Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
INTRODUCTION
Water is absolutely necessary for life. Water is essential not only for survival of human beings, but also for plants & animals & all other living beings. Water is extremely useful to man in providing him with luxurious & comforts, in addition to fulfilling his basic necessities of life. However many of our villages are still suffering from adequate amenities specially the water supply. Besides providing water for drinking purpose it is also essential to supply water treated confirming to the requirements of potable water .
NECESSITY:
Yellur village is located at 11 km from Belgaum city. The village is not provided with proper and sustained water supply. Presently water is supplied through mini water supply scheme by bore wells. This system has been found to be insufficient due to increase population, dearth of available water and lack of proper management. This water must be treated properly; there is chances of water contamination due to presences of high fluoride and nitrate contents.
In order to ensure the availability of sufficient quantity of good quality of water, it becomes almost imperative in this present scenario of acute water storage, to plan & build suitable water supply scheme, which many provide potable water to meet the demand & requirement. Hence proper planning is necessary in this formulation & implementation of water supply scheme.
The growing population, unreliable monsoon & wasteful usage pattern has lead to wide spread scarcity of water. Hence it is being realized that mammoth efforts are needed to maximize the use of natural resources. The existing water supply is not sufficient to meet the basic needs of the people and hence people are more dependent on the ground water resources. This inconvenience of water can be avoided by constructing an efficient water supply scheme for the
SOURCES:
Rainfall is the main source of water for the village. The average rainfall is about 860.72 mm; there is an existing water supply scheme as well as mini water supply scheme with 21 bore wells and 8 open wells.
POPULATION FORECASTING:
Population:- The number of human beings residing in a certain area at any particular time.
Population density:- Number of persons per unit area. The water supply project is not designed for present population, but it is made to accommodate the future population at the end of 2 or 3 decades.
POPULATION FORECAST
There are mainly 3 methods of population forecasting and they are as follows : Arithmetical increase method Geometrical increase method Incremental increase method
1. 2. 3.
AIRTHMETICAL INCREASE METHOD:This is the simplest method. Generally gives lower results. In this method,the increase in population from decade to decade is assumed constant. It is analogous to simple interest method.
Pn = Po+nX
Pn=future population at the end of n decade Po = present population, X =Average population increase /decade
Average population increase /decade X = Total increase / Number of decades = 1187. 5 Population = P2011+ X x n Where n = Number of decades from 2011 P2013 = 13004 P2023 = 14192 P2033 = 16567
GEOMETRICAL INCREASE METHOD:In this method it is assumed that percentage increase in population from decade to decade is constant. It gives much higher values,hence it is suitable for growing towns & cities. This method is analogous to the compound interest method. Pn = P x ( 1 + r/100 )^n P =present population r = % growth rate n = no. of decades
r=11.13%
Population = P2011 x ( 1 + r/100 ) n
INCREMENTAL INCREASE METHOD:It combines both the airtmetic and geometrical average method. In this method decade growth rate is not assumed to be constant . The increment in increase for each decade is found from these. An average increment of the increases is found.
Pn=P+nX+{ n(n+1)/2 }Y
Year of census
Population
Increase/deca de
Incremental increase
8017 9612 10818 534 1415 1595 1206 534 1415 0.2 0.13 0.05 0.12 -389 -672 881
Summation
X=4750/4=118 7.5
Y=-180/3=-60
WATER DEMAND:
A small quantity of water is required per capita under normal condition but demand for other purpose will naturally depend on the standard of living and degree of culture.
1. 2. 3.
The various demands are as follows: Domestic Purpose. Civil or Public Purpose. Losses and wastes.
DOMESTIC:
The following demands may be considered as domestic demands. Drinking Cooking Bathing Washing of utensils etc Household and sanitary purpose Washing of clothes
70 LPCD: FOR SURFACE WATER SOURCE. 50 LPCD: FOR GROUND WATER SOURCE
JACK WELL : This is a structure constructed over suction well or suction sump for pumping raw water from the surface source to treatment units. Normally, the size of the sump shall be equal to 30 minutes of pumping capacity. Jack well with pump house is generally constructed with R.C.C as per site condition.
OVERHEAD STORAGE TANK: Overhead tanks are placed on the highest point of the proposed site location to avoid pumping and make use of available elevation in order to enable water supply under the action of gravity. Here R.C.C tank structure is been proposed.
For a given discharge , if smaller diameter of pipes are selected the velocity of flow increases resulting in higher frictional loss and hence increases the total pumping head, which requires increased HP of pump effecting in net increase of cost. If the diameter of the pipe selected is large then the pumping cost reduces but the initial cost of pipe increases. For the most economical condition we must choose such a pipe size whose pumping and initial costs will make the total annual expenditure minimum. Such size is called economical size of the pipe. The optimum velocity for most economical sizes of pipes is likely to be about 1m/sec.
