SUBSTATION COMMISSIONING COURSE

MODULE THREE

INSTRUMENT TRANSFORMER TESTING PROCEDURES

10/5/2013

Module Three

INTRODUCTION
The electrical commissioning and acceptance testing of electric power systems is essential for the energization of any electrical system for the first time.

10/5/2013

Module Three

INTRODUCTION
Module Three Discuss theory and ratings Safety issues Test equipment operation & hands on testing

10/5/2013

Module Three

INTRODUCTION
Skills learned in MODULE THREE: Acceptance testing for CTs and VTs Operate CT tester Apply safe work practices Analyze test values Complete test forms

10/5/2013

Module Three

INSTRUMENT TRANSFORMERS
A general classification Current transformers (CT) Voltage transformers (VT) Standard secondary rating: 5A for CT 120V for VT < 24 kV 115V for VT > 24 kV

Isolate primary quantities and convert into useable secondary values via transformation

Measurement values from CTs and VTs: Voltage, current, frequency, real / reactive power, energy, power factor, impedance
5

10/5/2013

Module Three

INSTRUMENT TRANSFORMERS
Polarity markings A designation of the relative instantaneous direction of currents

Current flowing into the polarity mark in the primary is relatively in phase with current flowing out the polarity mark in the secondary As if the primary and secondary are connected straight through
10/5/2013 Module Three 6

INSTRUMENT TRANSFORMERS

10/5/2013

Module Three

INSTRUMENT TRANSFORMERS
Nameplate Data Manufacturers name or trademark Manufacturers type Serial number Rated Voltage, maximum voltage or nominal system voltage Rated frequency Basic impulse insulation level (N/A for bushing CTs) Continuous rating factor for CT (1.0 or more) Thermal burden rating for VT (VA) Accuracy rating

10/5/2013

Module Three

INSTRUMENT TRANSFORMERS
Nameplate Symbols (: colon) Ratio expression between winding groups Example: VT with one primary and one secondary winding 14,400 : 120 V Ratio 120 : 1 Ratio between primary and secondary amperes

Example: CT with one primary and one secondary winding 100 : 5 A Ratio 20 : 1

10/5/2013

Module Three

INSTRUMENT TRANSFORMERS
Nameplate Symbols (x multiplication sign) Voltage rating or ratios between winding groups Current rating with two or more coils for series of parallel connection Example: CT with two primary windings for series or parallel conn. 100 x 200 : 5 A

Example: VT with two windings for series or parallel connection 2,400 x 4800 V Ratio 20 x 40 : 1

10/5/2013

Module Three

10

INSTRUMENT TRANSFORMERS
Nameplate Symbols (// double slant lines) (Not used for VT) Ampere rating of separate secondary winding with independent core Example: CT with two secondary windings and two cores. 100 : 5 // 5A
10/5/2013 Module Three 11

INSTRUMENT TRANSFORMERS
Nameplate Symbols (& ampersand) Voltage rating or ratios of separate winding on one core. Ampere rating of separate primary winding on one core.

Example: VT with one primary and two secondary winding 14,400 V: 120 & 72 V Ratio 120 & 200:1
10/5/2013

Example 1: CT with two primary windings designed to be used individually.


100 & 600 : 5A

Module Three

12

INSTRUMENT TRANSFORMERS
Nameplate Symbols (& ampersand) Example 2: Totalizing CT with four primary windings designed to be used simultaneously. 5 & 5 & 5 & 5 : 5A

10/5/2013

Module Three

13

INSTRUMENT TRANSFORMERS
Nameplate Symbols (& ampersand) Example 3: CT for threewire single phase.

