Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1 /33
Agenda
General Introduction to EV Reporting Comparison with other Methods EV Management in Practise Earned Value
Planned Value Actual Costs Schedule Performance Index Cost Performance Index
Introduction
2 /33
Example, PV
PV = planned % complete * baseline cost PV: Value of work scheduled to have been completed at a certain moment in time.
Introduction
3 /33
Example, EV
EV = actual % complete * baseline cost EV: Value of work actually accomplished at a certain moment in time.
Introduction
4 /33
Actual Costs
AC:
Value that gives insight in how much is paid for the work actually accomplished.
Introduction
5 /33
Introduction
EV and PV Curve
Introduction
7 /33
EV Calculations
%Complete = Earned Value / Budget at Completion * 100
%Spent = Actual Costs / Budget at Completion * 100 % Over/Under Spent = [(Actual Cost / Earned Value) - 1] * 100
Introduction
8 /33
Variance Analysis
Cost Variance (CV) = Earned Value (EV) Actual Costs (AC) Schedule Variance (SV) = Earned Value (EV) Planned Value (PV)
Introduction
9 /33
EV SPI PV
SPI 1 SPI 1
SPI 1
Example:
Introduction
10 /33
EV CPI AC
CPI 1
CPI 1
CPI 1
Example:
Introduction
11 /33
Introduction
12 /33
Critical ratio
Critical Ratio (CR) = CPI * SPI
CR 1 CR 1 CR 1
Introduction
13 /33
Introduction
As we proceed further through the project, our ability to change the SPI and CPI values decreases exponentially. Very early in the project, the SPI and CPI values are elastic. However, starting very early in the project, the SPI and CPI values will increasingly reflect the final project condition
% Project Complete
14 /33
Forecasting
15 /33
Advantages of EV Reporting
Early warnings Costs Forecasting Communication (External) Control
16 /33
Advantages
Simple Little effort required
17 /33
Advantages
More insight in monetary relativity
18 /33
Advantages
Insight in accomplished work
19 /33
Advantages
Insight in accomplished work
Disadvantages
No insight in value of accomplished work
20 /33
Advantages
Forecasting ability
Disadvantages
Requires realistic planning More time consuming to administer
21 /33
Advantages
Simple, using information readily available to most projects Common indicators for comparison with other projects
Disadvantages
Relies on realistic estimate of % Complete, (or EV) which may by nature be more subjective than tracking the accumulated completion values of many measurable smaller units.
Assumes that progress and spend forecasts are linear, which is normally not the true case.
22 /33
Key Decisions
Method of EV Calculation; Tracking and Reporting Frequency Threshold Establishment What Cost Elements comprise Planned Value Whether to track resource actual hours including Overtime or a standard 8 hour day. Which resource labour costs should be included? Level of detail of EV management Baseline Timing
23 /33
EV Management in Practise
EV management Methods
Percentage complete Physical percentage complete Fixed percentage from start
EV Management in Practise
24 /33
Level of detail
Examples of levels
The project lifecycle stage The workstream (activity grouping)
EV Management in Practise
25 /33
Baseline timing
EV Management in Practise
26 /33
Baseline timing
EV Management in Practise
27 /33
EV Management in Practise
28 /33
Example EV Report
29 /33
30 /33
31 /33
Example EV Report
32 /33
33 /33