Sei sulla pagina 1di 23

Estidama Implementation Plan

Al Mafraq Hospital

Prepared by Sustainability Manager Wissam Yassine QA/QC Manager

Reviewed HSE Manager Stephen Lapsley

Approved Project Director Vanessa Currie

Date

Rev

Mike McDonnell

06-04-2011

Estidama Implementation Plan


Al Mafraq Hospital

Waste Management Plan

Table of Contents:

0.0 Table of Contents 1.0 Introduction 2.0 Project Description 2.1 2.2 2.3 Overview Sustainability Objectives HLMR Responsibilities

2 3 3 3 3 4 5 5 6 8 9 10

3.0 Managing the Sustainability Objectives 3.1 3.2 HLMR Management Plans Material & Procurement

4.0 Roles & Responsibilities 5.0 Monitoring & Inspecting 6.0 Education & Training 7.0 Appendices 7.1 7.2 7.3 7.4 7.5 Appendix A Appendix B Appendix C Appendix D Appendix E Estidama Material Compliance Sheet Estidama Material Tracking Document Estidama Material Registers Expected Recycled/Regional Materials Training Register & Program

11 12 13 14 15

Page 2 of 15

Estidama Implementation Plan


Al Mafraq Hospital

Waste Management Plan

1.0 Introduction
This Estidama Implementation Plan provides the framework on how HLMR plan to meet the sustainability objectives of Al Mafraq Hospital; it shall serve as a high level plan defining HLMR responsibilities. Specific plans will be developed to address specific requirements, these are: IAQ Management Plan, Waste Management Plan and Construction Environmental Management Plan, these plans will be cross referenced in the Estidama Implementation Plan as appropriate.

2.0 Project Description 2.1 Overview


The project involve the construction of a 745-bed general hospital which will be one of the leading trauma/surgery hospitals in the region, and will provide a cost-effective alternative for patients who previously had to seek specialised care overseas for neurosurgery, orthopaedics, acute rehabilitation and plastic surgery. HLMR scope of works includes construction of: Two-story basement including service accommodation, labs, CSSD, dining and parking. Three-story outpatient building including clinics and auditorium facilities. Link Bridge. Three-story podium building including diagnostics, operating theatres, ER, rehab, ICU and maternity. Two nine-story and two 11-storey inpatient towers. Peripheral buildings including substations, cooling plant, workshop, mortuary, underground tanks and service tunnels. Landscaping, infrastructure and external works.

2.2 Sustainability Objectives


Project specs section 01353 Estidama Requirements, call for compliance with certain Estidama prerequisites and credits needed for project to obtain Estidama- certified 1 pearl certification based on Estidama Building Guidelines Assessment Method Report, May, 2008 Issue . However, since the referenced Estidama guideline and credits are out-dated and cannot be utilized, HLMR put in RFI-002 requesting permission to follow the newest Estidama guideline to achieve 1 pearl certification. The Engineer replied by instructing HLMR to follow the specs, confirming that the project doesn t seek official certification and that no application will be made to the UPC. Moreover the Engineer said that Estidama requirements will be followed on the project only as adherence to the environmental best practices . Thus, the compliance with the sustainability requirements on the project will be assessed solely by the Engineer/Employer with no submission made to any external agencies for certification. This Estidama Implementation Plan will extract the sustainability requirements which are the contractor s responsibility from the specs, present their requirements and our plan to comply with these requirements.

Page 3 of 15

Estidama Implementation Plan


Al Mafraq Hospital

Waste Management Plan

2.3 HLMR Responsibilities


The project specs refer to several credits which are the contractor s responsibility and these are reproduced in the following schedule. There is also reference to other credits which are solely design credits such as water efficient appliances, external lighting, smoking ban, and operational waste management. HLMR cannot influence the compliance with these credits and will just follow the design drawings and specs and provide any required supporting documentation upon the Engineer request. The following table lists the credits that are under HLMR s direct control and their requirements. Contractor Estidama Responsibility Matrix Reference Energy Use ADE3 External Lighting HLMR to submit technical analysis prepared by supplier of external lighting control system (sensor) to identify how the lighting energy will be minimized. 1- Implement a measurement and verification plan that evaluates energy performance and efficiency by comparing actual to predicted performance. 2- Measurement and verification period shall cover not less than at least one year of postconstruction occupancy. HLMR to submit technical report prepared by subcontractor of lifts and escalators how the use of energy efficient motors has participated in reduction of the energy consumption in the lifts and escalators and accordingly in the overall energy consumption of the project. 1- Evidence that mineral fibre or glass wool suspended ceiling will not contribute in the increase in the pollutants. 2- Comply with VOC content for adhesives, sealants, paints & coatings on the project. 3- No added urea formaldehyde in composite wood & Agrifibre products. 4- High performance cleaning. Develop & implement in IAQ Management plan during construction that meets the SMACNA guidelines. 1- Regional Material: Minimum 10% (by cost) of the material should be extracted and manufactured within 800 KM from the project. 2- Recycled Content: Minimum 10% (by cost) of the materials should be made of recycled content. All indoor floor finishes are to be approved in writing by the future occupants. HLMR to submit samples of full range of each material for selection by Employer and Operator. Secondary Credit Title Credit Requirements HLMR Responsibility

