Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Project
Project is any work that has:
A well defined objective / goal Sequence of the multitudinous activities A specific start and end
Project Characteristics
The start is known as source and end is known as sink A project can have multiple sources (start) but will have a single sink (end)
Examples: Building of a dam, Bandra-Worli sea link, Chandrayaan, Repair of a machine etc.
Constrains to be considered are physical, human and financial resources On the basis of priority and later on available resources Analysis of technical feasibility Measurement of cost Measurement of benefits Comparison of benefits & cost
Project Management is the scientific way of planning, implementing, monitoring & controlling various aspects of a project such as time, money, materials, manpower and 3 other resources
Network Techniques
o o
Critical Path Method (CPM) Programme Evaluation & Review Technique (PERT)
Bar charts does not show relationship between jobs Charts are static Networks shows relationship in jobs and required resources
Gantt Chart
Date Activities
A 1 2 3 4 5 6 7 8
F
5
2 A
Source / Start
5 3 G
Sink /
3 3 E 6 6 I 4
Nodes
B 7 C 5
H 2 3
8 End
F 7
Problem 1
For a project consisting of several activities, the duration and required resources to carry out each of the activities and their availabilities are given below:-
Activity
Duration
Men required
Draw the Gantt chart & Resource Graph Resource availability = No of men = 50
Problem 1 contd . .
Days Activities
1-2 1-6 2-3 2-4 35 4-5 5-7 6-7 7-8 Resources 50 70 50 30
20 20 20 30 20 30 30 20 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
20
Problem 1 contd . .
Class Intervals
No of men
Problem 1 contd . .
Men
80 70 60 50 40 30 20 10
Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Problem - 2
The following table gives for each activity of a project its duration and corresponding resource requirements and total availability of each resource
Activity
Resource required
Problem 3
A project consist of 7 activities for which the relevant data are given below:
Preceding Activity
Duration
Problem 3 contd . .
Days Activities
A B C D E F G
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Problem 4 (Practice)
Draw the Gantt Chart and Resource Graph for the project schedule based on the table below
Activity
Preceding Act
Duration G H I C,D E F 5 6 6
Workers 5 4 5
Calculate total time for completion Find days of over allocation of workers if maximum available are 20
Problem 5
Duration (months)
Activity G H I 3 7 10
Assume that activity start in beginning of month and finish at end of month Draw Gantt chart and work out monthly aid and cumulative cash flows Draw S curve for cash flows
Problem 5 . . contd
Duration (months)
Activity G H I 3 7 10
Days
Activities
J
May 01 Jun 01 Jul 01 Aug 01 20 Sep 01 Oct 01 Nov 01 15 Dec 01 Jan 02 Feb 02 Mar 02 Apr 02 May 02 Jun 02 15 5 Jul 02 Aug 02 Sep 02 Oct 02 Nov 02 30 10 20 25
45 45 50 50 75 75 70 25 50 50 30 20 20 20 20 20 20 20 20 20 40 40
Problem 5 contd . .
cost Dec 02
Cumulative Cost 1000 950 900 850 850 800 750 700 650 600 550 500 450 400 350 300 250 200 150 100 50
May 01 Jun 01 Jul 01 Aug 01 Sep 01 Oct 01 Nov 01 Dec 01 Jan 02 Feb 02 Mar 02 Apr 02 May 02 Jun 02 Jul 02 Aug 02 Sep 02 Oct 02 Nov 02 Dec 02
Problem 5 contd . .
(750)
Time
Problem 6 (Practice)
Draw Gantt chart and work out monthly aid and cumulative cash flows Draw S curve for cash flows