Sei sulla pagina 1di 53

ABSTRACT

This project titled STUDY OF PROTECTIONS OF 60 MW TURBO-GENERATORS OF CAPTIVE POWER PLANT IN VSP covers the complete electric protections of Turbo generator in a Thermal Power Plant of Visakhapatnam Steel Plant. The main objective of the project is to study the various protections provided for the alternator and the necessity of each. The study also covers verification of the existing settings used for different protective relays by actually calculating the fault currents under various conditions. Normally the faults in Generator can occur either inside like stator, rotor or external to it in the bus-ducts of feeders. While internal faults in a generator should be cleaned as fast as possible to minimise the damage of the core where as the external faults should be sustained for a considerable period to enable the respective down-stream protections to act and isolate the same from the generator. In case of downstream protections not clear a fault, a backup is to be provided in generator scheme to isolate the same. Proper coordination between these protections are also to be verified.

Chapter-1
1

INTRODUCTION
An electrical power system should ensure the availability of electrical energy without interruption to every load connected to the system. Among all the systems, electrical energy is quite transferable to the consumers by transmission and distribution systems. The power supply to the consumer should not disturbed and the agencies which supplies the power without interruption. As industrial processes and plants have become more complex and extensive, the demand for improved reliability of electrical power supplies has also increased. The potential costs of outage time following a failure of the power supply or plant have accordingly risen dramatically as well. If at all any fault happens in the system the fault system has to be isolated so that other system should not be disturbed. This is a challenge to the engineers to supply the uninterrupted power to the customers. required. The protection analysis of generator is studied under existing system. The protection analysis is very important for long period running of generator free from mal-trippings. It is noteworthy that generator capacity increased from 10 MW to 500 MW. So the cost of the machine also increases naturally. If the analysis of the relay settings is not proper the machine, may not trip during fault condition due to which winding may burn or its insulation may get deteriorate as high currents circulated in the stator windings of the machine. The adequate protection of the machine depends upon choosing of suitable relays and also their settings. To attain this, logical and fast acting protective equipment is

The protective equipment design depends upon the nature of faults occurring in the power system. If at all fault happens in the balanced system with huge power loss at fault point with unbalanced nature of the power system it is difficult and laborious to calculate the fault currents and voltages. So, power system engineers established some special methods to calculate fault conditions such as Symmetrical & Unsymmetrical in nature. Among all the faults,

symmetrical three phase fault is most severe fault and LG fault is most occurring fault. The Power Grid Corporations Sub-station adjacent to Ukkunagaram is connected to Vijayawada by a 400 kV line. It is also being connected to Jaipur, Orissa (Eastern Grid) through DC back to back arrangement of 500 MW capacity and by 400 kV AC double circuit line. Power is stepped down through a 315 MVA, 400/220 kV auto transformer at Power Grid Corporation Sub-station and is fed to the adjacent AP TRANSCO switching station. This switching station is also connected to Bommuru and Gajuwaka sub-stations by 220 kV double circuit lines. Bommuru sub-station is connected to generating stations at Vijayawada, Lower Sileru, Vijjeswaram, Kakinada and Jegurupadu. connected to Upper Sileru. Gajuwaka sub-station is

One 1,000 MW TPP has been set up near

Visakhapatnam as Simhadri NTPC. This plant is connected to Kalpaka switching station. Power is supplied to VSP from AP TRANSCO switching station over two 220 kV lines on double circuit towers. Power is received at the Main Receiving Station (MRS) located near Main gate and further distributed to various units within the plant.

BASIC REQUIREMENTS OF PROTECTIVE RELAYING


A well designed and efficient protective relaying should have: SPEED:Protective relaying should disconnect a faulty element as quickly as possible. Modern high-speed protective relaying has operating time 0.02 to 0.04 sec. and CBS have interrupting time 0.05 to 0.06 sec. Hence clearing time may be about 0.07 to 0.10 sec. SELECTIVITY:It is ability of the protective systems to determine the point at which the fault occurs and select the nearest of circuit breaker tripping of which will lead to clearing of fault with minimum or no damage to the system. RELIABILITY :The protection relaying must be ready to function reliable and correct in operation at all times under any kind of fault and abnormal conditions of the power system for which it has been designed. SIMPLICITY :Simplicity of construction and good quality of the relay, correctness of design and installation qualified maintenance and supervision etc. are the main factors which influence protective reliability. ECONOMY : As with all good engineering design economics play a major role. Too much protection is as bad as to little and the relay engineer must strike a sensible with due regard to practical situation considered.
4

Chapter-2 INTRODUCTION TO VSP


Steel comprises one of the most important inputs in all sectors of economy. Steel industry is both a basic and a core industry. The economy of any nation depends on a strong base of Iron and steel industry in that country. History has shown that countries having a strong potentiality of Iron and Steel Production have played a prominent role in the advancement of civilisation in the world. Steel is such a versatile commodity that every object we see in our day to day life has used steel either directly or indirectly. To mention few it is used for such a small item as nails, pins, needles etc. through surgical instruments, agricultural implements, boilers, ships, railway materials, automobile part etc., to heavy machines, structures etc. The great investment that has gone into

fundamental research in Iron and steel technology has helped both directly and indirectly many modern fields of todays science and technology. It would seen very painful to image the fate todays civilisation had steel not been there. The per capital consumption of steel in India during 1970s was around 10 kg compared to about 700 kg obtaining in many advanced countries, over 800 kg in Japan. This was very low. Viewing in the backdrop of Indian population which was standing at about 800 Million, even a 10 kg of increase in steel consumption would need the setting up of a 8 Million ton of steel per year production capacity. Keeping this end in view the Government of India had cleared the decision of setting up of a shore based integrated steel plant at Visakhapatnam.

BACKGROUND
The decision of Government of India to set up an integrated steel plant at Visakhapatnam was announced by the then Prime Minister Smt. Indira Gandhi in the Parliament on 17th April 1970. Visakhapatnam Steel Plant (VSP), a public sector undertaking, is a subsidiary of Rashtriya Ispat Nigam Limited. It is one of the most sophisticated modern plants. The foundation stone for which was laid by the former Prime Minister Smt. Indira Gandhi in the year 1972. It is

strategically located on the coast of Bay of Bengal in the state of Andhra Pradesh. An integrated steel plant with the state-of-the-art technology. Overcoming the perils of recession in the steel market it has turned into a profit making organization with proper strategic decisions. The management of late has been geared up to implement new technologies to meet the challenges of completion and the dumping imports of steel. Visakhapatnam is in a

geographically advantageous position. Midway between Kolkata and Chennai. It is easily accessible to major business centers. A professionally organized steel plant, VSP has been the recipient of the ISO 9001, ISO 18001, and the ISO 14000 certifications. Armed with these quality standards and an advocate to the TQM it has achieved the six-sigma and 5S level of efficiency. The management of the plant is organized into production, marketing, finance, personnel, purchase and other auxiliary departments. The plant is designed to produce 3.0 Million tones of liquid steel. It

possesses the state-of-the-art technology and a strong well trained manpower of 17,000 employees. The organization is house of technology where international levels of efficiency are being pursued in terms of productivity and specific energy

consumption.