DATA :
Design population for 2030 Per Capita Demand Value of HWC Losses considered Raw water demand(lpd) No of hour of Pumping Discharge (lps) Length of rising main Pump setting level Full supply level Efficiency of pump
:16567 : 70 : 145 : 20 % :1391628 :12 Hour : 5.11 : 260M : 805.5M : 858.025M : 60%
Velocity V = Q / A = 5.11 x 10-3 / (3.1416 x 0.10142 /4) = 0.63 m/sec Using Hazen Williams formula, V = 0.854 x C x R 0.63 S 0.54 0.63 = 0.854 x 145 x (0.1014/4) 0.63 S 0.54 Solving, S = 0.004145 m / m Frictional loss = S x L = 0.005535 x 345 = 1.43 m Losses in bends, specials etc = 10 % of frictional loss = 0.10 x 1.43 = 0.143 m Static head = FSL pump setting level = 858.025 805.5= 52.525m Total head = H = 37+ 1.43 + 0.143 = 54.098m BHP @ 60% efficiency = w Q H / (75) = 1000 x (5.11/1000) x 54.098/ (75 x 0.60) = 6.144.38 HP KW required = 0.746 x 6.144 = 4.58
Cost of pumping machinery @ 4000/BHP = 4000 x 4.58 = 18320 Annual electricity charges = KW x pumping hrs x 365 x energy charges = 3.27 x 12 x 365 x 3.20 = 45804.32 M&R depreciation charges = 7.5% of cost of pumping machinery = (7.5/100) x 17522.80 = 13142.10 Total O & M charges = 45804.32 + `13142.10 = 58946.42 Capitalized value of O&M Cc = CR [1-(1+r)-n]/r Taking r =7 .5 % and n=10 years, Cc = CR [1-(1+0.075)-10]/0.075 = CR x 6.864 = 58946.42 x 6.864 = 404608.2 Where, CR is annual energy charges CC is capitalized energy charges Cost of pipe in /m length = 170 Total cost of pipes = 345x 170 = 58650 Grand total capitalized cost = 58650 + 404608.2 + 45804.32 = 480781.1 Selection of the pipe diameter shall be based on the grand total of capitalized cost for 10 years.
Water hammer is a pressure surge or wave caused when a fluid in motion is forced to stop or change direction suddenly (momentum change). Water hammer commonly occurs when a valve closes suddenly at an end of a pipeline system.
Type of pipe = PVC(Polyvinyl chloride) Pipe rating = 6 Outer diameter of pipe = 110 mm Thickness of pipe = T = 4.3 mm Inner diameter of pipe = d = 110 2 x 4.3 = 101.4 mm Length of rising main = 345 m Discharge Q = 16567 X 1.2 x 70 / ( 12 x 60 x 60 ) = 5.36 lps Full supply level = 858.025m RL of rising main at pumphouse = 810.025 m Static head = 858.025 810.025 = 48m Velocity V = Q / A = 5.36x 10-3 / (3.1416 x 0.10142 /4) = 0.664m/sec Pressure wave velocity C = 1425 / (1 + K d / TE) where, K = bulk modulus of water = 2.07 x 108 kg /m2 E = Modulus of elasticity of pipe material = 3 x 108 kg /m2
C = 1425 / [1 + (2.07 x 108 x 0.129 / (0.0043 x 3 x 108))] = 305.9 m/sec Water hammer pressure = C V / g = 305.9 x 0.63 / 9.81 = 20.7 m Static head + water hammer head = 48 + 20.7 =68.7 m
2 x static head = 2 x 48 = 96 m Final design head = maximum (68.7, 96) = 57.5 m Final design pressure = 96 / 10 = 9.6ksc < 6 ksc Based on economical and water hammer
WATER TREATMENT :
The main aim of water treatment is to produce and maintain water that is hygienically safe, aesthetically attractive and palatable, in an economical manner. Though the treatment of water would achieve the desired quality, the evaluation of its quality should not be to the end of treatment facilities but should be extended to the point of consumer use.
SEDIMENTATION TANK
Sedimentation is the separation from water by gravitational settling of suspended particles that are heavier than water. It is one of the most commonly used unit operation in the flow sheet of conventional water treatment.
Filtration Tank:
To remove impurities that have remained after sedimentation. Water is filtered through beds of fine granular materials such as sand. This process is called FILTRATION. There are two types of filters. Slow sand filters Rapid sand filters
A slow sand filter must be cleaned when the fine sand becomes clogged, which is measured by the head loss. The length of time between cleanings can range from several weeks to a year, depending on the raw water quality.
The operator cleans the filter by scraping off the top layer of the filter bed. The filtered water quality is poor during this time and should not be used. In climates subject to below-freezing temperatures, slow sand filters usually must be housed.
It shall be constructed to store clear treated water the water is then supplied to chlorination tank.
CHLORINATION TANK:
The chlorination tank shall be installed to mix pure water with the requisite amount of bleaching powder as to cause disinfection. Contact period of more than half an hour is desired in chlorination tank. Normal dose of chlorine to be taken is 0.3 ppm for a contact period of half an hour. Normally chlorine content in bleaching powder is 30%.
Diameter of pipes used in lanes is as follows: Main line: 110 mm dia PVC pipes. Sub lanes: 75mm dia PVC pipes. Sub-sub lanes: 75mm dia PVC pipe
For one day Losses Per capita supply Total population 24 1.1 70 16567 Lpcd No Hr
Supply hour
Total length of pipe
4
7801.335
Hr
m
THANK YOU