engr_zaheer@uet.edu.pk LECTURE # 7
Process Description
Learning Objectives
After you have completed this section you will be able to: Use Compressors in Aspen HYSYS Use Recycle Operation in Aspen HYSYS
1) Component List
Nitrogen CO2 Methane Ethane Propane i-Butane n-Butane i-Pentane n-Pentane n-Hexane
Propane
0.0725
n-Hexane
0.0357
8
1. Installing a Mixer
Connections Name Inlet Outlet Parameters Pressure Assignment Equalize all Mixer 1 To Compression To LP Sep
10
2. Installing a Separator
Connections Name LP Sep
Inlet
Vapor Outlet Liquid Outlet
To LP Sep
LP Sep Vap LP Sep Liq
11
3. Installing a Compressor
Connections
Name Stage 1
Inlet
Outlet
LP Sep Vap
Stage 1 Out
Energy
Parameters
Stage 1 HP
Adiabatic Efficiency
Worksheet
75% (Default)
3450 kPa
12
4. Installing a Cooler
Connections
Name Stage 1 Cooler
Inlet
Outlet
Stage 1 Out
Cooler 1 Out
Energy
Parameters
Stage 1 Q
Pressure Drop
Worksheet
0 kPa
50C
13
14
6. Installing Separator
Connections Name IS Sep
Inlet
Vapor Outlet Liquid Outlet
To IS Sep
IS Sep Vap IS Sep Liq
15
7. Installing a Valve
Connections Name Inlet Outlet Worksheet LD1 Out, Pressure 1725 kPa Let Down 1 IS Sep Liq LD1 Out
16
Inlet
Outlet
IS Sep Vap
Stage 2 Out
Energy
Parameters
Stage 2 HP
Adiabatic Efficiency
Worksheet
75% (Default)
6900 kPa
17
Inlet
Outlet
Stage 2 Out
Cooler 2 Out
Energy
Parameters
Stage 2 Q
Pressure Drop
Worksheet
0 kPa
50C
18
Inlet
Vapor Outlet Liquid Outlet
Cooler 2 Out
HP Sep Vap HP Sep Liq
19
20
21
EXERCISE