For the financial year 2003-04 the organization recorded a

turnover of Rs. 6174 crores. VSP achieved a turnaround to post a net profit of nearly Rs. 1521 crores. The net profit estimated for financial year 2005-06 is 16,000 Crores. In addition to a wide range of steel products there are other byproducts which are produced by VSP like tar, pitch and the noted fertilizer Pushkala. VSP because of its geographical advantage and standard products has carved a niche for itself. Nearly 40% of the South Indian domestic market has been captured for the steel products. International customers are from the countries of China, Singapore, Russia, Nepal, Sri Lanka, USA, Japan, UAE etc.

VSP TECHNOLOGY : STATE- OF- THE- ART

7 Metre tall Coke oven batteries with coke dry quenching Biggest Blast furnaces in the country Bell less top charging system in Blast furnace 100% slag granulation at the BF cast house. Suppressed combustion LD gas recovery system. 100% continuous casting of liquid steel. Tempcore and Stelmor cooling process in LMMM & WRM. Extensive waste heat recovery systems i.e. BPTS, GETS, ECS. Comprehensive pollution control measures.

ACHIEVEMENT AND AWARDS


1) 2) Indira Priya Darshini Vrikshamitra for massive afforestation efforts of RINL : 1992-93. Award from Ministry of heavy industries for achieving MoU targets

for 2000-01. 3) 4) 5) 6) 7) 8) 9) 10) 11) 12) 13) 14) 15) 16) 17) 18) National Energy conservation award-2002 -- First Prize in Integrated sector. Certificate of appreciation for achieving OHSAS 18001 from department of Factories, Govt. of Andhra Pradesh. Award from Andhra Pradesh Pollution Control Board for significant work "on cleaner production technologies". Rolling shield on Environment protection. II prize for RINL's stall at the International Trade fair. Successful re-certification of ISO 9001 : 2000. Quality circle & Suggestion related awards. Udyog excellence Gold Medal award for excellence in Steel Industry. Best Management award from Govt. of Andhra Pradesh. Best safety award from Govt. of Andhra Pradesh. ISO 14001 accreditation. OHSAS 18001 accreditation. Best Taxpayer award from Govt. of Andhra Pradesh. Award .from Andhra Pradesh Pollution Control Board (APPCB), Govt of A.P. for best efforts in Rainwater harvesting. Awarded 1st Prize by the Govt of India "Indira Gandhi Rajbhasha Shield" for propagation of Official language (Hindi). RINL was awarded "Best Enterprise Award" by WIPS in 2001.02 (forum of women in public sector) for making excellent contribution in harnessing the growth and development of women and impacting their lives significantly in and around the Public Sector. 19) 20) VSP has bagged the "Greentech Safety Silver Award" for the year 2002.03 in Steel Sector for implementing best safety standards. Vizag Steel's global rating has gone up to 67th position in 2002 from 68th in 2001 amongst World's largest steel producing companies. 21) 22) VSP has won the Rolling Shield for "Ecological Protection" instituted by the Ministry of Information and Broadcasting. Best HRD practices Award by ISTD for the year 2002-03.
8

23)

Special award (being hat trick) for the lowest specific energy consumption among integrated steel plant in India.

Chapter-3
INTRODUCTION TO THERMAL POWER PLANT
Power requirement of VSP is met through captive generation as well as supply from ABSEB grid. The captive capacity of 270 MW is sufficient to meet all the plant needs in normal operation time we have 3 units of each 60 MW and one unit of 67.5 MW capacity.

BOILERS
Thermal Power Plant has 5 Boilers each of 330 T/hr. steam capacity at 101 KSCA and 540O C. The boilers are of BHEL make, capable of firing combination of fuels namely, Coal, Coke Oven Gas, Blast Furnace Gas and Oil. Normally 4 Boilers are kept in full load operation to produce 247.5 MW of power, supply steam to 2 Turbo Blowers and process needs. Boilers outlet flue gas is passed through Electro Static Precipitators to control air pollution.

TURBO GENERATORS
Thermal Power Plant has 4 Turbo Generators, three of 60 MW capacity each and the fourth 67.5 MW . Special features of the turbo sets are :i) ii) iii) Electro Hydraulic Turbine Governing System. Central admission of steam to reduce axial thrust. Forced air cooled generators

Power is generated and distributed at 11 kV for essential category loads. Excess power from TG-1, 2 and 3 is transferred to 220 kV Plant Grid through step up/down transformers. All the Power Generated from TG-4 at 11 kV is stepped up through a 220 kV transformer and transferred to plant grid.

TURBO BLOWERS
VSP has 2 Blast Furnaces. To meet the blast air requirement, 3 Turbo Blowers, each of 6067 NM3 /min capacity, are installed at TPP. These blowers are of axial type and are the largest blowers installed in India. provided with suction filters, pre-coolers and inter- coolers. The blowers are

AUXILIARIES OF TPP
These include coal conveyors, cooling towers & pump house No-4 for cooling water system, pump house for ash water, ash slurry , fire water and fuel oil & HSD air compressor station, emergency Diesel Generators, electric switch gear for power distribution, ventilation and air conditioning equipment etc. The entire power generated at Back Pressure Turbine Station and Gas Expansion Turbine Station is transmitted over 11 kV cables to power plant, stepped up through a 220 kV transformer at LBSS5 and transferred to plant grid.

CHEMICAL WATER TREATMENT PLANT


Chemical Water Treatment Plant located in TPP zone produces high purity De-mineralised Water and Soft Water. There are six streams of De-mineralising units each capable of producing 125 cubic meters per hour each. Two softening units of 125 m3/hr. each. DM water is supplied to TPP, Steel Melt Shop, CDCP

10

Boilers at Coke Ovens, and Rolling Mills. Soft water is supplied to Chilled water plant-I, II and SMS mould cooling.

CHILLED WATER PLANT NO- 2


Chilled Water Plant No-2 located in TPP zone is having nine Chillers, each having a chilling capacity of 337 M3/hr. The chilled water is supplied to TPP, Blast Furnace and Sinter Plant for air conditioning purpose at 70 C. The return water temperature is 160 C.

COKE DRY COOLING PLANT (CDCP) BOILERS


In VSP, hot coke produced in the Coke Oven Batteries is cooled by circulating Nitrogen in Coke Dry Cooling Plant. The hot circulating gas is passed through Waste Heat Boilers in which steam is produced at 40 KSCA pressure and 4400 C temperature. There are three Coke Dry Cooling Plants, four Waste Heat Boilers. Boiler is of 25 T/Hr Capacity.

BPTS & CHILLED WATER PLANT NO- 1


The 40 KSCA steam generated in CDCP Boilers is utilised for driving 2 Nos. of 7.5 MW Back Pressure Turbines for generation of Power. The 2.5 Ata exhaust steam is utilised for production of Chilled water in CWP-1. The 7 Ata extraction steam is used for process requirements of CO & CCP zone . The CWP-1 has 5 Chillers installed, each capable of cooling 337 M3/hour BPTS and CWP-1 are housed in a single located near Battery No-3 of CO&CCP zone.

