BSC6800 System Commissioning

Review

BSC6800 system commissioning includes loading

commissioning,
interface and

License
service

commissioning,
commissioning

and
that

ultimately bring the system into normal operation after the hardware installation and software installation .

Objectives

Upon completion of this course,you will be able to: Master the loading commissioning,

License commissioning, and interface


and service commissioning .

References

31041209-BSC6800

Installation

Manual

System

Commissioning (V1.20)

Course Contents

Overview

Loading Commissioning
Feature Commissioning Interface and Service Commissioning

Prerequisite

Preparing Delivery-Attached Manuals

Checking Hardware
Checking Software Checking Network

Checking Configuration Data


Checking Peer Equipment

Prerequisite

Hardware Installation check


Hardware installation check


DIP switch and jumper check

Prerequisite

Software Installation check


Object Operating system No. 1 Item Windows 2000 Server? SP4 patch installed? Result Y[ ] N[ ] Remark If no, install the operating system according to Appendix A in Huawei BSC6800 WCDMA Radio Network Controller Installation Manual Software Installation. If no, install/upgrade the patch according to Appendix A in Huawei BSC6800 WCDMA Radio Network Controller Installation Manual Software Installation. If no, install the SQL Server according to Appendix A in Huawei BSC6800 WCDMA Radio Network Controller Installation Manual Software Installation. If no, install/upgrading the patch according to Appendix A in Huawei BSC6800 WCDMA Radio Network Controller Installation Manual Software Installation.

Y[ ] N[ ]

SQL Server

SQL Server 2000 Standard Version? SP3 patch installed?

Y[ ] N[ ]

Y[ ] N[ ]

5 BAM software 6 7 8 LMT software 9

SQL Server started? BAM version right? BAM Server started? Files to be loaded in specified directory? LMT version right?

Y[ ] N[ ] Y[ ] N[ ] Y[ ] N[ ] Y[ ] N[ ] Y[ ] N[ ]

Prerequisite

Network Communication check


Object Network configuration of BAM Server No. 1 Item Network adapters teamed? IP setting right? IP setting right? Result Y[ ] N[ ] Remark If no, team the network adapters according to Appendix A in Huawei BSC6800 WCDMA Radio Network Controller Installation Manual Software Installation.

2 3

Y[ ] N[ ] Y[ ] N[ ]

Network configuration of LMT computer Internal network

BAM and WMPU in normal communication?

Y[ ] N[ ]

External network

LMT and BAM in normal communication?

Y[ ] N[ ]

Procedure

system commissioning procedure


Start

Loading commissioning

Feature commissioning

Interface and service verifying

End

Course Contents

Overview

Loading Commissioning
Feature Commissioning Interface and Service Commissioning

Introduction

loading commissioning procedure


Start

Set loading channel

Generatedata f iles

LoadFAM sof tware

Check loading

End

Introduction

FAM software loading channel

WMPU Other boards in WRSS WRSS Program files Data files BAM Boards in WRBS WMUX/WSPU WRBS

Setting Loading Channel


The loading channel is a LMT-BAM-WRSS-WRBS channel Setting BAM-WRSS Channel

Carry out SET WMPUIP to set the external IP address of the WMPU

Setting Routes for BAM (default)

Route No.
1 2

Network address
80.0.0.0 192.1.0.0

Netmask
255.0.0.0 255.255.0.0

Gateway address
10.121.A.C 10.121.A.C

Interface
10.121.A.B 10.121.A.B 1 1

Metric

Generating Data Files

The program files have come into being in the BAM Server since BAM software installation. You need generate the data files for loading

You may prepare a Man Machine Language (MML) script of the configuration data (data script) and then generate data

files from the script for loading in offline mode


checking Data script Data Script Execution Carry out FMT DATA to generate the data files for loading

Generating Data Files


Host software of the WRSS

Board WMPU WNET WLPU MPUB.VFS NETB.VFS, CLKC_LOG.VFS LPUBGFI.VFS

Host software

WHPU

WHPU750.VFS, WHPU1200.VFS, WHPULOGC.VFS, WHPUWC.VFS

Generating Data Files

Data file of the WRSS

The data file to be loaded to the WRSS is BNET.dat. When you


prepare a load data file, BNET.dat will be created and saved in the new folder Config under the directory LoadDATA

