equipments Hauling Equipment Mix production plants Mix Laying Equipments Compaction Equipment Accessories
LAYER
RAW MATERIAL
MAJOR EQUIPMENTS
WMM/WBM
BM/DBM/BC
Prime Coat / Tack Coat
GSB Production
For natural GSB no blending required In some cases, materials from different sources may be blended to achieve desired properties (drainage & strength) The blending of raw materials to produce GSB can be done at stock yard using Excavator/Wheel Loader In some cases a Pug-mill is used to achieve desired mix properties
WMM Production
At the bottom of each bin there is a gate for controlling material flow and a feeder unit for metering the flow The aggregate in right proportion is carried to the mixer, by conveyor belt
Feeding of Bins
Option 1 : Direct Feeding A ramp is provided up to brim of bins, which is used by dumpers/wheel loaders to feed the bin Option 2: An extra bin is provided at Ground level, where the dumper/wheel loader empties aggregate, and then the aggregate is taken to the right bin, through a radial conveyor
Water Supply
Continuous Water Supply is ensured by installing Water tank & Pump A Bore-well may be required for ground water source Water Flow meter with Sensor to control flow
Pug mill
A pug mill is a machine in which materials are simultaneously ground and mixed with a liquid A typical pugmill consists of a horizontal boxlike chamber with a top inlet and a bottom discharge at the other end, 2 shafts with opposing paddles, and a drive assembly To achieve uniform mixing, a pugmills live zone should be completely filled with mix
Discharge System
Discharge system is not required if Pug mill is placed at sufficient height However, in most cases, the mix from pug mill is taken by a Load out Belt conveyor to a storage silo This ensures continuous operation The trucks are fed from under the storage silo
Salient Features
Capacity 100-200 TPH Hire Charge Rs. 1-2 lakh / month Autometic / Semi-autometic / Mechanical Leading Brand : Local Manufacturers
Asphalt Production
An asphalt plant is a high-tech group of equipment which is capable of uniformly blending, heating, and mixing the aggregates and binder, while at the same time meeting strict environmental regulations Two types of plants are in use: Batch Heater & Drum Mix. Drum Mix plants are most common now.
Conveyors
2 sets of Belt Conveyors are used for feeding aggregates into the drum & carrying mix to storage silo Additionally Radial conveyor may be used to fill bins Conveyors are equipped with load cells for continuous monitoring of weight, and limit switch for emergency switch offs Conveyors are the parts of the plant susceptible to maximum Wear & Tear
Dust Collectors
Because of air pollution requirements, asphalt plants are equipped with dust control systems
The two most commonly utilized systems are the water venturi approach & the cloth filtration baghouse system
The wet approach does require the availability of adequate water supplies
It introduces water at the point where dust laden gas moves through the narrow throat of a venturi-shaped chamber The dust becomes entrapped in the water and is thereby separated from the exhaust gas
The dry baghouse systems allow mechanical collection and recycling of fines
The system works by forcing the dust laden gas through fabric filter bags which hang in a baghouse The dust falls into hoppers in the bottom of the baghouse and is moved by augers to a discharge vane feeder
Storage silo
Since drum plants produce a continuous flow of asphalt , the output must be stored in silos Upright cylindrical structures, silos, fed at the top by a drag flight conveyor, and discharge to transport trucks through bottom dump Sealed/Filled with inert gas to prevent hardening & ageing of mix Drop control methods to avoid segregation Insulated to retain heat
Operator Cabin
Asphalt plants today are all electronically controlled A fully automatic control cabin with AC/DC control panel, on board electric power console, distribution, switch board, is provided for controlling the quantity and quality of production with operator sitting in A/c comfort. In addition to controlling pant operations, this facilitates controlling mix recipes, checking quality parameters, storing and printing data, monitoring health of plant, and identifying problems if any.
Salient Features
Capacity 100-500 TPH Needs DG back up of >500 kVA Acquisition Cost Rs. 50-200 Crores Hire Charge Rs. 10-30 lakhs/month Leading Brand MARINI
If the existing pavement is structurally weak, it is completely dismantled by ripping or milling and reconstructed
Ripping
Dismantling of existing pavement can be done by a Tractor Ripper or an Excavator The ripping action is similar to plowing, using a stronger ripper The method in recent times has been completely replaced by milling
Milling
Milling (also called grinding or cold planing) can be used to dismantle/smoothen an existing pavement Rather than filling in low spots, as a leveling course does, milling removes the high points in an existing pavement to produce a relatively smooth surface The basic components of a milling machine are
a cutting drum to mill the existing pavement a vacuum to collect the milled particles a conveyance system to transport the milled particles to a dump truck for hauling
Advantages of Milling
Eliminates the need for complicated leveling courses and problems with quantity estimates for irregular leveling course thicknesses used to fill existing pavement depressions. Provides RAP for recycling operations. Allows efficient removal of deteriorated flexible pavement material that is unsuitable for retention in the pavement structure. Provides a highly skid resistant surface suitable for temporary use by traffic until the final surface can be placed. Allows curb and gutter lines to be maintained or reestablished before flexible overlays. Provides an efficient removal technique for material near overhead structures in order to maintain clearances for bridge structures, traffic signals and overhead utilities.