11

GAS EXPANSION TURBINE STATION (GETS)


Both the Blast Furnace of VSP are designed to operate at a high top pressure of 2.5 Kg/cm2. The high pressure BF Gas is cleaned in Gas cleaning plant and expanded in Gas Expansion Turbines driving electric generators. The BF Gas after passing through the Turbine is fed to gas distribution net work and is used as heating fuel in TPP & other units of VSP. Each Blast Furnace is connected to a Gas Expansion Turbine of 12 MW capacity 7.5 MW of power is generated by each of the turbine at full production level. GETS is located in BF zone, between the two furnaces.

TPP ELECTRICS
There are 3 Generators present in the TPP. The capacity of each

generator is 60 MW, Generation of the voltage level 11kV, total generation is 180 MW out of this 30-40 MW are consumed by the Blast furnace, Steel Melting Shop, Coke oven, Rolling mills and 30-32 MW is consumed by the TPP auxiliaries. Remaining 110 MW is connected to LBSS5. In addition to this there is one generator (TG-4) rated at 67.5 MW, 11 Kv, 90 MVA. There are two Gas Expansion Turbines (GETS) and two Back Pressure Turbines (BPTS) rated 12 MW & 7.5 MW respectively. From this 20 MW is supplied to LBSS5. LBSS1 consumes a load of 40 MW. The remaining 157.5 MW is supplied to Main

Receiving Station (MRS). At this station LBSS2 consumes a load of 50 MW for Blast furnace and Air separation plant. LBSS3 consumes a load of 5 MW for LBSS3 MMSM and WRM. LBSS4 consumes a load of 30 MW. Township

consumes a load of 5 MW. There are two APSEB tie lines connected to MRS for exporting and importing depending upon the conditions.
12

GSB- 1
Generator Switch Board-1 is a 11 kV, 4500 Amps, 3 section board, located at 0 meters in TPP. Each 60 MW generator is connected to each section of the board. The bus is provided with a bus coupler and the bus coupler 4500 Amps reactor between section-1 & 2 as well as between section-2 & 3. To sections-1 & 3 of GSB-1 350 MVA, 220 kV/11 kV are connected. Out of these 3 transformers, two are always in operation and the other one is standby. The 220 kV side of transformers are connected to sub-station called Load Block Sub-Station-5 (LBSS). Power is evacuated through LBSS-5 transformers-1, 2 and 3 and is

distributed through the 220 kV network of the plant. All the critical loads of the steel plant i.e. Water supply, Blast furnace, Steel Melt shop and Coke oven are connected to GSB through 11 kV cables. In addition all the TPP auxiliaries are also connected to GSB-1. All outgoing feeders are connected to GSB through link-reactor and Minimum Oil Circuit Breaker (MOCB) in addition to earthing switches. Turbo Generators of TPP normally operate in parallel with state grid. All three generators of each 60 MW are connected to Generator switch board. This GSB-1 is a 11 kV 4500 Amps, 3 selection board located at 0 Mt level in AA bay. All category-1 loads of the steel plant are connected to GSB-1 through 11 kV cable. Power is evacuated through 50/63 MVA (11kV/220kV) transformer 1, 2 & 3 which are connected to Section-1 and 3 of the GSB-1. Synchronisation facility exists for any of the incoming generator, 50/63 MVA Transformer-1, 2, 3.

ISLAND OPERATION SCHEME :-

13

A scheme has been envisaged at TPP to get isolated form the grid in case of system disturbance or low frequency condition with ABB make relay type FCX 103b relay with following settings: df/dt 2 cycles/sec rate of fall below 50 HZ 1st stage 47.5 HZ FOR 0.5 SEC. over frequency 51.5 HZ with time delay 150 MS 2nd stage 46.9 HZ with 1 sec. delay

POWER REQUIREMENT
Integrated Steel Plants are major consumers of electricity, with specific consumption of power at around 600-650 kWh/Ton of liquid steel. The estimated annual power requirement of Visakhapatnam Steel Plant, at full level of production in each shop (corresponding to 3.0 MT of liquid steel), is 1932 million kWh. This corresponds to an average demand of 221 MW. The estimated

energy consumption and average demand of major shops is given below:

SHOP

Annual Energy (106 kW Hrs.)

Average Demand (MW)

RMHP CO & CCP SINTER PLANT BLAST FURNACE SMS & CCM LMMM WRM MMSM CRMP TPP ASP

35 171 254 210 126 100 118 100 35 310 258

4.0 19.5 29.0 24.0 14.5 11.5 13.5 11.5 4.0 35.0 29.5

14

COM. STATION & CWP AUXILIARY SHOPS WATER SUPPLY TRAFFIC & OTHERS TOWNSHIP LOSSES TOTAL

131 20 15 7 28 14 1932

15.0 2.5 2.0 1.0 3.0 1.5 221.0

SOURCES OF POWER
Power requirement of VSP is met through captive generation as well as supply from APSEB grid. The captive capacity of 270 MW is sufficient to meet all the plant needs in normal operation time. In case of partial outage of captive generation capacity due to breakdown, shutdown or other reasons, the short fall of power is availed from ABSEB grid. Turbo Generators of VSP normally operate in parallel with state grid. exported to APSEB. The agreement with APSEB provides for a contract demand of 150 MVA and permit export of power. Tariff for import, export, demand charges, penalties etc. are stipulated. For purpose of billing, import and export energy is separately metered at Main Receiving Station. Excess generation over and above plant load is

POWER DISTRIBUTION IN POWER PLANT


220 kV & 11 kV LOAD BLOCK SUBSTATION-5 (LBSS-5) Integrated Steel Plants are major consumers of electricity, with specific consumption of power at around 600-650 kWh/Ton of liquid steel. The estimated annual power requirement of Visakhapatnam Steel Plant, at full level of
15

production in each shop (corresponding to 3.0 MT of liquid steel), is 1932 million kWh. This corresponds to an average demand of 221 MW. Power requirement of VSP is met through captive generation as well as supply from AP TRANSCO grid. The captive capacity of 270 MW is sufficient to meet all the plant needs in normal operation time. In case of partial outage of captive generation capacity due to breakdown, shutdown or other reasons, the short fall of power is availed from ABSEB grid. Turbo Generators of VSP

normally operate in parallel with state grid. Excess generation over and above plant load is exported to AP TRANSCO. The agreement with AP TRANSCO provides for a contract demand of 150 MVA and permit export of power. penalties etc. are stipulated. LBSS-5 is located outdoor and it consists of 220 kV, 1250 A, 3 phase main bus-1, main bus-2 and transfer bus. LBSS-5 is having 12 bays i.e. three nos. for the three tie lines, two nos. of LBSS-1 lines, 3 nos. for the three 50/63 MVA transformers, one no. for 30/40/50 MVA transformer, one for 90 MVA transformer, one for Bus coupler & one for bypass. In case of any difficulty in taking into service any of the 220 kV circuit breakers of transformer or lines as the case may be, bypass breaker can be taken into service in lieu of the defective breaker by charging the transfer bus. Both 220 kV main bus-1 & main bus-2 can be paralleled & transformer feeders (T1, T2, T3, T4 & T5) can be either connected to Bus-1 or Bus-2 or distributed between Bus-1 & Bus-2 depending on operational/maintenance requirement. All 220 kV circuit breakers are SF6 Tariff for import, export, demand charges,

breakers. Synchronising facility exists only for tie lines ML1, ML2, ML3, Bypass and Bus coupler breakers at Control & Relay panel of LBSS-5 located in ECR.
16

The loads (lines or transformers) can be transferred form Bus-1 to Bus-2 and vice versa live through On Load Bus Transfer scheme (OLBT). A typical single line diagram is enclosed.

