Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
• Explination of timestudies.
• Line capacity calculation.
• Manpower planning.
• World class manufacturing cell (Video).
• Line balancing.
Time Study & Line Balancing
1. Conducting a timestudy:
• Identify all the activities of an operation (Welding operation):
• load part in jig, clamp and start cycle (operator).
• robot welding the part (machine auto cycle).
• unload part from welding jig (operator).
• Record the time utilised to perform each activity:
• load the part 10 seconds (operator)
• Welding 40 seconds (robot)
• Unloading 5 seconds (operator)
• Operator allowance 9% of total time: 5 seconds
Total time to produce a part: 60 seconds (60 parts per hour).
• Operations such as leak testing and final checking have no machine time all the time is
operator time.
Line Capacity / Hourly Target
Available time
Available time per shift:(8hours x 60 minutes) 480
Less: Lunch time 30
Less: Meeting 10
Less: Houskeeping 5
Net available time: 435
Less :Planned down time:
Robotic Consumable changes: 10%
Machine availabilty (100% - 10%) 90%
Total available time:(435 x 90%) 392
Dr.
Wiesner
S/ boss
Embos Leak test
rolling
Final Final
Exit check Round
weld
Entry
Cone / inlet Cone / inlet Cone round
pipe tackweld pipe tackweld weld
Current Layout Line 1D & Output
Current Process Flow & Cycle Times
Operation No operators Parts / cycle FTF (min.) Operator Min. Parts / hour
Inlet cone tackweld Included in first tackweld
1 2 0.57 105
Inlet cone tackweld cycle
Assumptions:
1. Line availability = 80%
2. Current bottleneck = 72 / hour at 100%. At 80% availability the revised hourly target = 58 parts / hour.
3. Based on current demand the tact time = 51 parts / hour (demand can be achieved in 2 shifts, any increase will require a 3rd shift)
Operation No operators Parts / cycle FTF (min.) Operator Min. Parts / hour
Inlet cone tackweld Included in first tackweld
1 2 0.57 105
Inlet cone tackweld cycle
Calibration 1 Operator dependant
1 0.65 92
Sensor boss rolling 1
Cone round weld 2 1.35 0.25 89
1
Outlet cone sub assy tack 1 0.37 0.1 162
Final round weld 1 2 1.34 0.9 90
Leak Tester 1 1 0.83 Operator dependant 72
Heat shield clinching 1 1 0.66 91
Heat shield spot weld 1
1 0.52 115
Heat shield embossing 1 Operator dependant
Heat shield welding
1 2 0.55 109
Heat shield welding
Dr. Wiesner 1 1 0.69 Operator dependant 87
Final check 1 1 0.82 Operator dependant 73
Total Operators: 10
Revised Layout: Line 1D
Dr.
Wiesner
Leak test
S/ boss
Embos
rolling
Final
check Final
Exit
Round
weld
Cal.
Tackweld
Teamleader
Entry
Cone / inlet Cone / inlet Cone round
pipe tackweld pipe tackweld weld