To load a data file to the WRSS is right to load BNET.dat to the WMPU

Generating Data Files


Host software of the WRBS
Board WMUX B00MUX0.bin Host software

WSPU
WSPUb WFMR WXIE WOSE/WOME WBIE/WTIE

B00SPU0.bin
B00EPU0.bin B00FMR0.bin, B00FMR0.dsp B00XIE0.bin B00OIE0.bin B00BIE0.bin

Generating Data Files

Data file of the WRBS

The data file of the BSC6800 system is stored as ".dat" file in


the BAM server, When receiving a data load request from a board subsystem, the server will load the corresponding data file to the subsystem

Such data files include the configuration data that will be stored on the WMUX or on the WSPU

The file name of the data file is in the format of HXYABCN.dat

Loading FAM Software

Setting Loading Mode of Program File

Carry out SET LODPARA . Select "WRSS or "WRBS" FLASH)" for [Host code load control]

for

[Subrack Type] and "FLWF (FORCEDLY LOAD AND WRITE

The program files will be loaded from the BAM Server and written to the Flash Memory of the corresponding boards when

the boards start or reset.

Checking Loading

Checking Board State


On the equipment panel

Through an MML command: DSP BRD

The BSC6800 contains two sets of configuration parameters that respectively exist in FAM and BAM. They are both in tables

Carry out ACT CRC to check the data consistency on table level Carry out CMP TBLDATA to check the data consistency on record level

Check that the cell setup procedure, common channel setup


procedure and measurement messages are all normal through the message tracing on a LMT

Course Contents

Overview

Loading Commissioning
Feature Commissioning Interface and Service Commissioning

Introduction

Function of License file


Feature Max. number of users Inter-RAT handover out-going switch Inter-RAT handover in-coming switch Description Max. number of users allowed in the BSC6800 Inter-RAT handover between GSM and WCDMA (from UMTS to GSM) Inter-RAT handover between GSM and WCDMA (from GSM to UMTS) The BSC6800 can perform PDCP header compression to increase the connection rate. Location services based on Cell ID Location services based on OTDOA Location services based on A_GPS The following optimization means are provided, that is, cell breathing, load handover and potential user control. The BSC6800 can control the AMR encoding rate to provide the best speech quality, increase inverse cell coverage and reduce system load.

No. 1 2 3

4
5 6 7 8

PDCP header compression function


Cell ID LCS OTDOA LCS A_GPS LCS Load optimization

AMR control

Introduction

Function of License file

10

TFO/TrFO

TFO: Speech information is not coded using code converter if UEs in a mobile-to-mobile call support the same code type as the network. TrFO: The BSC6800 involved in a mobile-to-mobile call supports speeches or multimedia services in TrFO mode. Bandwidth resources can be allocated flexibly to satisfy the requirements of burst PS services. The services can be handed over between dedicated and common channels so that the resources can be fully utilized. On setup of an Radio Resource Control(RRC) connection, the BSC6800 can specify a cell for the User Equipment(UE) to access according to the resource status to increase the access success rate. Message trace and interpretation on standard Iub, Iur, Iu and Uu interfaces, single subscriber trace and cell trace Cell broadcast service

11

Dynamic channel configuration control

12

Direct retry

13 14

Call trace Cell Broadcast Service(CBS)

Introduction

Commissioning Procedure
Start

Import License file

Activate License file

N Feature controlled by algorithm switch? Y Set algorithm switch of feature

End

Importing License File


Import a correct License file as prompted during BAM installation Otherwise, copy the License file to the following directory:

BAM installation directory\LICENSE BAM installation directory\FTP\LICENSE

Activating License File

Activating License File with Reconfiguration of RNC ID and PLMN ID

Carry out SET OFFLINE to switch to the offline mode, and then
reconfigure the RNC ID and PLMN ID accordingly
If the BSC6800 has no basic information, carry out ADD RNCBASIC to add the RNC ID and PLMN ID If the basic information of the BSC6800 is not authorized in the License file, carry out MOD RNCBASIC to modify the RNC ID and PLMN ID as those presented in the License file

Carry out ACT LICENSE to activate license file. BAM will check validity of the file. If valid, the file will be written into the memory of

BAM

To activate the License function in the FAM, carry out RST SYS to reset the BSC6800 system