SYNCHRONISATION
The operation of connecting an alternator in parallel with another alternator or with common bus-bars is kwon as Synchronizing. Generally, alternators are used in a power system where they are in parallel with many other alternators. It means that the alternator is connected to a live system of constant voltage and constant frequency. Often the electrical system to which the alternator is connected, has already so many alternators and loads connected to it that no matter what power is delivered by the incoming alternators, the voltage and frequency of the system remains the same. In that case, the alternator is said to be connected to infinite bus-bars. It is never advisable to connect a stationary alternator to live bus-bars, because, stator induced emf being zero, a short circuit will result. For proper synchronization of alternators, the following three

conditions must be satisfied. (1) The terminal voltage or effective voltage of the incoming alternator must be the same as bus-bar voltage. (2) The speed of the incoming machine must be such that its frequency (=PN/120) equals the bus-bar frequency. (3) The phase of the alternator voltage must be identical with the phase of the bus-bar voltage. It means that the switch must be

17

closed at (or very near) the instant of the two voltages have correct phase relationship. Synchronisation facility exists for any of the incoming generators, 50/63 MVA Transformer 1, 2 & 3, Bus couplers and Bus couplers with reactors at 11 KV. The synchronising operation is to be carried out using synchronising trolley in ECR.

Chapter-4
THEORETICAL REVIEW OF RELAYS
TYPES OF PROTECTIONS : Two types of protection: 1. 2. Primary protection Backup protection

Primary protection :Primary protection is the first line of defence and primary relays clear faults in the protected section as fast as possible. 100% reliability is not guaranteed for protective scheme and also for associated CTs, PTs and CBs. Therefore some sort of backup protection must be provided.

Backup protection :Backup relays operate if the primary relays fail and cover not only the local station but the next one also and have a time delay long enough for the primary relays to operate if they can.

18

ELECTROMAGNETIC RELAYS
These are earliest form of relays devices used for power system protection and till now they are the most widely used variety relays. All these devices

depend upon electromagnetic interaction and have mechanical movement associated with them which Actually make or break pairs of contacts indicating relays operations. The electromagnetic interaction is manifested either in form of force of attraction or torque of rotation which has produced different classes of electromagnetic relays

ATTRACTED ARMATURE TYPE


The type includes plunger, hinged armature relays. These are the simplest type which respond to AC as well as DC. The principle of this type is that an electromagnetic force is produced by the magnetic flux operating quantity . If this force exceeds the restraining force , the relay operates . the electromagnetic force is given by F = KI2 ------------ (1)

INDUCTION RELAYS
Induction type relays are the most widely used for protective relaying purposed involving A.C. quantities. Torque is produced in these relays when one alternating flux reacts with the current induced in the rotor by another alternating flux displaced in time and space but having the same frequency. These relays are classified depending on the type of rotor. If the rotor is a disc, is known a induction disc relay. If the rotor is a cup, the relay called as induction cup relay. The Actuating force is given by F = K 1 2 Sin ---- (2)

19

In the abnormal conditions or fault conditions the corresponding relay contact operation which in turn operates the tripping relay type VAJHM called master trip relay or Generator lock out relay which will trip generator circuit breaker. Alarm annunciation will come on control desk. The following are the relay details which are used for generator in TPP.

DESCRIPTION Under voltage relay Generator under voltage relay Generator reverse power relay Generator low forward power relay Generator field failure relay Generator negative sequence current relay Definite time O/C relay with 1st high set unit Voltage control over current relay Generator over voltage relay Voltage neutral displacement relay Directional inverse time over current relay Directional inverse time earth fault relay VT fuse failure relays Generator out of step relay Generator differential relay Generator restricted E/F relay Generator under frequency relay Sensitive E/F & Instantaneous O/C relay

Reference 27A/27B 27 G 32 G 37GA/GB 40 G 46 G 50T/51G 51 V 59G1/59G2 64V 67RYB 67W 68A/68E/68PM 78G 87G 64G 81G 64S/50X

Make EE EE EE EE EE EE EE EE EE EE EE EE EE EE EE EE E ABB

Type VAG 31 VAG 21 WCD11 WCD13 YCGF11 CTN31 CTU62 CDV62 CAGM22 VDG14 CDD21 CDD21 VAGM-61 ZTO CAG34 CAG14 FTG11 RX1428X RX12 21

GENERATOR DIFFERENTIAL RELAY


20

This relay is used to protect against stator faults as shown in below figure. A differential relay is defined as the relay that operates when the vector difference of two or more similar electrical quantities exceeds a predetermined value.

External & Internal circuit connections of generator differential relay

When there is no fault in the generator winding for through faults the current in pilot wires fed from CT connections are equal. The difference in

current I1 -I2 is zero. When there is a fault inside the protected winding, the balance is disturbed and difference current (I1- I2) flows through operating coil of the relays.

21

Relay settings: Plug setting R 0.1 Y 0.1 B 0.1 0.05 to 0.2 Range

CTR- 4500/1A

GENERATOR RESTRICTED EARTH FAULT RELAY


Connection diagram is shown in below figure. In circulating current protection schemes, the sudden and often asymmetrical growth of the system current during external fault conditions can cause the protective current transformers to go into saturation resulting in a high unbalance current. To ensure stability under these conditions, a voltage operated, high impedance relay is used. It is a attracted armature relay.

22

External & Internal circuit connections of generator stator earth fault relay

NEGATIVE PHASE SEQUENCE RELAY


Negative phase sequence currents to star resulting from unbalanced loading produce a field rotating at twice synchronous speed with respect to the rotor and hence induce double frequency currents in the rotor. These currents are very large and result in severe over heating of the rotor. It is necessary to limit the time for which negative phase sequence currents can flow in a steam generator. The time for which a generator may be allowed to operate with unbalance stator currents without danger of permanent damage is obtained from expression: I22 T = K Where K is the constant depending up on the type of the machine. The E.E. make scheme suitable for this application employs a type CDN relay which comprises an induction disc tripping unit having an adjustable inverse time current ( I22 T ). The relay settings I 2 s. A B C Range 7.5% K3 1

10% 10% 10%

23

10% 15% 20% 30%

1.78 4 7.1 16

GENERATOR VOLTAGE CURRENT RELAY

RESTRAINED

OVER

Fault conditions cause a greater drop in busbar voltage than normal over load, and this fact has been utilised in voltage restrained over current relay. The relay has two operating characteristics viz. An over load characteristics determine by the operation of instantaneous under voltage unit monitoring the generator voltage. Under over load conditions, when the generator voltage is usually near normal the instantaneous under-voltage unit is energised and the short across the resistor in the shading coil circuit is removed. Below figure shows the internal connections diagram.

24

External and internal connections of Voltage restrained over current relay

The relay operates on a long IDMT under fault conditions, when the generator voltage falls to the setting of the under voltage unit, the resistor is short circuited and the torque on the disc increased by 2.5 times so that the normal setting currents are 0.4 times those marked on the plug board, and the relay operates in Accordance with the fault characteristic. Both characteristic of the relay as shown in figure.