Salient Features
Cut Width 75mm to 4.5m Cut Depth Up to 250mm per pass Production Rate 100-200 tons/hr Material Size after milling 95% passing the 50mm sieve Acquisition Cost Rs. 2-3 Crore Hire Charge Rs. 6-8 lakhs Diesel Consumption 20 ltrs/hr Leading Brand - WIRTGEN
Mechanical Broomer
A Brush, made of metal wire & nylon bristles, is fixed to the rear of a tractor, and towed on the road A debris hopper is attached with main frame in front of bush, with lever-controlled unloading mechanism Hire Charge Rs. 1000015000 / month Diesel Consumption 2 ltrs/hr
Tractor Compressor
Jet of compressed air is also often used for road cleaning A tractor compressor is used to supply compressed air to clean the underlying layer Hire Charge Rs. 1500020000 / month Diesel Consumption 4 ltrs/hr
Bitumen Sprayer
These trucks must be able to apply the liquid asphalt to a surface at uniform rates They have insulated tanks for maintaining material temperature and are equipped with burners for heating the asphalt material to the proper application temperature Discharge pumps are used to maintain continuous and uniform pressure for the full length of the spray bar The nozzle angle must be set properly, usually 15 - 30 from the horizontal axis of the spray bar so that the individual spray fans do not interfere or intermix with one another The height of the nozzle above the surface determines the width of an individual fan To ensure the proper lap of the fans, the nozzle (spray bar) height must be set and maintained
Bitumen Sprayer
The factors which affect uniform application are:
The asphalt spraying temperature The liquid pressure across the spray bar length The angle of the spray nozzles The nozzle height above the surface The distributor speed
The relationship between the application rate and the truck speed is obvious; truck speed must be held constant during the spraying to achieve a uniform application Hire Charge Rs. 40000-80000 /month Diesel Consumption 8 ltrs/hr
Laying of WMM
Laying of WMM can be done either by a Motor Grade, a Mechanical Paver, or a Sensor Paver
Parameter Rate of Progress Hire Charge Quality, Line Level Motor Grader 1 1 3 Mechanical Paver 2 2 2 Sensor Paver 3 3 1
Material Wastage
Laying Of Asphalt
Asphalt is laid using a Sensor Paver The sensor paver ensures the line, level, and quality of mix The mix is loaded in the front hopper, carried to the rear by set of flight feeders, spread out by a set of augurs, and leveled by a screed.
Parts of Paver
Consists of a Tractor Unit & a Screed Tractor (Material Feed System)
Push Roller & Truck Hitch Hopper Conveyor Augur
Screed
Screed Plate; Strike-off plate; Screed Arms; Depth crank; Screed Heater; Screed Vibrator; Screed Extension
Hopper
Pavers can receive mix directly into their hoppers from rear dump or flow bottom trucks The hopper is used as a temporary storage area for HMA delivered by the transport vehicle Hopper sides (or wings) can be tilted up (or folded) to force material to the middle where it is carried to the rear by the conveyor system Hoppers can also be fit with inserts to allow them to carry more mix
Conveyor
The conveyor mechanism carries the mix from the hopper, under the chassis and engine, then to the augers The amount of HMA carried back by the conveyors is regulated by either variable speed conveyors and augers or flow gates, which can be raised or lowered by the operator or, more often, by an automatic feed control system
Augur
The auger receives HMA from the conveyor and spreads it out evenly over the width to be paved There is one auger for each side of the paver and they can be operated independently
Windrow Elevator
Paving operation is often affected by delay in truck loads. This cause undulation in the mat Windrow elevators were developed to address transfer and truck queuing effects on mat quality The flight system of the elevator continuously lifts the mix into the hopper from the windrow If queuing delays individual trucks, the effect to paving speed is limited or nonexistent because the windrow storage allows the paver to continue moving
Screed
The most critical feature of the paver is the self-leveling screed unit, which determines the profile of the HMA being placed The floating screed is free to pivot about its pin connections. This pinconnected tow arm arrangement allows the screed to be self-leveling and gives it the ability to compensate for base surface irregularities
Screed
Screed Plate The flat bottom portion of the screed assembly that flattens and compresses the
Screed Angle -
The vertical plate just above the leading edge of the screed used to strike off excess HMA and protect the screeds leading edge from excessive wear Long beams that attach the screed to the tractor unit
Depth crank -
The manual control device used to set screed angle and ultimately, mat thickness
Screed Vibrator -
Device located within the screed used to increase the screeds compaction effort.
