Writing your SAP BI business case and determine global architecture Defining the global scope of your implementation Writing a milestone plan Developing your global staffing plan Budgeting On-boarding, training and global staffing issues Writing your workplan Monitoring the progress and risk of your global project Monitoring quality / instituting a formal approval process Why you need an SAP BI user acceptance group
2
In Part 2
Leveraging the standard content Modeling for your solution Deliverables Best practices for managing the implementation of ODS and InfoCubes Managing the environments and transports Managing unit, system, integration & stress testing of SAP BI Executing the cut-over to production Conducting end-user and power user training Establishing the end-user support organization Post-implementation review and next steps
3
Writing your SAP BI business case and global architecture Identifying your requirements, scope, and plan-of-attack Staffing your project: lessons and examples Budgeting: how much? and for how long? Final preparations: on-boarding, writing the workplan, etc. Wrap-up
The business case must be aligned with some concrete multi-national business benefits The best way to write a business case is to align it with one of these areas:
Money Strategy Reducing time and effort of delivery Improved information quality and access for end users
Observation
Maintaining a custom developed BI solution is complex and expensive. Updating extract programs when upgrading R/3 is expensive. Web delivery requires rapid data delivery of high consistency with the source system.
SAP BI BW
SAP is responsible for maintenance of the product. BW R/3 integration points are maintained and tested by SAP
Benefit
Substantial maintenance cost savings
Substantial cost savings, by not having to redevelop new extract programs for each SAP upgrade
Cost Avoidance
Web strategy
BW is closely integrated Enables web initiatives to get with R/3, and can deliver closer to the source data, data that reflects the both in time and consistency. source system at short time intervals. BW is closer to the Users spend less time on source system, and more reconciling data, and more accurately reflects data time analyzing it.
Reconciliation Effort
Information Access
Load times in BI are less than traditional, custom- developed data warehouses
Observation
Need to increase time to deliver new applications and enhancements existing areas
SAP BI
Benefit
Typical use of 60-80% Reduced development of pre-delivered time for new decision content increases support areas development speed SAP BI is the cornerstone of SAPs New Dimension product offerings Through use of summaries, TREX, and the new accelerator, SAP BWs architecture lends itself to faster query performance Enables closer integration with other SAP modules
Integrated Products SAP continues to offer new products and modules that the organization might wish to leverage in the future Query speed Business users need fast access to their data
Users get the data they need quickly to perform their job functions
Observation
It is the organizations SAP strategy to leverage investments in the SAP to the fullest extent, and maximize SAP resource utilization. The organization must be able to leverage industry standards to enable business users to access data in a variety of ways The organizations competitors and some of the organizations business areas are installing SAP BI
SAP BI
SAP BI is a SAP product, and is based on standard SAP NetWeaver technologies (Basis, ABAP, etc.)
Benefit
Strategic fit and synergy with SAP. SAP Basis, ABAP, etc. resources can be used across SAP projects, including SAP BW. Simplifies user access to data, expands options for using standard presentation and web tools, or developing your own. Enables the organization to leverage industry solutions and know-how.
Tool Standardization
Microsofts ODBO application interface and Java (SAP BI 3.5) are supported by a variety of major presentation and web tools. Increased industry resource pool and knowledge of SAP BW
Industry Trend
Real-time Inquiry
Operational Reporting
ERP
DW
Dividing Line
Five years ago, with version 3.0B, BI became increasingly able to report on operational detailed data. But some reports still belong in R/3 or other transactions systems
9
Extract
Transform
Data Warehouse
Access
Managed Query Env.
OLAP
Calculate
Attribute Synchronize Reconcile
Internet
Vendor Provided
Data Marts
Writing your SAP BI business case Identifying your requirements, scope, and plan-of-attack Staffing your project: lessons and examples Budgeting: how much? and for how long? Final preparations: on-boarding, writing the workplan, etc. Wrap-up
11
CONTINUE
Build a global data warehouse for the company, and proceed sourcing local data from old legacy systems driven from a top-down approach.