Time / current characteristics of Voltage restrained over current relay

TIME IN SECS. NORMAL VOLTS


100 50 30 20 15 10 8 7 6 5 4

0.4 0.6 0.8


0.4 0.6 0.8

1
1

1.5
1.5

2
2

3
3

4
4

5
5

6
6

8
8

10
10

15
15

20
20

25

30 20 10 8

3.5

2.6

2.2

TIME IN SECS. - LOW VOLTS

Plug setting Time multiplier CTR -

R 1.5 1

Y 1.5 1

B 1.5 1

4500/1A

GENERATOR DIRECTIONAL OVER CURRENT RELAY


When fault current can flow in both directions through the relay location, it is necessary to make the response of the relay directional by the introduction of directional control elements. Directional over current relays are combination of directional and inverse over current relay units as shown in figure.

26

GENERATOR DIRECTIONAL OVER CURRENT RELAY

Plug Setting: R 1 Y 1 B 1 Range 0.5 -2A

CTR - 4500/1A

PSM :
1 1.3 2 2.5 3 4 5 6 7 8 9 10 12 14 16 18 20

30 20 15 10 8

3.5

3 2.8

2.6 2.4

2.2

GENERATOR DIRECTIONAL EARTH FAULT RELAY


The relay is used for directional earth fault protection for generator. Typical external and internal connection shown in figure above. Since the current may be derived from any phase, in order to obtain directional response it is necessary to obtain a related voltage. Such a voltage is the residual voltage of the system. Which is vector sum of the individual phase voltage of the system. The voltage developed across secondary terminals will be vector sum of the phase to ground voltage. This will be zero for balanced phase voltage, but for simple earth fault conditions will be equal to the depression of the faulted phase voltage. In all cases the residual voltage is equal to three times the zero sequence voltage drop and is Displaced from the residual current.
27

The residual are applied to the

directional element of the earth fault relay. The relay inverse time characteristic scale is shown in figure below.

Relay settings: Plug setting TMS CTR- 0.1 - 0.1 4500/1A Range 0.1 to 0.4

PSM :
1 1.3 2 2.5 3 4 5 6 7 8 9 10 12 14 16 18 20

30 20 15 10 8

3.5

3 2.8

2.6 2.4

2.2

DEFINITE TIME/INSTANTANEOUS OVER CURRENT RELAY


This relay protects the generator against short circuit faults. This relay contains definite time over current element and instantaneous high set elements. The relays areas particularly suitable on systems where there is a wide variation in source impedance. Relay settings : Plug setting Time setting Instantaneous setting Definite time over current relay. Range 0.95 10 sec. 4 0.5 - 2 Amps. 6- 60 sec.

GENERAL FIELD FAILURE RELAY

28

Under current relays connected in the field circuit have been extensively but the most selective type of loss-excitation relay is a directional-distance type operating from the A.C. current and voltage at the main generator field. The enclosed figure shows loss-of-excitation characteristics and the operating characteristics of one type of loss-of-excitation relay on R-X-diagram when the excitation is lost, the equivalent generator impedance traces a path from the first quadrant into a region of the fourth quadrant that is entered only when excitation is severally reduced or completely lost. By encompassing this region within the relay characteristic, the relay will operate when the generator first starts to slip poles and will trip the field breaker and will trips the field breaker and disconnect the generator from the system.

R-X diagram

The satisfactory application of

YCAF field failure relay, requires full

knowledge of the operating conditions. i.e. the maximum rotor angle at which the Machine can operate within the stability limit. In general practice is to use an offset setting equal to half the Machine transient resistance and a circle diameter
29

equal to synchronous reactance of the Machine Xs for rotor angle upto 900. The external connection diagram of YCGF field failure relay is shown in figure.

General field failure relay

The relay movement is a high speed induction cup unit with operating, restraint and bias windings adjusting the ohmic values of the diameter and offset of the relay characteristic circle is provided by the combination of plug board and potentiometer settings K1 K2 K3 K4 and K5. K1 is in the restraint circuit and

provided line adjustment of characteristics circle diameter. K2 potentiometer is in the polarising circuit and should be set to coincide with offset taps K1 to establish maximum torque angle at an offset settings. The characteristics offset is

obtained by injecting voltage from the current circuit through transactor. Taps for this transactor are brought out to plug board K3 K4 and combinations of two plug

30

settings provide adjustment of offset settings. K5 allows course adjustment of the characteristics circle diameter by selection of taps on an auto-in the resistance circuit.

The setting values are K1 K2 K3 K4 K5 0.9 10 0 10 170

Generally they are set K2 = K3 + K4 i.e. offset taps. The diameter of the characteristics circle is K1 x K5 ohms. X1 = 0.25 = 25% MACHINE TRANSIENT IS SECONDARY OHMS = = 25 x 112 100 x 75 18.15 . 4500/1 11000/110

Required offsetting = X1 d = 18.15 2 2 = 9.05 We have put offset for 10. Xs = 2 = 200%

MACHINE SYNCHRONOUS REACTANCE IN SECONDARY OHMS = 200 100 x 112 75 x 4500/1 = 145.2 1100/110

Required circle diameter Xs = 145.2 As per relay design we have put setting
31

K5 - 170 and K1 -09 K1 x K5 = circle Dia 170 x 0.9 = 153

EARTH FAULT PROTECTION IN GENERATOR FIELD WINDINGS WHICH ARE NORMALLY UNEARTHED FIRST ROTOR EARTH FAULT
A single earth fault is not in itself dangerous since it does not cause any fault current, but a second fault effectively short circuits or all parts of the field system and the unbalancing of the magnetic force caused there by may be sufficient to spring the shaft and make it eccentric. If the condition were allowed to persist, however it might lead to reverse mechanical damage. The figure

shows the method detection using the principle of negative potential biasing, where by an earth fault any where in the field circuit can be detected. The d.c supply injection establishes a small bias on the alternator field winding circuit so that are points are negative with respect to earth.

Earth fault relay

32

The rectified output of a transformer fed from the station L.V supply provides a biasing potential approximately 30v. This is connected with positive terminal through a current limiting resistor and the secondary winding of transductor to the positive pole of the field circuit. When a fault occurs current flows in the bias circuit and the dc winding of the transductor. This results in saturation of the transductor core which reduces the impedance of the A.C. winding thus allows the relay A to operate. Thus giving alarm for first rotor earth fault. The relay will not operate if A.C. auxiliary supply fails. Under this conditions i.e. when auxiliary supply fails the relay B which will be in picked up condition when the auxiliary supply is available will drops off when auxiliary supply fails. This then n.c Contacts of the relay B will get through for A.C. failure alarm circuit. Technical data Field ckt voltage Bias ckt voltage Bias voltage Sensitivity 0-450 v d.c 240v 10% 5Hz 30v d.c 1ma DC 10%

Setting of the first rotor earth fault is 1mA. The circuit diagram of first rotor earth fault is shown in enclosed figure.