100 & 100 : 5A

10/5/2013

Module Three

14

INSTRUMENT TRANSFORMERS
Nameplate Symbols (/ single slant line) Two or more primary or secondary ratings obtained by taps in the secondary winding Example 1: VT with secondary tap for more primary voltage rating Different primary current ratings obtained by taps in the secondary winding

Example: CT with taps in the secondary for additional ratios


100 : 5 // 5A

12,000/14,400 :120 V Ratio 100/120 : 1


10/5/2013 Module Three 15

INSTRUMENT TRANSFORMERS
Nameplate Symbols (/ single slant line) Example 2: VT with secondary tap for additional secondary voltage ratings 14,400 : 120/72 V Ratio 120/200:1

10/5/2013

Module Three

16

INSTRUMENT TRANSFORMERS
North American Standards

CSA Originated in 2007 An adoption of IEC 60044 part 1 to part 7 ANSI/IEEE IEEE C57.13-2008 Standard Requirements for Instrument Transformers ANSI/IEEE C57.13.1-1981 Guide for Field Testing of Relaying Current Transformers

10/5/2013

Module Three

17

INSTRUMENT TRANSFORMERS
CSA Standards CAN/CSA-C60044-1 to -8 (part 1 to part 8), 2007 Part 1: Current Transformers Part 2: Inductive Voltage transformers Part 3: Combined Transformers Part 4: N/A Part 5: Capacitive Voltage transformers Part 6: Requirements for Protective Current Transformers for Transient Performance Part 7: Electronic Voltage Transformers Part 8: Electronic Current Transformers
10/5/2013 Module Three 18

INSTRUMENT TRANSFORMERS
What is a CT ? A device that isolates and transforms the primary current quantity into a proportional secondary current quantity

The CT has: Primary winding or primary conductor Magnetic core Secondary winding

10/5/2013

Module Three

19

INSTRUMENT TRANSFORMERS

Distributed uniform winding with negligible Leakage Flux


10/5/2013

Non-uniform distributed winding with some Leakage Flux


Module Three 20

INSTRUMENT TRANSFORMERS
How does a CT work ? Primary current flows generates magnetic field around the conductor Magnetic field flows in the magnetic core Magnetic field induces a voltage in the secondary winding Burden connected to secondary winding completes the circuit and allows current to flow

10/5/2013

Module Three

21

INSTRUMENT TRANSFORMERS
Ipri x Npri = Isec x Nsec Ipri = Isec = Npri = Nsec = Current flowing in primary winding Current generated in secondary winding Number of turns in primary winding Number of turns in secondary winding

10/5/2013

Module Three

22

INSTRUMENT TRANSFORMERS
What is the secondary current ? CT ratio: 5000:5A; 1000:1 Iprimary = 1000A

Isec = 1000A / (ratio) = 1000A /1000 = 1A


In reality, there will slightly less than 1A flowing. The difference is the known as the Ratio Error in %
10/5/2013 Module Three 23

INSTRUMENT TRANSFORMERS
Never open the secondary of a CT when primary current is flowing because dangerous high voltages will appear. IEEE C57.13 allow open circuit crest voltages up to 3500 V peak without voltage limiting devices.
10/5/2013 Module Three 24

INSTRUMENT TRANSFORMERS
CT Types Torroidal Wound Primary Bar Type Split Core Tororoidal Low flux leakage Typical of bushing and window CTs Primary conductor pass through center 600V insulation can be used in MV application with insulated primary conductors

10/5/2013

Module Three

25

INSTRUMENT TRANSFORMERS
CT Types

Torroidal (donut) Wound Primary Bar Type Split Core

Wound Primary Has an internal primary winding Wound more than 1 full turn on the core Core can be torroidal Must be inserted in series with the conductors Bar provides primary connection points, often mistaken for bar type
26

10/5/2013

Module Three

INSTRUMENT TRANSFORMERS
CT Types Torroidal (donut) Wound Primary Bar Type Split Core Bar Type Has a continuous bar for the primary winding Only 1 turn primary Core can be torroidal Must be inserted in series with the conductors Primary insulation part of CT construction

10/5/2013

Module Three

27

INSTRUMENT TRANSFORMERS
CT Types Torroidal (donut) Wound Primary Bar Type Split Core Split Core Core is separated into two parts For use where primary conductor cannot be easily removed

10/5/2013

Module Three

28

INSTRUMENT TRANSFORMERS

10/5/2013

Module Three

29

INSTRUMENT TRANSFORMERS
CT Ratio Ratio or primary current to secondary current

Expressed as current quantities 1000 : 5 A


Expressed as ratio numbers 200 : 1

10/5/2013

Module Three

30

INSTRUMENT TRANSFORMERS
Adjusting CT Ratio (low V) For some applications KA = (KN NSA) / NP KA = Actual ratio KN = Nameplate ratio NSA = Number of adjusted secondary turns adjusted To Add: loop X1 lead through H1. To Subtract: loop X1 opposite H1) NP = Number of primary turns
31

