Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Worlds biggest power cut At 02:35 on 30th July & 13:02 on 31st July Blackout in 22 States 620 Mn without power 3 grids failed: North, East, North-East Hundreds of trains and Lacs of households and establishments affected
Why it Happened?
Overdrawing
Distribution
Demand-Supply
NR, ER, WR, and NER synchronized as NEW Grid whereas SR is not synchronized
MUx 10000
MUx 100000
2 1.5 1
3
2 1
0.5
0 N W S E N-E Actual Energy
CRISIL 2011-12
In 2011-12, power sector accounted for 70-75 per cent of total coal consumption and 46 percent of total natural gas consumption Advantage
Low cost of generation
Disadvantages
Advantages
Low operating costs Absence of emissions
Disadvantages
Economic and social costs Submergence of forests and loss of marine life
Disadvantages
Possibility of nuclear hazard, e.g. Chernobyl, Russia High capital costs and long gestation period
US, China & Spain generate approx. 55% of the total Advantages
Plentiful and renewable Clean , no greenhouse gas emissions
Disadvantages
Intermittent supply Large number of turbines required Noise pollution
Disadvantages
Initial installation cost Large land requirements
Structural Framework
Functions
CEA
Formulation of National Electricity Plan in accordance with National Electricity Policy Main technical advisor of government and regulatory commissions Specifies electrical standards and safety requirements
CERC
Regulate tariff of companies owned or controlled by Central government To regulate and grant licenses for inter-state transmission and trading To advise Central government in formulation of National Electricity Policy and Tariff Policy.
SERC
Determines tariffs for generation, supply etc within state Issue licenses for intra-state transmission, distribution and trading Promote co-generation and generation of electricity from renewal sources of energy etc.
Functions
CTU and STUs
Undertake transmission of energy through transmission system Planning and coordination of inter/intra-state transmission systems
Appellate Tribunals
Hear appeals against orders of the Electricity Regulatory Commissions (ERC) Became operational in 2005
Bidding
Competitive bidding made mandatory for all power projects, since January 2011 Case 1 Bidding
Route, location and type of fuel is flexible (states with resource constraint) e.g. Project Amravati by Indiabulls in Maharashtra
Case 2 Bidding
Route, location and type of fuel is fixed (resource rich but cash constrained states) e.g. MPP Anpara by Lanco in Uttar Pradesh
Step to leverage best corporate practices Cut down high utility losses (national average ATC of 27+%) Predictable cash flows directly from end-consumers A total of 14 states have appointed franchisees for different zones
Franchisee Distribution
Sell power to franchisee Distribution Franchisee Franchisee distributes at price prescribed by SEC
End User
Geothermal Energy
One plant (25MW) under commissioning at Khammam in Andhra
Tidal Power
One plant (50MW) planned in Gujarat
Challenges
Acute shortage of power
Over 300 million people in India have no access to electricity Existing electricity supply is found to be intermittent and unreliable.
Challenges
Aggregate Technical and Commercial Losses
About 27% of generated power is lost International average is 10-15% Major technical reason is energy dissipation in conductors, transmission and transformation equipments Commercial losses caused by pilferage, defective meters and unmetered supply of energy The energy loss in some states is as high as 70%
Challenges
Fuel constraint
Thermal Power accounts for 65% of total electricity generated in India but affected by shortage of fuel India has abundant resources of coal but production has not been able to meet demand State owned Coal India which has monopoly in coal production has been marred by bureaucracy and environmental issues Lesser than projected production of natural gas has caused shortage of fuel and dependence on imported natural gas has increased
Challenges
Poor infrastructure
Ageing and improperly maintained infrastructure is affecting electricity supply Added production capacity has not been complemented by improved transmission and distribution infrastructure
Challenges
Pollution caused by thermal power plants
Indian coal-fired, natural gas-fired and oil-fired power plants are inefficient causing massive emission on greenhouse gases The CO2 emission per KWH produced is 50-120% higher in Indian thermal power plants as compared to EU countries
Oil
Nuclear Hydro Other Renewable 21%
5%
Way Forward
Strong political will required
Tariff reforms Strict regulation on state grids
Electricity Retailing( UK, US, New Zealand) Lack of incentives to promote selling power to grid by users Implementing Smart Grids for Distribution
Automatic Fault Detection Islanding Self-healing
Efficient utilization of resources AT&C losses should be brought at par to international average Privatization of Coal sector to achieve production efficiency
Lack of planning of maintenance Under frequency relays bypassed No Automatic Demand Management System Grid Security voluntary in India, not mandatory