SECOND ROTOR EARTH FAULT RELAY


When a single earth fault is detected in the d.c field circuit of a Machine, the Machine has to be taken out of service at the first opportunity. This is

because if allowed to run with an E/F on the rotor a subsequent second earth fault can cause severe damage to the Machine. However a relay which can detect such a second rotor earth fault and trip out the Machine can make it

33

possible to run the Machine even with single earth fault with out any such risks thus helping to preserve the generation Capacity. The heart of the second rotor earth fault detection scheme is a very sensitive transductor element. The AC winding of the transductor is connected in series with a rectified AC voltage relay A. The DC winding of the transductor on the other hand is connected in series with field earth fault circuit. Under normal conditions i.e. when no DC current flowing the AC winding and the transductor presents a high impedance and the AC winding and the transductor presents a high impedance and the AC voltage applied is mostly dropped across this winding. energised. When second rotor earth fault occurs a DC current flows through the transductor DC winding which causes the impedance of the AC winding to reduce considerably by driving the transductor core into saturation. Hence the applied voltage is fully available across the relay and the latter operates. The selector switch SW1 on the generator panel will have 4 (four) positions as follows. Hence the relay A drops i.e. remains de-

1. 2. 3. 4.

First rotor earth fault. Balance Test Second rotor earth fault.

Normally the selection of switch will be put in position 1 in which the first rotor earth fault relay will be in service. If the occurrence of the first rotor earth

34

fault of any one machine, the selector switch of the machine is put in position-2. Connecting the coarse control potentiometer across the field winding circuit of the affected machine. Simultaneously the milli-ammeter is also inserted in the circuit. As can be seen from the figure, the portions of the field winding on either side of the first rotor fault and the coarse control potentiometer forms a DC bridge with millammeter connected across a pair of nodes. By adjusting the coarse/fire control and the range selector switch of the milli-ammeter the bridge is balanced to mull point. The selector switch is kept in position-3 in which milli-ammeter is replaced by relay, but the relay trip circuit is isolated. After making sure that the relay does not pick-up then the SW1 is turned to position-4. Thereby putting the second rotor earth fault relay complete in service. Protection against prime mover failure (Need of low forward power relay and reverse power relay ): The effect of prime mover failure is to cause the

machine to motor by taking power from the system which may result in severe mechanical damage and, in addition will impose a heavy motoring load on the generator. The reverse power relay is normally used for two applications as a reverse power relay to trip the generator when the machine starts motoring and as a reverse power interlock device to prevent the possibility of a turbo-generator set overspeeding should a steam valve fail to close completely after the generator circuit breaker has opened on a fault. Use a low forward power interlock instead of reverse power interlock. So that it is not necessary the delay the generator circuit breaker tripping till the set has actually started motoring. When low interlock with normally closed contact as soon as the power supplied by the generator falls below O 5 % of rated
35

power the low power relay resets and completes the tripping circuits to the generator circuit breaker.

GENERATOR SENSITIVE PROTECTION

EARTH

FAULT

This protection is especially provided in the generator to sense any earth leakage near to the neutral. Question may come why separate earth fault relays is used. Reason is that other earth fault relay senses earth current of higher magnitude. But when there is a earth fault near to the neutral it may not be possible for the machine voltage to drive that much higher current. So one earth fault relay having very low current operating unit is used for sensitive earth fault relay. Since it is a low current setting relay it may mal operate. To protect it from mal operation we have used another relay which will sense earth fault current in earthing transformer neutral which will ensure that definitely some earth fault is present. This may operate generator terminal earth fault also. To prevent to do so we have put over current relay 50 X which will sense over current and prevent the earth fault relay to operate. RELAY SETTINGS : 64GS CTR 50 X 2.5 ma 4500 / 1A R Y B 2.5A 2.5A 2.5A 50NX1 (From earthing transformer # 1 neutral CT) setting - 0.05 Amps CTR - 200/1

PARTIAL DIFFERENTIAL PROTECTION SCHEME

36

This relay is meant for to protect the GSB-1 Bus sections. There are three sections. For each section one relay is provided. Partial differential relay

contains two separate relays. One is IDMT/INST over current relay for phase faults and other one is IDMT earth fault relay for earth faults. The partial differential relay will act when either of those two relays are acted. IDMT/INST over current relay: Plug setting IDMT R 1 Y 1 B 1 0.5-2 1 Range TMS

Instantaneous setting - 4 IDMT earth fault relay : Plug setting 0.1 Range 0.1 - 0.4 TMS 0.2

GENERATOR OUT OF STEP RELAY :A CAG 19 relay serves as an over current starter and this is set at between 50 and 20% of nominal current. Based on 5 A CTs below the current no operation can occur. Both character look into the source and consequently

ignore all conditions of load other than those which produce a reversal of power flow such as would occur with a condition of pole slip or power swing exceeding 90O. The timer is incorporated so that discrimination can be made between a

power sourcing and a pole slip condition. A trip condition can only occur if the timer has timed out before the fault moves into the blinder operate region. If the fault never reaches the operate region of the blinder or moves between the directional and blinder characteristics in a time less than the time setting than no

37

operation will occur. The relay consists of a directional unit and a reverse reach blinder based on the YTG Mho type static relay measurement technique and incorporates these components.

It is used to protect synchronous motors against the effects if pole slipping caused by excessive load or insufficient field excitation, pole slipping in the generator slowing down and losing synchronism. The ZTO relay consists of a directional unit with a variable lag angle (1) setting between 50 to 75O, and a blinder unit also with a variable lag angle (2) setting between 50 to 75O which has reverse resistive reach setting between 0-25 ohms and 32 ohms.

Since it can deal only with a pole slip condition emanating from are direction. generator. R1 = 0.90 to 1 The relay setting : K1 = 0.92 K2 = 0.82 K3 = 8 t = 50 1 = 75O 2 = 75O R2 = 0.55 to 1 R3 = 0.5 to 32 The ZTP relay is limited to applications in close proximity to a

38

Chapter-5 FAULT CALCULATIONS AND RESPONSE OF RELAYS FOR DIFFERENT FAULTS


We are having three generators of 60 MW capacity each and one

generator of 67.5 MW capacity. Our generators are floating neutral type. As our planet is captive power plant generators are connected to 11 KV Bus (GSB1). The 11 KV is stepped upto 220 KV through two 220KV/11KV power transformers. The 220 KV sub station is names as LBSS-5. We earthed our system at GSB-1 through three earthing transformers. Out of three transformers two transformers are taken to service. Our plant auxiliary supply and emergency loads are

connected to this GSB-1 Bus. We are having separate 220 KV station it is names as main receiving station. It receives the APSEB supply through line AL1 and AL2 our 220 KV substation (LBSS5) is having tie connection with MRS. Four sub-stations located at different places are fed through MRS and catering the loads our steel plant. Figure shows the single line diagram of total power system in V.S.P.

