Lecture Objectives, by the end of this lecture, YOU should be able to:
- Explain what is the P.I. (Productivity Index) - Explain what is the A.O.F. (Absolute Open Flow) and how to determine it for OIL & GAS wells.
FTC - SWT 3/4/2013
PRODUCTIVITY INDEX:
Productivit y
P.I.
Q (Pi Pwf)
That means , the well produced 3 bbls STO per day, per each psi of drawdown.
FTC - SWT 3/4/2013
Productivit y
MAXIMUM FLOW POTENTIAL or ABSOLUTE OPEN FLOW :
The rate at which a well would produce at a zero sandface (bottom-hole) back pressure.
(This rate cannot be measured and probably not achieved.)
Productivit y
OIL WELL (AOF) Plotting BHP v/s Q on a linear plot gives the Maximum Flow Potential or AOF.
Productivit y
psi bopd Pwf1 4000 2000
4000
Pwf2 3000 3000 Press. & Temp. dropped, oil & gas will separated
2000
bopd
FTC - SWT 3/4/2013
2000
3000
Productivit y
Productivit y
GAS WELL (AOF) Plotting pressure squared difference v/s flowrate on a log-log plot gives the Maximum Flow Potential or AOF. [(Pi2-Pwf2), PSIA2] v/s [SCFD]
GAS WELL (AOF) Deliverability Tests: To determine flow capacity and to predict flowrate decline over the life of the well.
Productivit y
Gas well with AOF > 50 MMSCFD are classified as HIGH Productivity Wells.
Gas well with AOF < 50 MMSCFD are classified as LOW / AVERAGE Productivity Wells.
FTC - SWT 3/4/2013
HIGH Productivity Gas Wells A.O.F. BACK PRESSURE TEST Clean-up, from a few hours to 24 hr. Initial Shut-in, twice the duration of the Clean-up4 different rates with stabilization on Flow at each chokes, from 4 to 8 hr on each choke. Final Shut-in, from 12 to 24 hr.
Productivit y
Note: There is stabilization when: (delta P) < 0.1% WHP, every 30 min.
FTC - SWT 3/4/2013
LOW Productivity Gas Wells A.O.F. ISOCHRONAL PRESSURE Clean-up, from a few hours to 24 hr. TEST
Productivit y
Initial Shut-in, twice the duration of the Clean-up4 rates of equal duration (4 to 8 hr) Flow at with stabilized Shut-in periods between flow (6 to 12 Final flow (4th), extends until The hr). stabilization. from 34 to 72 hr. Final Shut-in,
FTC - SWT 3/4/2013
LOW Productivity Gas Wells MODIFIED ISOCHRONAL PRESSURE TEST Clean-up, from a few hours to 24 hr. Initial Shut-in, twice the duration of the Clean-up4 rates of equal duration (4 to 8 hr) Flow at with Shut-in equal periods between flow, no matter if stable pressure has been reached or not. Final flow (4th), extends until The stabilization. from 34 to 72 hr. Final Shut-in,
FTC - SWT 3/4/2013
Productivit y A.O.F.
LOW Productivity Gas Wells MODIFIED ISOCHRONAL PRESSURE TEST - The modified isochronal test if shorter than the isochronal test because there is no need to wait for stabilization (apart for the last flow).
Productivit y A.O.F.
Productivit y
- Recent software products available for WT data interpretation, offer greater flexibility of test programme needs.
- The traditional approach such as Back Pressure & Isochronal Test can be modified to reduce the numbers of flow, and hence the overall timing of the test.