Extension of Time (EOT) and Related Costs in Construction

By Khalil T. Hasan Construction Solutions (www.cspk.org)


Presented at the FIDIC Middle East Contract Users Conference February 2013 Dubai, UAE

www.cspk.org

Time is of Essence
Delays are inevitable on construction projects The only project to have completed on time is a Mosque. Divine intervention (or Gods help) was understood to be the force behind the

timely completion of this Mosque.


Time and Money go hand-in-hand. When projects get late, additional costs are incurred. This makes it imperative to take control of project delays; timely and

effectively.

www.cspk.org

FIDIC

FIDIC

FIDIC

FIDIC

FIDIC

Majority of construction projects worldwide are administered by the


FIDIC forms of contract. FIDIC recognises delay and related costs and has provisions related thereto. For example;

Sub-Clauses 8.4 & 20.1 (FIDIC 1999 Edition)


Clauses 44 & 53 (FIDIC 1987 Edition)

www.cspk.org

The FIDIC Provisions define the conditions where delay may be claimed as the basis for an Extension of Time (EOT). Some examples are; Late provision of design or drawings Unforeseeable Physical Conditions encountered on Site Inclement Weather Variations instructed by the Engineer (Additional Works etc.)

www.cspk.org

Meanwhile the principles of how delay and related costs should be calculated are not defined by FIDIC. This leads to issues; issues which are usually contentious due to various 'schools of thoughts' and varied interpretations existing worldwide.

Disputes are the usual outcome.

www.cspk.org

Contentious Issues in Delay Analysis resulting in Disputes


Critical Path Who owns the Float? Concurrent (or Contractor) Delays and how these effect Entitlement EOT and its relation with Compensation for Delay Which is the best Method of Delay Analysis?
As-Planned Vs. As-Built Comparison Impacted As-Planned Collapsed As-Built / But-For Time Slice / Sub-Networks / Time-Impact Etc.

www.cspk.org

In order to eliminate disputes or facilitate settlement of disputes, there are now certain standards used worldwide. The leading standards are; Society of Construction Laws Delay and Disruption Protocol (SCL Protocol)

AACE 29R-03 (Forensic Schedule Analysis)


www.cspk.org

The SCL Protocol was finalized in October 2002 after several years of deliberations and considerable debate and agreement between experts from different backgrounds

www.cspk.org

The objective of the SCL Protocol was to bring reasonableness and fairness into the delay assessment process and to eliminate widespread manipulation of complex delay issues
www.cspk.org

The SCL Protocol tried to standardize the issues such that disputes would be reduced or eliminated

www.cspk.org

It is recommended that;

should be adopted as a Standard and should be, where possible, incorporated in the Construction Contracts

www.cspk.org

The SCL Protocol can be downloaded from:

www.eotprotocol.com
www.cspk.org

The remaining slides of this lecture will review and discuss the basic Principles suggested and recommended by the SCL Protocol
www.cspk.org

Basic Principles suggested and recommended by the SCL Protocol

www.cspk.org

The Principles suggested by the SCL Protocol are simple.

Some of the key principles suggested by the Protocol are;

www.cspk.org

RULE NO. 1
If there is an Employers delay, which is beyond the Contractors control, and if this delay impacts the Completion Date of the Works,

the Contractor should be entitled to receive an Extension of Time (EOT).


[This will effectively result in an extended Time for Completion and will relieve the Contractor from having to pay penalties for delay (or Delay Damages under FIDIC)]

www.cspk.org

RULE NO. 2
For the case of recovery of delay (or prolongation) costs incurred due to the Employer delays, the Contractor must be able to prove that there has been no other delay, which is in his own control, and which is equally (or partly) contributing for delaying the Time for Completion.

This category of delay is called a Concurrent (or Contractors) Delay


[In order to win a Delay Costs Claim, the Contractor must be able to prove that he has not been responsible for Concurrent Delays to the Time for Completion]

www.cspk.org

RULE NO. 3
Where Contractors Delay to Completion occurs concurrently with Employers Delay to Completion, the Contractors concurrent delay should NOT reduce any Extension of Time (EOT), which is due.
[Result of Rule No. 1 will not change and is irrespective of the result of Rule No. 2]

www.cspk.org

The foregoing Rules proposed by the SCL Protocol are meant to bring fairness and reasonableness into the delay assessment process.
[The emphasis of the SCL Protocol is that no one Party should benefit from default of the other Party]

www.cspk.org

The Illustrations demonstrating the principles of the SCL Protocol are contained in the following Figures A to G

www.cspk.org

Figure A - Accepted Contract Programme


1 2 3 Path 1 4 5 6 7 8 Weeks 9 10 11 12 13 14 15 16 17 18 19 20 21 22

Path 1 Float = 3.5 Weeks Contract Start Date Contract Completion Date

Path 2

Path 2 Float = 5.5 Weeks

www.cspk.org

Figure B - Delay Impact 1


1 2 3 4 5 6 7 8 9 10 Weeks 11 12 13 14 15 16 17 18 19 20 21 22

PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1


<=Date of Excusable Delay Path 1 Float = 3.0 Weeks Contract Start Date Contract Completion Date