NAME PLATE DETAILS OF TG1, TG2 & TG3


MW rating MVA rating : : 60 MW 75 MVA
39

Rated power factor Rated voltage Rated current Rotor voltage Rotor current Connection Speed Coolant Winding type Positive sequence impedance Negative sequence impedance Zero sequence impedance

: : : : : : : : : : : :

0.8 11000 Volts 3936 Amps 300 Volts 596 Amps Star 3000 rpm Air Double layer 18.8% 19.7% 12.9%

NAME PLATE DETAILS OF TG4


MW rating MVA rating Rated power factor Rated voltage Rated current Rotor voltage Rotor current Connection Speed Coolant Winding type Positive sequence impedance Negative sequence impedance Zero sequence impedance : : : : : : : : : : : : : : 67.5 MW 84.375 MVA 0.8 11000 Volts 4429 Amps 307 Volts 624 Amps Star 3000 rpm Air Double layer 21.45% 20.92% 11.57%

NAME PLATE DETAILS OF TRANSFORMERS T1 & T2


Rated KVA Rated voltage : : ON AN 50000 ON AF 63000 HV
40

220 kV

LV HV Rated current Frequency Positive sequence impedance Negative sequence impedance Zero sequence impedance : : : : : ON AN ON AF 50 Hz 22.67% 21.58% 16.79%

11

kV LV 131.2 A 165.3 A 2624.6 A 3307.0 A

All the values are based on 50 MVA

NAME PLATE DETAILS OF TRANSFORMERS T3.


Rated KVA Rated voltage Rated current Frequency Impedance voltage : : : : : 9000 HV LV 220 kV 11 kV

HV 236.2 A LV 4723.8 A 50 Hz 11.6%

FAULT CALCULATIONS
Choose a system base of 100 MVA and base voltage as 11 kV at all Generators. The impedance voltages on 100 MVA base are as below.

GENERATORS TG-1, TG- 2 & TG3


(MVA)b, new (KV2)b, old We have Z(p.u.) new = Z(pu) old x ------------------ x -----------------(MVA)b, old (KV2)b, new 100 112 Positive sequence impedance or reactance, XG1 (pu) = 0.188 x ------- x -----75 112 = 0.25067 pu

41

100 112 Negative sequence impedance or reactance, XG2 (pu) = 0.197 x ------- x -----75 112 = 0.2626 pu 100 112 Zero sequence impedance or reactance, XG0 (pu) = 0.129 x ------- x -------75 112 = 0.172 pu

Generator TG-4
100 112 Positive sequence impedance or reactance, XG1 (pu) = 0.2145 x --------- x -----84.375 112 = 0.2542 pu 100 112 Negative sequence impedance or reactance, XG2 (pu) = 0.2092 x ------- x -----84.375 112 = 0.2479 pu 100 112 Zero sequence impedance or reactance, XG0 (pu) = 0.1157 x ---------- x -------84.375 112

REACTORS
Reactance of reactors = 0.2 (positive) = 0.2 (negative) = 1.0 (Zero sequence) (KV2)b 112 Base reactance, Xb = ------------ = -------- = 1.21 (MV)b 100

= 0.13713 pu

0.2 Positive sequence reactance, of reactor = -------- = 0.1653 pu


42

1.21 0.2 Negative sequence reactance, of reactor = -------- = 0.1653 pu 1.21 1.0 Zero sequence reactance, of reactor = -------- = 0.82645 pu 1.21

TRANSFORMERS T1 & T2
100 112 Positive sequence impedance or reactance, XT1 (pu) = 0.2267 x --------- x -----50 112 = 0.4534 pu 100 112 Negative sequence impedance or reactance, XT2 (pu) = 0.2158 x ------- x -----50 112 = 0.4316 pu 100 112 Zero sequence impedance or reactance, XT0 (pu) = 0.1679 x ------- x -------50 112 = 0.3358 pu

TRANSFORMER T3
100 112 Positive sequence impedance or reactance, XT1 (pu) = 0.116 x --------- x -----90 112 = 0.1289 pu

EARTHING TRANSFORMER
Here the 11 kV bus is earthed using zigzag transformer earthing through a 14 resistance.

43

Actual value 14 Its pu value = --------------------- = ------- = 11.57025 pu Base value 1.21

3 FAULT OR SYMMETRICAL FAULT CALCULATIONS For Fault at F 1 :


The Thevenins equivalent circuit for fault at F1 is obtained by exciting the passive Thevenins network at the fault point by negative of pre-fault voltage and is as shown in figure enclosed. On reducing the circuit in the enclosed figure we get The equivalent impedance of circuit at F1 = j 0.12007 pu 1.0 Fault current, If = ----------------- = - j 8.32863 pu j 0.12007 If (pu) = 8.32863 If = 8.32863 x base value of current 100 x 106 Base value of current = ------------------------ = 5248.6388 Amps 3 x 11 x 103 Fault current, If = 8.32863 x 5248.6388 = 43.71897 kA

If = 43.71897 kA
The contribution of each generator to the fault are given as: Current contributed by Generator-1, IG1 (pu) = 3.99 IG1 = 3.99 x 5248.6388 = 20.942 kA

IG1 = 20.942 kA
44

Current contributed by Generator-2, IG2 (pu) = 1.9803 IG2 = 1.9803 x 5248.6388 = 10.394 kA

IG2 = 10.394 kA
Current contributed by Generator-3, IG3 (pu) = 1.27623 IG3 = 1.27623 x 5248.6388 = 6.6985 kA

IG3 = 6.6985 kA

Current contributed by Generator-4, IG4 (pu) = 1.0821 IG3 = 1.0821 x 5248.6388 = 5.6797 kA

IG4 = 5.6797 kA

The relays which are operated for 3 fault at F1 is:


Partial differential IDMT/Instantaneous over current relay: The relay settings are : R 1 Y 1 B 1 TMS 0.45

and instantaneous over current setting = 1.3 x 4 = 5.2 Amps The 3- symmetrical fault current is, If = 43.7139 kA Fault current when referred to CT secondary = 43.7139 / 4500 = 9.7 So, for 3- operates. For the IDMT relay, for PSM = 9.7, time in seconds = 3.1 sec. (from the scale). fault partial differential instantaneous over current relay

45

Actual operating time = 3.1 x 0.45 = 1.395 sec. The IDMT relay will act with 1.395 seconds time delay if instantaneous over current relay fails to act. For this fault i.e. for 3- fault on GSB1, differential relay of Generator-1 will not act since it is a through fault. If the fault occurs before the generator circuit breaker then the differential relay will operate to open the generator circuit breaker. The fault current remains same if the fault occurs either on GSB-1 section or before Generator circuit breaker or before Power transformer circuit breaker. But the relays operating at different faults are not same. If the fault occurs before generator circuit breaker the differential relay will act instantly and trip the generator circuit breaker. So the remaining system will not be effected. In the same way if the fault occurs before the power transformer circuit breaker the transformer differential relay will act and trip the transformer circuit breaker only, so remaining system will be unaffected.