Focus on a bottom-up approach where the BI project will prioritize supporting and delivering local BI solutions, thereby setting the actual establishment of the global Data Warehouse as secondary, BUT not forgotten.
CHANGE
12
For each dimension, articulate an approach, constraints, limitations and assumptions before you start your project.
13
Culture, language, attitudes and politics can get in the way of a global project Make sure you have a blend of local resources in leadership roles and consider local consultants instead of bringing in US resources
14
Infrastructure Prerequisites
What happens if the data movement fails? How can you get access to backup tapes? Can the bandwidth handle end-of month high volumes? What infrastructure do each source site use?
15
Training
Documentation
2. Does basic conversational English mean that users can read and understand technical training material and documentation?
3. Have you installed Unicode on your BI system?
16
One of the first steps is to gather the right requirements. This is done in a variety of ways, depending on which methodology you employ. It is a complex process involving:
1.
2. 3. 4.
An SAP NetWeaver implementation involves more than just black-and-white technical decisions; just because something is technically feasible, doesnt mean it is wise or desirable from a business perspective.
17
First, determine what the local and shared business drivers are, and make sure you meet these objectives. Define the scope in terms of what is included, as well as what is not included, make sure everyone is at least heard. In some cultures, process is as important as outcomes. Make sure you obtain approval of the scope before you progress any further. All your work from now on will be driven based on what is agreed to at this stage. As part of the written scope agreement, make sure you implement a formal change request process. This typically includes a benefit-cost estimate for each change request and a formal approval process.
Note
Change management is done to manage scope, timelines and competing business requirements. Put in place a process for capturing feedback & requests. 18
Resources
(people, technology and money)
Time
Warning
If one of these dimensions changes, you have to adjust at least one of the others
19
Plan multiple implementations, and write a long-term outline. Control change with a formal change request process.
20
Selecting A Methodology
i.e., when time-to-delivery is moderate, or when the impact of failure is moderate. Also be aware of local variations of the methodologies
The diagram is intended to illustrate the differences among the appropriateness of each methodology. The decision is clearer in the extreme. In practice, however, there are gray zones where more than one answer may be correct.
Time to Delivery
Low Low
High
Impact of Failure
21
August
8/13 8/20 8/27
September
9/10 9/17 9/24 10/1 9/3
October
10/15 10/22 10/29 10/8
November
11/12 11/19 11/26 11/5
Dec.
12/10 12/3
Environments
Post this plan on the walls and in the hallways of ervyone affected. Dont hide it in the PM's office in a different country. Keep it under 30 items
Wrap Up
BI Environment install & verification BI Accelerator Install & verification Portal Environment install User security migration and testing PCA ODS and Cube creation G/L line item ODS and Cube creation Data loads Query replication Data validation Query validation Testing and demo Scope definition Blueprinting Realization Testing and demo Scope definition Blueprinting Realization Testing and demo Scope definition Blueprinting Realization Testing and demo Scope definition Realization Testing and demo Scope definition Blueprinting Realization Testing and demo Scope definition Blueprinting Realization Testing and demo Address outstanding issues Re-testing Outstanding items & lessons learned
22
Writing your SAP BI business case Identifying your requirements, scope, and plan-of-attack Staffing your project: lessons and examples Budgeting: how much? and for how long? Final preparations: on-boarding, writing the workplan, etc. Wrap-up
23
Option
1 2 3 4 5 6
Benefits
Risks
Single site Distributed analysis Distributed analysis and design Co-located analysis and design Multiple co-located analysis and design Fully distributed development
The more distributed the SAP BI development effort becomes, the more difficult it is to maintain communication and get cohesive requirements.