Activating License File

Activating License File without Reconfiguration of RNC ID and


PLMN ID

Carry out SET ONLINE to switch to the online mode Carry out ACT LICENSE to activate license file. BAM will check validity of the file. If valid, the file will be written into the memory of BAM

Setting Algorithm Switch of Feature


Carry out SET CORRMALGOSWITCH to set an algorithm switch You may set the following classes of algorithm switches using the command:

Channel class algorithm switch Handover algorithm switch

Power control algorithm switch


Traffic combination switch

Course Contents

Overview

Loading Commissioning
Feature Commissioning Interface and Service Commissioning

Introduction

You need also perform commissioning for interface data and dialtests for system services before you put the BSC6800 into normal service

Iub Interface Commissioning

Physical Link Commissioning

Local loop
Set the loopback type of a test E1/T1 link as LOCAL on a LMT using:
SET E1T1LOP if the E1/T1 link is on an E1/T1 trunk SET SDHLOP if the E1/T1 link is on an SDH

Carry out LOP E1T1 on the LMT to initiate a local loopback test for the E1/T1 link Set the loopback type of the test E1/T1 link as NOLOOP on the LMT When performing a loopback test for an E1/T1 link in an IMA group, be

sure to carry out RST IMAGRP to reset the IMA group after the loopback
test

Iub Interface Commissioning

Physical Link Commissioning

Combined loop
Set the loopback type of a test E1/T1 link as REMOTE in the operation and maintenance system at the peer end Carry out LOP E1T1 on a LMT to initiate a combined loopback test for the E1/T1 link.

Iub Interface Commissioning

Control Plane Commissioning

Carry out DSP SAALLNK to check that all Signaling ATM Adaptation Layer (SAAL) links are available

Carry out DSP IUBP to check that the NCP link and all CCP links are

available

Carry out DSP AAL2ADJNODE to check that the adjacent node of NodeB is available

Iub Interface Commissioning

User Plane Commissioning

Carry out DSP AAL2PATH to check that the AAL2 path(s) to a specified adjacent node is/are functional

Iu Interface Commissioning

Physical Link Commissioning Control Plane Commissioning


Carry out DSP SAALLNK to check that all SAAL links are available. Carry out DSP MTP3BLNK to check that all MTP3b links are available. Carry out DSP SSN to check that all SCCP subsystems are available.

Carry out DSP AAL2ADJNODE to check that the adjacent node of


MSC is available.

User Plane Commissioning

Iur Interface Commissioning

The commissioning of an Iur interface is similar to that of an Iu interface.

You need also check that the IP routes of the BSC6800 to other Radio Network Controllers (RNCs) are available for supporting lossless relocation. Carry out PNG IPADDR on a LMT to check the

connectivity of an IPoA to another RNC

Service Commissioning

Dial-tests for basic services


Basic service Dial-test method Make fifty calls from a UE to a fixed network phone. Make fifty calls from the network phone to the UE. Make fifty calls from a UE to another UE. Send a fax from a UE to the PSTN. Send a fax from the Public Switched Telephone Network(PSTN) to the UE. Send a video service from a UE to another UE Activate 384-kbit/s and 144-kbit/s services, visit World Wide Web(WWW) Server and browse pages on a UE fifty times. Expected results The connection success rate is above 90%. The calls sound clear. There is no loud noise in the calls. The connection success rate is above 90%. The calls sound clear. There is no loud noise in the calls. The UE sends and receives the faxes normally. The audio part sounds clear. The visual part is continuous. The two parts are synchronous. The activation success is above 90%. The browsing is successful. The download is not intermittent. The average download rate reaches 300 kbit/s or above. The handover success rate is above 95%. The handover success rate is above 95%. The switchover success rate is above 90%. There is no service interruption in the switchover procedures.

Voice service

CS streaming service

PS service

Activate 384-kbit/s and 144-kbit/s services and perform download some data using FLASHGET on a UE for half an hour.
Perform CS voice service handover fifty times. Perform PS service handover fifty times. Perform switchover for the WMPUs, WMUXs and WSPU/WSPUbs fifty times during service

Mobility management Operation and maintenance management

Service Commissioning

Dial-tests for features

Feature

Dial-test method

Expected results The connection success rate is above 90%. The calls sound clear. There is no loud noise in the calls.

Inter-RAT handover

Hand over a dual-mode UE from UMTS to GSM and back fifty times.