For Fault at F 2 :
The Thevenins equivalent circuit for fault at F2 is obtained by exciting the passive Thevenins network at the fault point by negative of pre-fault voltage and is as shown in figure enclosed. On reducing the circuit in the enclosed figure we get The equivalent impedance of circuit at F2 = j 0.10699 pu 1.0 Fault current, If = ----------------- = - j 9.346745 pu j 0.10699 If (pu) = 9.346745
46

Fault current, If = 9.346745 x 5248.6388 = 49.0577 kA

If = 49.0577 kA
The contribution of each generator to the fault are given as: Current contributed by Generator-1, IG1 (pu) = 2.22213 IG1 = 2.22213 x 5248.6388 = 11.6632 kA

IG1 = 11.6632 kA
Current contributed by Generator-2, IG2 (pu) = 3.989 IG2 = 3.989x 5248.6388 = 20.9364 kA

IG2 = 20.9364kA

Current contributed by Generator-3, IG3 (pu) = 2.22213 IG3 = 2.22213 x 5248.6388 = 11.6632 kA

IG3 = 11.6632 kA

Current contributed by Generator-4, IG4 (pu) = 0.91355 IG3 = 0.91355 x 5248.6388 = 4.7949 kA

IG4 = 4.7949 kA

The relays which are operated for 3 fault at F2 is:


Partial differential IDMT/Instantaneous over current relay: The relay settings are :
47

R 1

Y 1

B 1

TMS 0.45

and instantaneous over current setting = 1.3 x 4 = 5.2 Amps The 3- symmetrical fault current is, If = 49.0577 kA Fault current when referred to CT secondary = 49.0577 / 4500 = 10.9 So, for 3- operates. For the IDMT relay, for PSM = 10.9, time in seconds = 2.9 sec. (from the scale). Actual operating time = 2.9 x 0.45 = 1.31 sec. The IDMT relay will act with 1.31 seconds time delay if instantaneous over current relay fails to act. For this fault also the differential protection scheme of Generator-2 will not act since it is a through fault. fault partial differential instantaneous over current relay

UNSYMMETRICAL FAULT CALCULATIONS


Here we have discussed the most occurring unsymmetrical fault i.e. L-G fault only. The 3 sequence diagrams are enclosed.

FOR L-G FAULT OR EARTH FAULT AT F 1


From the sequence diagrams Equivalent positive sequence impedance at fault point F1 = Z1 = j 0.131922 pu Equivalent negative sequence impedance at fault point F1 = Z2 = j 0.121268 pu Equivalent zero sequence impedance at fault point F1 = Z0 = 17.3652+ j 0.413 pu For L-G fault, the positive, negative and zero sequence networks are connected in series. EO 1.0 IR1 = IR2 = IRO = ----------------- = -------------------------------Z1+Z2+Z0 17.3652 + J 0.66618 = 0.057544 -2.197O
48

Fault current If = 3 x IR1 = 3 x 0.057544 = 0.172632 pu

If = 0.17263 x 5248.6388 = 906.083 A

If = 906.083 A

The contribution of each generator to the fault are given as: Current contributed by Generator-1, IG1 (pu) = 0.09084 IG1 = 0.09084 x 5248.6388 = 476.7863 A

IG1 = 476.7863 A
Current contributed by Generator-2, IG2 (pu) = 0.047182 IG2 = 0.047182 x 5248.6388 = 247.6413 A

IG2 = 247.6413 A

Current contributed by Generator-3, IG3 (pu) = 0.03461 IG3 = 0.03461 x 5248.6388 = 181.6554 A

IG3 = 181.6554 A

The relay which is operated is: Fault current If = 906.083 A Fault current when referred to CT secondary = 906.083 / 4500 = 0.201352
49

Partial differential protection for GSB-1 Section-1 Plug setting = 0.1 A Time multiplier setting = 0.3 Plug setting multiplier = 0.201352 / 0.1 = 2.0135 From the scale for PSM = 2.0135, time in sec = 10 sec. The time required for the relay to operate for the earth fault at F1 = 10 x 0.3 = 3 Sec. Partial differential IDMT earth fault relay (51N) of GSB-1 Section-1 will act with operating time = 3 Sec. Here the fault is at GSB-1 Section-1 so the restricted earth fault relay will not operate since it is a through fault. If the earth fault is at generator terminals then for the same fault current i.e. If = 906.083 Amps the current contribution of each Generator are: IG1 = 476.7863 A IG2 = 247.6413 A IG3 = 181.6554 A IG1 when referred to CT secondary = 476.7863 / 4500 = 0.106 A The restricted earth fault relay setting = 0.05 Amps Restricted earth fault relay of Generator-1 will operate for Earth faults at Generator-1 terminals only.

FOR L-G FAULT OR EARTH FAULT AT F 2


From the sequence diagrams Equivalent positive sequence impedance at fault point F2 = Z1 = j 0.11368 pu Equivalent negative sequence impedance at fault point F2 = Z2 = j 0.1179 pu Equivalent zero sequence impedance at fault point F2=Z0=17.5537+j 0.413225 pu
50

For L-G fault, the positive, negative and zero sequence networks are connected in series. EO 1.0 IR1 = IR2 = IRO = ----------------- = -------------------------------Z1+Z2+Z0 17.3553 + J 0.644805 = 0.0575796 -2.128O Fault current If = 3 x IR1 = 3 x 0.0575796 = 0.172738 pu

If = 0.172738 x 5248.6388 = 906.64 A

If = 906.64 A
The contribution of each generator to the fault are given as: Current contributed by Generator-1, IG1 (pu) = 0.04720235 IG1 = 0.04720235 x 5248.6388 = 247.748 A

IG1 = 247.748 A
Current contributed by Generator-2, IG2 (pu) = 0.07833 IG2 = 0.07833 x 5248.6388 = 411.1432 A

IG2 = 411.1432 A

Current contributed by Generator-3, IG3 (pu) = 0.04720235 IG3 = 0.04720235 x 5248.6388 = 247.748 A

IG3 = 247.748 A

51

The relay which is operated is: Fault current If = 906.64 A Fault current when referred to CT secondary = 906.64 / 4500 = 0.2015

Partial differential protection for GSB-1 Section-1 Plug setting = 0.1 A Time multiplier setting = 0.3 Plug setting multiplier = 0.2015 / 0.1 = 2.015 From the scale for PSM = 2.015, time in sec = 10 sec. The time required for the relay to operate for the earth fault at F1 = 10 x 0.3 = 3 Sec. Partial differential IDMT earth fault relay (51N) of GSB-1 Section-1 will act with operating time = 3 Sec. Here also the fault is at GSB-1 Section-2 so the restricted earth fault relay will not operate since it is a through fault. If the earth fault is at second generator terminals then for the same fault current i.e. If = 906.64 Amps the current contribution of each Generator are: IG1 = 247.748 A IG2 = 411.1432 A IG3 = 247.748 A IG2 when referred to CT secondary = 411.1432 / 4500 = 0.0914 A The restricted earth fault relay setting = 0.05 Amps Restricted earth fault relay of Generator-2 will operate for Earth faults at Generator-2 terminals only.

52

Chapter-6 CONCLUSION
The very purpose of protection system is to monitor the unwanted conditions and when such conditions arise, to remove the fault in the shortest time possible, leaving unaffected are operational.

In this project we have studied analysed the protection provided to 60 MW Turbo generator in Thermal Power Plant of

Visakhapatnam Steel Plant.

In this we have analysed both

symmetrical and unsymmetrical faults and response of different relays for these faults with the existing settings. In the present age, microprocessor based relays have come to market. These relays provide a spectrum of information in a single relay. Practically it has been observed that these relays are good from the study and analysis point of view where as for reliability and dependability, the Electro Mechanical and Electro Magnetic Relays are still superior to microprocessor based relays. Since

Electromechanical relays operate only with actual electrical signals.

53

Potrebbero piacerti anche