24
Developer training should start early for all project team members
SAP R/3 skills are not easily transferable to SAP BW
Note
Hands-on experience is needed Its very hard to learn while being productive
The quality of the team members is much more important than the number of members
An experienced SAP BI developer can accomplish in one day what 3 novice developers can do in a week The tool has a steep learning curve
25
Project time and cost estimates should be based on teams experience level
(we will take a second look at this when we do the budgeting!)
Make a list!
26
crossing 4 or more time zones need over 36 hours to adjust! This increases to over 72 hours when crossing 6 or more time zones. Some simple rules to address this:
Create a "project time" in the middle. I.e. for European and US projects, middle time would be Eastern US time +3 hrs, and European central times less 3 hours. No meetings would be scheduled between 8-11am in Europe, nor between 2-5pm in the US.
Source: Leveraging resources in global software development Battin, Crocker, Kreidler, Subramanian, Software, IEEE
Fly to the destination the day before, or allow at least 4 hours downtime for sleeping and showering at the hotel. Dont schedule meeting times around when people are traveling. Keep each trip over 5 days minimum to adjust for sleep, or risk running the team "into the ground" Plan extended weekends for family time for staff after a long trip (including consultants)
27
Project sponsor Project Manager Business team Business analyst Presentation developer Technical team
4-5 team members and normally 3-6 months duration depending on scope
28
E.g., Global Cost and Profitability, international cross organization or consolidated billing
Project sponsor/ Steering Committee Project Manager SAP BW Architect Business Analyst(s) Extract, Transforms and Loads Data Management (InfoCubes & ODS) Presentation Developer(s) Sr. Presentation developer Presentation developer
Note: These are roles, not positions (sometimes one team member can fill more than one role)
Basis and functional R/3 support 8-10 team members and normally 2-4 months duration depending on scope 29
Project Manager SAP BI Architect Portal developer(s) Sales Team Finance Team
Note: These are roles, not positions (sometimes one team member can fill more than one role)
30
Independent (38%)
30% Successful
31
Writing your SAP BI business case Identifying your requirements, scope, and plan-of-attack Staffing your project: lessons and examples Budgeting: how much? and for how long? Final preparations: on-boarding, writing the workplan, etc. Wrap-up
32
1. 2. 3. 4.
2. Start the budgeting process by estimating the workload in terms of the development effort. Refine based on the teams skill experience and skill level
33
L M L M L M L L L L L L L L L M M M M
Financials General ledger line item (ODS) COPA Prod cost planning released cost estimates (COPC_C09) Exploded itemization standard product cost (COPC_C10) Cost and allocations (COOM_C02) Cost object controlling (0PC_C01) Order Billing Sales order Acct. Rec. (0FIAR_C03) Deliver Shipment cost details (0LES_C02) Shipment header (0LES_C11) Stages of shipment (0LES_C12) Delivery data of shipment stages (0LES_C13) Delivery service (0SD_C05) Planning and Scheduling Material Movements (0IC_C03) APO Planning SNP Integration Manufacturing Processes Production Orders Cross Applications Total Hours
216 158 216 238 216 238 216 216 216 216 216 216 216 180 216 277 277 277 277 4,298
229 286 229 286 1144 286 229 229 229 229 228 228 228 229 457 832 832 832 832 8,074
188 153 188 216 188 216 187 187 187 187 187 187 187 133 132 216 216 216 216 3,587
101 127 101 126 101 137 101 101 101 101 101 101 101 101 101 127 127 127 127 2,110
132 153 133 153 132 153 132 132 132 132 132 132 132 132 132 153 153 153 153 2,656
134 152 135 152 135 152 135 135 135 135 135 135 135 134 134 152 152 152 152 2,681
100 120 100 120 100 120 100 100 100 100 100 100 100 100 100 120 120 120 120 2,040
79 94 79 94 79 94 79 79 79 79 79 79 79 79 79 94 94 94 94 1,606
150 180 150 180 150 180 150 150 150 150 150 150 150 150 150 180 180 180 180 3,060
403 470 403 470 403 470 403 403 403 403 403 403 403 403 403 470 470 470 470 8,126
1,732 1,893 1,734 2,035 2,648 2,046 1,732 1,732 1,732 1,732 1,731 1,731 1,731 1,641 1,904 2,621 2,621 2,621 2,621 38,238
Remember that your sizing also has to be based on the teams experience and skill level.