Screed
Since the screed is free floating it will slide across the HMA at an angle and height that will place these six forces in equilibrium When all the forces acting on the screed are constant, it will ride at a constant elevation above the grade or follow the stringline When any one of these forces is changed, the screed angle and elevation will change (which will change the mat thickness) to bring these forces back into equilibrium In typical paving operations the screed angle is manually adjusted to control mat thickness, using a thickness control screw or depth crank
Speed of Paver
Paver speed affects mat thickness by changing the screed angle If a paver speeds up and all other forces on the screed remain constant, the screed angle decreases to restore equilibrium, which decreases mat thickness, and vice versa.
Salient Feature
Capacity > 500 TPH, Restricted by capacity of plant Width Basic width is 2.5m. Can be extended up to 9m Diesel Consumption 7-10 ltrs/day Acquisition Cost Rs. 1-2 Crores Hire Charge Rs. 1-5 lakhs/month Leading Brand VOGELE, BITELLI, INGERSOLRAND
Compaction of Asphalt
Because of the relationships between pavement air voids and mechanical stability, durability and water permeability, asphalt pavements are designed based on the mix being placed at a specified density Four basic type of equipments are available for compaction of asphalt mix
The Paver Screed Smooth Drum Steel Wheel Roller (static) Smooth Drum Steel Wheel Roller (vibratory) Pneumatic Tire Roller
Paver Screed
The screed takes the head of HMA from the material delivery system, strikes it off at the correct thickness and provides initial mat compaction Screed compaction depends upon screed weight, frequency and amplitude of Screed Vibrator Approximately 75 to 85 percent of the theoretical maximum density of the HMA will be obtained when the mix passes out from under the screed
Increase in vibratory amplitude increases compactive effort, but it can fracture aggregate particles. Better solution is to maintain low amplitude vibration, and increase no. of passes.
Salient Features
Weight ranges from 1 MT (mini) to 20 MT Diesel Consumption 5-15 ltrs/day Acquisition Cost Rs. 7-50 lakhs Hire Charge Rs. 0.4-2 lakhs/month Leading Brand L&T CASE, BOMAG
Salient Features
Weight is > 20 MT Diesel Consumption 10-12 ltrs/day Acquisition Cost Rs. 25-30 lakhs Hire Charge Rs. 1-2 lakhs/month Leading Brand BITELLI, INGERSOLRAND
Rolling steps
Compaction of an asphalt mat is usually viewed in terms of three distinct steps:
Breakdown Intermediate Finish
Sometimes density cannot be achieved by a single roller within the time duration available
In that case an intermediate rolling step is required to supplement the breakdown step in reaching the required density
Steel wheel rollers are used for finish rolling Pneumatic rollers are multipurpose and can be used for breakdown and intermediate rolling The vibratory steel wheel-type rollers are usually the roller of choice for breakdown and intermediate rolling because of their adaptability to a range of mixes and differences in mat thickness
Roller capability for a project must match the net roller speed with the average paver speed It must be remembered that increased roller speed simply reduces compactive effort, so speed alone cannot be used to compensate for increased production
Other Equipments
Dumper Trucks Mix Transportation Tele-Light Mast Night Paving Tractor/Truck Transporting Tools & Tackles Water Tanker Conveyance Vehicle Power Generator Plant Wheel Loader Operations Weigh Bridge
Critical Issues
Minimizing Downtime Right Usage Regular maintenance to reduce breakdown Idling of costlier resource due to shortage of cheap resource Availability of spare parts After sales service
Problem
You are required to do the equipment planning for a four laning project of an existing 2 lane highway in the state of Maharashtra. Length of Project 50kms Duration 30 months Complete dismantling & reconstruction of existing road is required Existing road asphalt thickness 150mm New pavement: 150mm DBM, 50mm BC There is one central camp and plant For how many months you need to mobilize a 100 tph milling machine What capacity of asphalt plant you shall propose How many dumpers for transportation of asphalt and milled material What average paver speed will match the plant production Considering 2m wide drum with 10% overlap, & 3 passes for compaction, how many rollers are required Assume 80% productivity & 16 working hours per day