Corner and Wall Panel installation
Establish guide lines, vertical line at 18 in. o.c and horizontal line 9.8ft o.c Vertical lines for Studs and Horizontal lines for runner below and above.
Align the lower starter using base line, mark the holes and drill holes.
Case 1 : If the wall is made of wood, no need to bore a hole, directly use screw. Case 2 : If the wall is made of concrete, bore a hole for plastic tox.
Plastic Tox
Lower Runner
Drill hole according to the screw slot on the runner ( 7 slots per pc.)
Upper Runner
Drill holes on the slots , insert plastic tox and fix the screw using portable drill. For wooden walls, directly use wood screw.
Stud facing up
Upper runner
On the 6 ft full length, insert 4pcs studs @ 18 o.c with first and last stud facing down. Intermediate studs spacing will still be 18 but facing up.
Upper Runner
Vertical Studs
Mark the holes on the studs and remove it for drilling holes.
Drill holes using impact drill , insert plastic tox and fix the wood screw.
Drilled holes
Re-insert the studs after drilling and fix the tox and screw.
Plastic spacers
Plastic Spacers
Starter
Base Drain
Attach the base drain on the lower runner and fix it using metal screw Next, Attach the starter as shown.
T-Joiner
T-Joiner
Base Drain
T-Joiner
Base Drain
Starter
Screw Installation.
Corner panel
Stud Clip
T-Joiner
T-Joiner Clip
T-Joiner Clip
T-Joiner
Installation continued
Silicon Rubber
Rubber Roller
D
Window Corner installation
runners
Install first lower runner and upper runner, then the vertical stud.
Aluminum Window
L-Male Adaptor
Install the L-Male Adaptor on the upper runner and on the vertical studs around the window.
L-Male Adaptor
L-Female Adaptor
Y-Aluminum Adaptor
Insert the W-Aluminum adaptor to lock the panels. Remove plastic cover.