34
The next step is to prioritize and outline the effort on a strategic timeline
Make sure your sponsor and the business community agree with your delivery schedule
35
3. Use Project Estimates & the Timeline to Create Project Load Plan
2005 qtr 1 Financials General ledger line item (ODS) 866 COPA 946.5 Prod cost planning released cost estimates (COPC_C09) Exploded itemization standard product cost (COPC_C10) Cost and allocations (COOM_C02) Cost object controlling (0PC_C01) Order Billing Sales order Accounts receivables (0FIAR_C03) Deliver Shipment cost details (0LES_C02) Shipment header (0LES_C11) Stages of shipment (0LES_C12) Delivery data of shipment stages (0LES_C13) Delivery service (0SD_C05) Planning and Scheduling Material Movements (0IC_C03) APO Planning SNP Integration Manufacturing Processes Production Orders Cross Applications Total 1,813 qtr 2 qtr 3 qtr 4 qtr 1 qtr 2 2006 qtr 3 qtr 4 qtr 1 2007 qtr 2 qtr 3
866 947 867 1017.5 1324 1023 867 1017.5 1324 1023 866 866 866 866 866 866 866 865.5 865.5 865.5 820.5 866 865.5 865.5 865.5 820.5 952 1310.5 1310.5 952 1311 1311 1311 1311 1,311 1,311
1,732 1,893 1,734 2,035 2,648 2,046 1,732 1,732 1,732 1,732 1,731 1,731 1,731 1,641 1,904 2,621 2,621 2,621 2,621
1,813
4,232
4,232
2,598
2,598
4,283
4,283
3,573
6,195
2,622
38,238
Note
There are 480 available work hours per project member per quarter. Knowing this, we can plan the number of team members we need NOTE: Remember to plan for different vacation schedules (i.e. in Europe a 3-4 weeks vacation is not unusual).
36
Tip
Many companies plan a 60%- 40% mix of internal and external resources for a first go-live. Also, most use $50-$90 per hr for internal budgeting and $90-$170 per hr for external resources.
37
Writing your SAP BI business case Identifying your requirements, scope, and plan-of-attack Staffing your project: lessons and examples Budgeting: how much? and for how long? Final preparations: on-boarding, writing the workplan, etc. Wrap-up
38
Training days In-house (if new in the training role) days 15 3-5 15-20 5-10 10-15 5-10 3-5 3-5 3-5 3-5
Dont underestimate the value of in-house, hands-on training in addition to formal SAP training classes.
Note
It is also important to provide technical training to the team members in their own language and this is normally best done in their respective countries, 39
A sample workplan can be downloaded from the SAP Best Practices for BI web site
40
ID
TASK
1 SAP Best Practices BI Implementation Roadmap - read Notes 11 Blueprint Phase & Planning Phase 12 Apply for Going Live Check 13 Finalize Project Scope [selected scenarios] 14 Check Content delivered by Best Practices 15 Determine those issues affecting BW Implementation and assign risk to project 16 Present Final Scope to Customer and Get Signoff of Scope 17 Project Planning Phase 18 Set Up Development Environment 19 Define transport Strategy 20 Activate TMS 21 Define Project Organization and Create Teams 22 Analyze Roles and Tasks by Standard Content Areas and Technical 23 Update delivered Project Plan & finalize, including resources assignments 24 Define customer rollout & training strategy for SAP BW 25 Define types of users of the BW 26 Determine Number of users for BW 27 Determine Data Access Requirements
The Workplan
1. 2. 3.