Path 2

Path 2 Float = 5.5 Weeks

AFTER EXCUSABLE DELAY Path 1


Impact on Path 1 = 2.0 Weeks

Excusable Delay

Contract Completion Date Path 1 Float = 1.0 Week

Path 2

Path 2 Float = 5.5 Weeks

(1) EOT Entitlement (a) 2.0 Weeks (b) 1.0 Weeks (c) 0 Weeks (d) 5.5 Weeks

(2) Period of Prolongation Costs (a) 5.5 Weeks (b) 0 Weeks (c) 1.0 Weeks (d) 2.0 Weeks

(3) Compensation for Delay to Progress (a) 2.0 Weeks (b) 1.0 Weeks (c) 0 Weeks (d) 5.5 Weeks

(4) Other Compensation (a) 0.1% of Contract Price (b) Direct Costs of Excusable Delay (c) NIL (d) (a) plus (b)

www.cspk.org

Principles & Provisions of the SCL Protocol relevant to Figure B

Core Principle No. 7 - Float as it relates to time Unless there is express provision to the contrary in the contract, where there is remaining float in the programme at the time of an Employer Risk Event, an EOT should only be granted to the extent that the Employer Delay is predicted to reduce to below zero the total float on the activity paths affected by the Employer Delay.
Guidance Section 1.12.1 If as a result of an Employer Delay, the Contractor is prevented from completing the works by the Contractors planned completion date (being a date earlier than the contract completion date), the Contractor should in principle be entitled to be paid the costs directly caused by the Employer Delay, notwithstanding that there is no delay to the contract completion date (and therefore no entitlement to an EOT), provided also that at the time they enter into the contract, the Employer is aware of the Contractors intention to complete the works prior to the contract completion date, and that intention is realistic and achievable.
www.cspk.org

Figure C - Delay Impact 2


1 2 3 4 5 6 7 8 9 10 Weeks 11 12 13 14 15 16 17 18 19 20 21 22

PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1


<=Date of Excusable Delay Path 1 Float = 3.0 Weeks Contract Start Date Contract Completion Date

Path 2

Path 2 Float = 5.5 Weeks

AFTER EXCUSABLE DELAY Path 1


Impact on Path 1 = 3.5 Weeks

Excusable Delay

Contract Completion Date Float = -0.5 Week

Path 2

(1) EOT Entitlement (a) 0.5 Weeks (b) 3.5 Weeks (c) 0 Weeks (d) 5.5 Weeks

(2) Period of Prolongation Costs (a) 5.5 Weeks (b) 0.5 Weeks (c) 3.5 Weeks (d) 0 Weeks

(3) Compensation for Delay to Progress (a) 3.5 Weeks (b) 0.5 Weeks (c) 0 Weeks (d) 3.0 Weeks

(4) Other Compensation (a) 0.15% of Contract Price (b) Direct Costs of Excusable Delay (c) (a) plus (b) (d) NIL

www.cspk.org

Principles & Provisions of the SCL Protocol relevant to Figure C


Core Principle No. 4 - Procedure for granting extension of time The EOT should be granted to the extent that the Employer Risk Event is reasonably predicted to prevent the works being completed by the then prevailing contract completion date..The goal of the EOT procedure is the ascertainment of the appropriate contractual entitlement to an EOT; the procedure is not to be based on whether or not the Contractor needs an EOT in order not to be liable for liquidated damages. Core Principle No. 5 Effect of delay For an EOT to be granted, it is not necessary for the Employer Risk Event already to have begun to affect the Contractors progress with the works, or for the effect of the Employer Risk Event to have ended.

www.cspk.org

Figure D - Delay Impact 3


1 2 3 4 5 6 7 8 9 10 Weeks 11 12 13 14 15 16 17 18 19 20 21 22

PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1


<=Date of Excusable Delay Path 1 Float = 3.0 Weeks Contract Start Date Contract Completion Date

