Demonstration Panel
October 12, 2007
Underdrains
Inlet Detail
Observation Wells
Work In Progress
(1) Tennis, P.D., Leming, M.L., Akers, D.J., Pervious Concrete Pavements, Portland Cement Association, PCA Serial No. 2828, 2004, page 8
Figure A7.5.1, ACI 211.3, M inimum void content for percolation based on NAA-NRMCA tests and test methods
Percolation, in/min = 5.684*10
-7
*(void content,%)
5.3034
Proctor - 20 Blows
C 29 Jigging
C 138 Rodding
Usable Voids vrs. Gravimetric Voids Effective Porosity vrs. Total Voids
Usable Voids, % = 0.898 * (Gravimetric Voids, %) 3.1
A 4 inch thick pervious pavement with 15% usable (effective) voids will store 0.60 inches of rainwater (4 * 0.15 = 0.60)
10
15
20
25
30
35
No. 8 Coarse Aggregate No. 67 Coarse Aggregate Figure A7.5.2, ACI 211.3, Relationship between void content and 28-day compressive strengths for No. 8 and No. 67 coarse aggregates
No. 8 Coarse Aggregate fc = 6,526 - 193.7 * (void content, %) No. 67 Coarse Aggregate fc = 5,657 - 170.7 * (void content, %)
psi
psi
25
30
35
Pavement Serviceability AASHTO Road Test Relationship between serviceability and load repetitions
ACI 330 Guide for The Design and Construction of Concrete Parking Lots
Frost Heave
Frost Penetration Depth in MD = 30 FAA recommends 65% of the frost depth contain non-frost-susceptible material For 30 FPD, depth of pervious material (concrete plus base) shall be 20 inches
Conclusions
Failure due to freeze-thaw cycles are the result of aggregate deterioration or cement paste matrix failure Sand, latex and air entrainment admixture improved freeze-thaw durability
Suggested Methods to Improve Cold Weather Durability Use 8 to 24 of Open Graded Base
Use Sound Aggregates Use Air Entraining Admixture Use 5 to 10% Fine Aggregate Place perforated PVC pipe in base to capture and remove water
Pre-paving Conference
Within two weeks of first placement In attendance: Owners Representative Contractor Concrete Supplier Concrete Foreman Testing Agency
Test Panel
Minimum 225 ft2 Use proposed mix design and materials Use proposed placement equipment Include at least one typical joint
Test Panel
Fresh density: with +/- 5.0 lb/ft3 Three cores: average thickness not more than less or 1.5 more than specified thickness Single core: not more than less than specified thickness
Testing Thickness
Average of three cores more than 1-1/2 greater than specified thickness No single core more than less than specified thickness
Testing Thickness
Three cores per 5,000 ft2 Average of three cores not more than less than specified thickness
Subgrade Preparation
Maintain final subgrade elevation Permeability testing: Portland Cement Association recommends: Soils with a percolation rates of in/hr. ASTM D 3385, Double-ring Infiltrometer testing Subgrade support: minimum density of 92% maximum dry density Subgrade in moist condition within 3% of optimum moisture content
Base Materials
Open graded aggregate 30% to 40% void content Elevation of base shall be maintained during placement of concrete.
Concrete Materials
Comply with ASTM C 94 Aggregates Max. size 1/3 thickness Aggregates Use 3/8 maximum size Admixtures for controlling hydration may be used and facilitate handling of plastic concrete
Curing Material
Clear 6 mil or thicker polyethylene Not acceptable: Woven materials, such as burlap and geotextile fabric Wax-based curing compounds
Forms
Height equal to the thickness of the pavement Held in place by stakes and braced to prohibit movement from pressure of concrete and thrust of machinery
Setting Formwork
Utilize form release agent May use previously placed pavement Limit placement width to 20 feet
Tolerances
Elevation: +3/4, -0 Thickness: + 1-1/2 , - Contraction joint depth: +1/4, - 0
Contraction Joints
Joints as shown on plans or as approved to 1/3 pavement thickness Early-entry dry-cut saw: 1 minimum
Contraction Joints
Spacing not exceed 20 feet Aspect ratio: 125% maximum
Contraction Joints
Angle at intersections: 80o to 100o Intersect free edges at 90o, 1.5 lap
Contraction Joints
Align with curb joints within
Curing
Begin curing with 20 minutes of concrete discharge Cover surface with 6 mil minimum polyethylene Cover exposed edges Cure for uninterrupted 7 days minimum
Good References
ACI 522.1-08 Specification for Pervious Concrete Pavement County of Fairfax, Letter 08-01 Ohio Ready Mixed Concrete Association Carolinas Ready Mixed Concrete Association Tennessee Ready Mixed Concrete Association Georgia Concrete Promotion Association
Thank you