400 to 1000 line-item workplans are not unusual for mid-size and large SAP BI implementations
Write a detailed workplan that references the methodology. Make sure the workplan is detailed enough to track project progress. Progress can be measured by hours used, vs. % of tasks completed.
More Details on workplan writing available here: Writing Solid and Realistic Work Plans for a SAP BI Implementation Project, SAP Project Mgmt Conference 2005,http://cscstudentweb.lrc.edu/swp/Berg/articles/PM05_Berg_Writingasolid.ppt
2-Jun
41
Source: Planning and improving global software development process by Setamanit, Wakeland, Raffo, May 2006, international workshop on Global software development
Recent research have demonstrated that global projects that spends more days (duration) on similar tasks, have less defects and less re-work. Since team members are more likely to work on multiple tasks not related to the project, longer durations on developing the SAP BI system does not mean more effort (i.e. work hours).
42
A - Assumptions (what assumptions are made, and what happens when these assumptions are no longer true?) R - Risks (what are the risks created by this approach, what are the impacts of failure, and how can these risks be minimized)
Developers, designers and business analysts should be forced to write at least one paragraph on each of these item. It forces new thinking as well as the constant questioning of assumptions (which may not be accurate).
43
Source: Leveraging resources in global software development Battin, Crocker, Kreidler, Subramanian, Software, IEEE
Having IT people engaged in SAP BI global development without providing the right infrastructure, approach and management is a recipe for failure
44
Create a formal escalation process of issues related to the project and make sure one culture does not dominate. Select a project language formally and make sure all team members are proficient in it.
Spend time rewarding inter-team cooperation and create opportunities for promotion within and outside both teams (cross pollinate)
45
Monitoring Progress
Note
Manage the workplan from a percent complete standpoint on a weekly basis Create weekly status reports with core progress metrics and send to all team members (keep it high-level and tangible) Require monthly status reports from all team members in a fixed format Keep a close eye on the deadlines for the deliverables and make to follow-up personally on late tasks Track percent complete tasks in the workplan against the number of hours, or days worked, to see if you are on-track.
SAP BI is a complex environment that has many dependencies. Late tasks can have significant impacts on the overall project.
46
Warning
System Testing
Complete? Yes
Complete?
Yes
Unit Testing
Yes
Peer Review
No
Approved?
Complete? No
Yes
Structured walkthrough
No Complete? Yes
Structured walkthrough 47
Create a user acceptance team consisting of 5-7 members from the various business departments or organizations
Keep the number odd to assist with votes when decisions need to be made. With fewer than 5 members, it can be hard to get enough members present at each meeting Make this team the focus of your requirements gathering in the early phase, then let this team perform user acceptance testing during the Realization phase Meet with the team at least once a month during realization to refine requirements as you are building, and have something to show them
This approach is hard to execute when also managing scope, but is I essential to make sure that the system meets users requirements s s u e
48
Writing your SAP BI business case Identifying your requirements, scope, and plan-of-attack Staffing your project: lessons and examples Budgeting: how much? and for how long? Final preparations: on-boarding, writing the workplan, etc. Wrap-up
49
Resources
http://csc-studentweb.lrc.edu/swp/Berg/BB_index_main.htm
50
Write the business case around the areas of greatest benefit to more than one user community - think globally act locally!!
Define your scope in-terms of what is included, and state what is not included and make it clear to everyone from the start
Establish a formal global change control process that is well communicated and that have instruments for capturing feedback
Plan your global project based on the hours required for the effort, and the project teams experience and skill levels. Add 15% more time than you would for a local project.
51
Establish milestone dates, and map the work hours required to these dates. Include local vacation schedules and holidays. Be sensitive to local work practices and don't 'enforce' your management style on the team (accept diversity). Establish a formal global on-boarding plan for project resources and make sure they receive appropriate training. Establish a formal process for quality control and approval of deliverables. Communicate often and spend time on team building activities.