10/5/2013

Module Three

INSTRUMENT TRANSFORMERS
CT Ratio Adjustment 20:5 CT needed 50:5 CT available

KA = (KN NSA) / NP = (10 + 2) / 3 = 4 or 4:1 Actual CT Ratio = 20:5

10/5/2013

Module Three

32

INSTRUMENT TRANSFORMERS
CT Standard Burden @ 5A, @ 60 Hz

10/5/2013

Module Three

33

INSTRUMENT TRANSFORMERS
Basis for Accuracy class for Metering CTs and VTs correction factor is within specified limits for specified load conditions

.6 lagging to unity PF
CT operating between 10% to 100% rated current

VT operating between 90% to 100% rated voltage

10/5/2013

Module Three

34

INSTRUMENT TRANSFORMERS
IT Standard Accuracy Class for Metering @ 60 Hz

10/5/2013

Module Three

35

INSTRUMENT TRANSFORMERS
CT Accuracy Rating for Metering Accuracy for a specified burden Example: 0.3 B 1.8 .3% accuracy for all other burden up to 1.8 Example: 0.3 B @ 0.2 .3% accuracy for burden of .2 and 3

10/5/2013

Module Three

36

INSTRUMENT TRANSFORMERS
CT Accuracy Rating for Relaying @ 60 Hz

Accuracy classification apply to full winding unless specified

10/5/2013

Module Three

37

INSTRUMENT TRANSFORMERS
Relaying CT Class C (Calculated) T X Class C Low leakage flux CTs Torroidal type 3% error @ 5A 10% error @ 100A

10/5/2013

Module Three

38

INSTRUMENT TRANSFORMERS
Relaying CT Class C T (Tested) X Class T High leakage flux CTs Primary Wound type % error obtained from testing Tested to 100A or > until 10% error is establish at specified burdens Test curve plotted for Ipr Vs Isec, the overcurrent curve
Module Three 39

10/5/2013

INSTRUMENT TRANSFORMERS
Relaying CT Class C T X (Defined) Class X User defined along with expected accuracy rating for protection application Minimum knee point voltage; Vk Maximum excitation current Ik at Vk Maximum secondary winding resistance at 75C, Rs
Module Three 40

10/5/2013

INSTRUMENT TRANSFORMERS
Secondary Terminal Voltage Saturation voltage level at 20X rated current

100 A
Vsat = 100 A x Burden

10/5/2013

Module Three

41

INSTRUMENT TRANSFORMERS
Saturation Curve B-H Curve Excitation Current Vs Excitation voltage Knee Point voltage, Vk 10% Ve 50% Ie

10/5/2013

Module Three

42

INSTRUMENT TRANSFORMERS
Transformer Formula Erms = 2 f N a Bpeak / 2 4.44 f N a B

Where: f = the supply frequency N = number of turns a = cross sectional area of the core B = peak magnetic flux density

10/5/2013

Module Three

43

INSTRUMENT TRANSFORMERS
Class C Saturation Curve Plotted on log-log scale Induced voltage Y-axis Excitation current X-axis Voltage begins at 1% Voltage ends at 5X Irated Vk identified where curve is at 45 tangent axis

10/5/2013

Module Three

44

INSTRUMENT TRANSFORMERS

10/5/2013

Module Three

45

INSTRUMENT TRANSFORMERS
Class T O/C Ratio Curve Plotted of linear scale Secondary current Y-axis Primary current X-axis 1 to 22 x rated I-primary for all standard burdens Curve identifies the burden which causes 50% ratio correction

10/5/2013

Module Three

46

INSTRUMENT TRANSFORMERS
What is a VT ? Isolate and transform the primary voltage into proportional secondary voltage Construction Primary winding Magnetic core Secondary winding