Path 2

Path 2 Float = 5.5 Weeks

AFTER EXCUSABLE DELAY Path 1


Contract Completion Date Float = -0.5 Week

Path 2

Excusable Delay
Impact on Path 2 = 6.0 Weeks

(1) EOT Entitlement (a) 0 Weeks (b) 6.0 Weeks (c) 0.5 Weeks (d) 5.5 Weeks

(2) Period of Prolongation Costs (a) 5.5 Weeks (b) 0 Weeks (c) 6.0 Weeks (d) 0.5 Weeks

(3) Compensation for Delay to Progress (a) 3.5 Weeks (b) 0.5 Weeks (c) 6.0 Weeks (d) 3.0 Weeks

(4) Other Compensation (a) (d) minus (c) (b) Direct NIL Costs of Excusable Delay (c) Direct Costs of Excusable Delay (d) 0.2% of Contract Price

www.cspk.org

Principles & Provisions of the SCL Protocol relevant to Figure D


Core Principle No. 4 - Procedure for granting extension of time The EOT should be granted to the extent that the Employer Risk Event is reasonably predicted to prevent the works being completed by the then prevailing contract completion date..The goal of the EOT procedure is the ascertainment of the appropriate contractual entitlement to an EOT; the procedure is not to be based on whether or not the Contractor needs an EOT in order not to be liable for liquidated damages. Core Principle No. 5 Effect of delay For an EOT to be granted, it is not necessary for the Employer Risk Event already to have begun to affect the Contractors progress with the works, or for the effect of the Employer Risk Event to have ended.

www.cspk.org

Figure E - Delay Impact 4


1 2 3 4 5 6 7 8 9 10 Weeks 11 12 13 14 15 16 17 18 19 20 21 22

PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1


<=Date of Excusable Delay Contract Completion Date Contract Start Date Float = -1.5 Weeks

Path 2

AFTER EXCUSABLE DELAY Path 1


Contract Completion Date Excusable Delay

Impact on Path 1 = 2.0 Weeks Float = -3.5 Weeks

Path 2

(1) EOT Entitlement (a) 3.5 Weeks (b) 2.0 Weeks (c) 1.5 Weeks (d) 0 Weeks

(2) Period of Prolongation Costs (a) 2.0 Weeks (b) 0 Weeks (c) 3.5 Weeks (d) 1.5 Weeks

(3) Compensation for Delay to Progress (a) 3.5 Weeks (b) 2.0 Weeks (c) 3.0 Weeks (d) 0 Weeks

(4) Other Compensation (a) (c) plus (d) (b) Direct NIL Costs of Excusable Delay (c) Direct Costs of Excusable Delay (d) 0.1% of Contract Price

www.cspk.org

Principles & Provisions of the SCL Protocol relevant to Figure E


Guidance Section 1.2.11 an EOT should be granted to the extent that the Employer Risk Event is predicted to prevent the works being completed by the then prevailing contract completion date. This process requires consideration of the available float Guidance Section 1.4.12 Where there has been Employer Delay, this may prevent the Employer charging the Contractor with LDs for failure to achieve a contract completion date

www.cspk.org

Figure F - Delay Impact 5


1 2 3 4 5 6 7 8 9 10 Weeks 11 12 13 14 15 16 17 18 19 20 21 22

PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1


<=Date of Excusable Delay Contract Completion Date Contract Start Date Float = -1.5 Weeks

Path 2

AFTER EXCUSABLE DELAY Path 1


Contract Completion Date Impact on Path 1 = 2.0 Weeks Excusable Delay Float = -3.5 Weeks

Path 2

(1) EOT Entitlement (a) 2.0 Weeks (b) 3.5 Weeks (c) 1.5 Weeks (d) 0 Weeks

(2) Period of Prolongation Costs (a) 0 Weeks (b) 2.0 Weeks (c) 3.5 Weeks (d) 1.5 Weeks

(3) Compensation for Delay to Progress (a) 3.5 Weeks (b) 2.0 Weeks (c) 3.0 Weeks (d) 0 Weeks

(4) Other Compensation (a) (c) plus (d) (b) Direct NIL Costs of Excusable Delay (c) Direct Costs of Excusable Delay (d) 0.1% of Contract Price

www.cspk.org

Principles & Provisions of the SCL Protocol relevant to Figure F


Guidance Section 1.4.8 Where an Employer Risk Event occurs after the contract completion date, in a situation where failure to complete by the contract completion date has been caused by Contractor Delays, the principle set out in Section 1.4.7 above should apply, except where the Employer Risk Event is a non-compensable Employer Risk Event. In such an event, no EOT (or compensation) should be due. Where an EOT is due after the contract completion date, the Employer Risk Event does not exonerate the Contractor for all its delays prior to the Employer Risk Event occurring. The effect of the Employer Risk Event should be assessed as described above and any EOT found due should simply be added to the contract completion date.