10/5/2013

Module Three

47

INSTRUMENT TRANSFORMERS
5 Groups of VT All capable of operating at 110% for emergency condition Emergency for 1 minute Some have special emergency rating conditions All must operate within thermal limits and or specified temperature rise

10/5/2013

Module Three

48

INSTRUMENT TRANSFORMERS

10/5/2013

Module Three

49

INSTRUMENT TRANSFORMERS
VT Accuracy Rating Accuracy rating for each standard burden For maximum burden For specified burden Example: 0.3 Z; 0.3 Y, 0.6 Z and 1.2 ZZ; 0.3 Z @ Y Accuracy for two 2ndary or tapped 2ndary windings Burden is the total for the VT Accuracy class apply with the burden divided between the 2ndaries outputs in any manner
10/5/2013 Module Three 50

INSTRUMENT TRANSFORMERS
Thermal Burden Rating The maximum volt-ampere (VA) it can carry within temperature design limits Each winding can have its own rating One specified rating is for combined distribution between the 2ndaries, including taps

10/5/2013

Module Three

51

TESTING INSTRUMENT TRANSFORMERS


Safety Consideration Many testing involves using high voltages Should be done by trained qualified personnel Safe work practice and procedures required Review Module 2 IEEE Standard 510 1983, Recommended Practice for Safety in High Voltage & High Power Testing

10/5/2013

Module Three

52

TESTING INSTRUMENT TRANSFORMERS


CT Testing Primary Insulation Resistance Dielectric Withstand Secondary Insulation Resistance Secondary Burden Saturation Ratio and Polarity

10/5/2013

Module Three

53

TESTING INSTRUMENT TRANSFORMERS


CT Testing Primary Insulation Resistance Dielectric Withstand Secondary Insulation Resistance Secondary Burden Saturation Ratio and Polarity Primary Ins. Resistance Test For Bar and Primary wound CTs DC voltage test at the rated crest voltage on the primary winding Secondary grounded 1 minute test

10/5/2013

Module Three

54

TESTING INSTRUMENT TRANSFORMERS


CT Insulation Resistance: Bar Type and Primary Wound

DC Voltage test
Isolate Primary Isolate & Gnd Secondary Connect HV lead to H1/H2 Connect LV to Gnd / 2ndary Test for 1 minute Record test value

10/5/2013

Module Three

55

TESTING INSTRUMENT TRANSFORMERS


CT Testing Primary Insulation Resistance Dielectric Withstand Secondary Insulation Resistance Secondary Burden Saturation Ratio and Polarity Dielectric Withstand Test For Bar and Primary wound CTs AC voltage test at the 75% factory test voltage Secondary grounded 1 minute test

10/5/2013

Module Three

56

TESTING INSTRUMENT TRANSFORMERS


CT Dielectric Withstand: Bar Type and Primary Wound

AC Voltage test
Isolate & Gnd Secondary Connect HV lead to H1/H2 Connect LV to Gnd / 2ndary Test for 1 minute Record test value

10/5/2013

Module Three

57

TESTING INSTRUMENT TRANSFORMERS


CT Testing Primary Insulation Resistance Dielectric Withstand Secondary Insulation Resistance Secondary Burden Saturation Ratio and Polarity 2ndary Ins. Resistance Test Test for secondary wiring Secondary wiring isolated and ungrounded 1000 VDC 1 minute test

10/5/2013

Module Three

58

TESTING INSTRUMENT TRANSFORMERS


CT Secondary Circuit Insulation Test

10/5/2013

Module Three

59

TESTING INSTRUMENT TRANSFORMERS


CT Testing Primary Insulation Resistance Dielectric Withstand Secondary Insulation Resistance Secondary Burden Saturation Ratio and Polarity 2ndary Burden Test Conducted in 2 parts Part 1, 1A current injection Measure circuit burden Part 2, four-wire resistance measurement Measure secondary winding resistance Burden = part 1 + part 2

10/5/2013

Module Three

60

TESTING INSTRUMENT TRANSFORMERS


Part 1: CT Secondary Circuit Burden Measurement

10/5/2013

Module Three

61

TESTING INSTRUMENT TRANSFORMERS


Part 2: CT Secondary Winding Resistance Measurement

10/5/2013

Module Three

62

TESTING INSTRUMENT TRANSFORMERS


Total burden calculation ZT = RCT + (RL + ZB) Where ZT

Total burden ()
DC Winding resistance () Lead resistance () Device impedance ()