www.cspk.org

Figure G - Delay Impact 6


1 2 3 4 5 6 7 8 9 10 Weeks 11 12 13 14 15 16 17 18 19 20 21 22

PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1


<=Date of Excusable Delay Contract Completion Date Contract Start Date Float = -1.5 Weeks

Path 2
Path 2 Float = 2.5 Weeks

AFTER EXCUSABLE DELAY Path 1


Contract Completion Date

Float = -1.5 Weeks

Path 2

Excusable Delay = 3.5 Weeks

(1) EOT Entitlement (a) 2.5 Weeks (b) 3.5 Weeks (c) 1.0 Weeks (d) 1.5 Weeks

(2) Period of Prolongation Costs (a) 0 Weeks (b) 2.5 Weeks (c) 3.5 Weeks (d) 1.5 Weeks

(3) Compensation for Delay to Progress (a) 0 Weeks (b) 2.0 Weeks (c) 3.0 Weeks (d) 3.5 Weeks

(4) Other Compensation (a) (b) plus (d) (b) Direct Costs of Excusable Delay (c) NIL (d) 0.2% of Contract Price

www.cspk.org

Principles & Provisions of the SCL Protocol relevant to Figure G Slide 1/2
Guidance Section 1.4.1 Where Contractor Delay to Completion occurs concurrently with Employer Delay to Completion, the Contractors concurrent delay should not reduce any EOT due.
Guidance Section 1.4.7 Where Employer Risk Events and Contractor Risk Events occur sequentially but have concurrent effects, here again any Contractor Delay should not reduce the amount of EOT due to the Contractor as a result of the Employer Delay. Concurrency (Appendix A Definations and Glossary) True concurrent delay is the occurrence of two or more delay events at the same time, one an Employer Risk Event, the other a Contractor Risk Event and the effects of which are felt at the same time. The term concurrent delay is often used to describe the situation where two or more delay events arise at different times, but the effects of them are felt (in whole or in part) at the same time. To avoid confusion, this is more correctly termed the concurrent effect of sequential delay events.

www.cspk.org

Principles & Provisions of the SCL Protocol relevant to Figure G Slide 2/2
Core Principle No. 9 - Concurrent delay its effect on entitlement to extension of time Where Contractor Delay to Completion occurs or has effect concurrently with Employer Delay to Completion, the Contractors concurrent delay should not reduce any EOT due. Core Principle No. 14 - Link between extension of time and compensation Entitlement to an EOT does not automatically lead to entitlement to compensation (and vice versa). Core Principle No. 10 - Concurrent delay its effect on entitlement to compensation for prolongation If the Contractor incurs additional costs that are caused both by Employer Delay and concurrent Contractor Delay, then the Contractor should only recover compensation to the extent it is able to separately identify the additional costs caused by the Employer Delay from those caused by the Contractor Delay. If it would have incurred the additional costs in any event as a result of Contractor Delays, the Contractor will not be entitled to recover those additional costs.

www.cspk.org

Key Guideline, Suggestion and Advice of the SCL Protocol


Guidance Section 3.2.13 Although the programme should be the primary tool for guiding the CA in his determination of EOT, it should be used in conjunction with the contemporary evidence to ensure that the resulting EOT is fair and reasonable. It will also be necessary for the parties to apply common sense and experience to the process to ensure that all relevant factors are taken into account, and that any anomalous results generated by the programme analysis are managed properly.

www.cspk.org

Correct Responses for Figures B to G


Figure No. B C D Question 1 (c) (a) (c) Question 2 (b) (b) (d) Question 3 (a) (d) (d) Question 4 (b) (b) (c)

E
F G

(b)
(a) (c)

(a)
(b) (a)

(d)
(d) (a)

(c)
(c) (b)

www.cspk.org

Congratulations we have come to the end of the Lecture.


You are now a Qualified and Certified Delay Claims Analyst and Expert.

www.cspk.org

FIDIC and Construction Solutions thank you for your attendance and contribution. We wish you all Good Luck.

www.cspk.org

We urge all participants to review the SCL Protocol on their own. Construction Solutions Claims Management Division (www.cspk.org) will remain available for further discussions on the foregoing and any other relevant issue. This Lecture was delivered by the Managing Partner of Construction Solutions, Mr. Khalil Tayab Hasan. For any queries and clarifications, please feel free to contact Mr. Hasan at;