RCT = RL = ZB =

10/5/2013

Module Three

63

TESTING INSTRUMENT TRANSFORMERS


CT Testing Primary Insulation Resistance Dielectric Withstand Secondary Insulation Resistance Secondary Burden Saturation Ratio and Polarity Saturation Test Secondary winding excitation test Primary open circuited Step voltage increase, current proportional Test for knee-point voltage Rapid rise is I-excitation 10% V = 50% I

10/5/2013

Module Three

64

TESTING INSTRUMENT TRANSFORMERS


CT Saturation test

10/5/2013

Module Three

65

TESTING INSTRUMENT TRANSFORMERS


CT Testing Primary Insulation Resistance Dielectric Withstand Secondary Insulation Resistance Secondary Burden Saturation Ratio and Polarity Ratio and Polarity test Secondary winding excited at 1V per turn Primary open circuited H1-H2 compared to X1-X2 Phase measured, ratio calculated Phase difference 0 means polarity correct

10/5/2013

Module Three

66

TESTING INSTRUMENT TRANSFORMERS


CT Ratio and Polarity Test

10/5/2013

Module Three

67

TESTING INSTRUMENT TRANSFORMERS


CT Testing Primary Insulation Resistance Dielectric Withstand Secondary Insulation Resistance Secondary Burden Saturation Ratio and Polarity Ratio and Polarity test (ALT) Use individual meters, phase angle and voltmeter Secondary winding excited at 1V per turn Primary open circuited H1-H2 compared to X1-X2 Phase measured, ratio calculated Phase difference 0 means polarity correct
Module Three 68

10/5/2013

TESTING INSTRUMENT TRANSFORMERS


CT Ratio and Polarity Test (alternate connections)

10/5/2013

Module Three

69

TESTING INSTRUMENT TRANSFORMERS


VT Testing Insulation Resistance Dielectric Withstand Ratio and Polarity

10/5/2013

Module Three

70

TESTING INSTRUMENT TRANSFORMERS


VT Testing Insulation Resistance Dielectric Withstand Ratio and Polarity Insulation Resistance Test DC voltage test at the rated crest voltage 3 tests HV to Gnd HV to LV LV to Gnd

10/5/2013

Module Three

71

TESTING INSTRUMENT TRANSFORMERS


VT Insulation Resistance Tests

10/5/2013

Module Three

72

TESTING INSTRUMENT TRANSFORMERS


VT Testing Insulation Resistance Dielectric Withstand Ratio and Polarity Dielectric Withstand Test AC voltage test at the 75% factory test voltage Secondary grounded 1 minute test

10/5/2013

Module Three

73

TESTING INSTRUMENT TRANSFORMERS


VT Dielectric Withstand Tests

10/5/2013

Module Three

74

TESTING INSTRUMENT TRANSFORMERS


VT Testing Insulation Resistance Dielectric Withstand Ratio and Polarity Ratio and Polarity test Primary winding excited at 1V per turns ratio Secondary open circuited X1-X2 compared to H1-H2 Phase measured, ratio calculated Phase difference 0 means polarity correct Compare ratio with nameplate
Module Three 75

10/5/2013

NETA STANDARD
5. NETA Acceptance Testing Procedure
10/5/2013

5.1 Visual and Mechanical Inspection 5.2 Electrical Test 5.2.1 Current Transformer 5.2.2 Voltage Transformer 5.3 Test Value Analysis 5.3.1 Visual and Mechanical 5.3.2 CT Electrical Test 5.3.3 VT Electrical Test
Module Three 76

TEST SET MANUAL


Module 3: CT Tester Module 2: 15 KV Insulation Resistance Test set AC High Potential Test set DC High Potential Test set Digital Low Resistance Test set

10/5/2013

Module Three

77

TEST FORMS
Current Transformer Test Form Voltage Transformer Test Form

10/5/2013

Module Three

78

10/5/2013

Module Three

79

10/5/2013

Module Three

80

Potrebbero piacerti anche