ADE4

Information on Energy use & savings

Primary

ADE6

Lifts & Escalators

Secondary

Indoor Environmental Quality

ADIEQ4

Indoor Air Quality

Primary

Management ADM1 Materials Construction Indoor-AirQuality Management Primary

ADMAT1

Material Specifications: Major Building Elements

Primary

ADMAT3

Indoor Floor Finishes

Secondary
Page 4 of 15

Estidama Implementation Plan


Al Mafraq Hospital

Waste Management Plan

ADMAT5

Sustainable Material Sourcing

ADMAT7

Insulating Materials

N/A

Certified Wood

Develop sustainable procurement policy and procedures, ensuring that it encompass key aspects of sustainability. 1- Use only thermal insulants and refrigerants that are free from ozone depleting substances in either manufacture or composition which means that they have an Ozone Depleting Potential (ODP) of zero. 2- No asbestos to be used within the development. Provide a minimum of 50 percent (by cost) of wood-based materials that are produced from wood obtained from forests certified by an FSC-accredited certification body Procurement strategy which includes review of materials sourcing for longevity, waste minimization and recyclability

Primary

Primary

Primary

Waste Management ADWAS1 Reduction of Waste Primary

When there were different credit requirements between the Estidama guideline and the project specs, the requirements of the specs took precedence.

3.0 Managing the Sustainability Objectives 3.1 Estidama Management Plans


HLMR realizes that reaching the sustainability objectives of the project requires dedication and commitment and for this purpose we have developed individual management plans to help us tailor specific solutions to suit the individual requirements of the Estidama credits. These plans will be submitted for approval separately, a general overview of each of these plans and how to they contribute to achieving the specific Estidama credits is presented here: Construction Environmental Management Plan The construction environmental management plan for the project establish the general environmental protection procedures that will be implemented on site during construction and will cross reference Estidama specific plans where applicable. Construction Waste Management Plan A construction waste management plans will be developed and implemented on site in line with project specification section 01524: Construction Waste Management. We noticed that there are no construction waste management recycling targets in the Estidama guideline or the project specifications. However, we are confident that our procedures will enable us to recycle at least 50% by weight of the waste generated on site. This will be detailed in the waste management plan. A waste management subcontractor has been identified and engaged. To maintain greater control over recycling rate, the scope of the waste subcontractor is limited to identifying recycling facilities and transferring the waste from site and obtaining the required documentation from the recyclers. Maintaining control over this activity on site will enable us to develop the mentality of our work force in terms of construction waste management.
Page 5 of 15

Estidama Implementation Plan


Al Mafraq Hospital

Waste Management Plan

Indoor Air Quality Management Credit ADM 1 addresses construction Indoor Air Quality. The intent is to reduce indoor air quality problems resulting from the construction process in order to help sustain the comfort and well-being of construction workers and building occupants. To address all these issue HLMR, in coordination with the MEP contractor, will develop an IAQ Management Plan, this details best practices among different areas that might affect IAQ during construction. The plan will conform to the SMACNA guidelines as required by the credit.

3.2 Sustainable Procurement Strategy


Materials used to construct a project constitute a considerable amount of the embodied environmental footprint of the building. Thus, developing a sustainable procurement strategy where selecting material is subject to certain sustainable criteria is a very important aspect when developing a sustainable project. This section will describe the sustainable material attributes which will be used to inform material selection decisions on the project. The criteria will mainly stem from the Estidama specification requirements. An Estidama Compliance Sheet was developed for the project which is attached in Appendix-A. This will be filled & stamped by suppliers/manufacturer and included in all material submittals in addition to any required back-up documents to assess and document the sustainable attributes of each material. In addition, a Material Tracking Document is being prepared which will include the cost of all materials that are required for tracking by the Estidama credits (Div. 2 to Div. 10), this will cover the recycled, regional and certified wood credits. A template of this tracking document is included in Appendix-B. Other credits such as low VOC content, zero ODP will be tracked using a set of registers which are included in Appendix-C. These tracking documents will be updated regularly and issued to the Engineer in the Estidama monthly report to keep him updated on the status of the material sustainable criteria achievement. The following tabulates the credits that regulate the materials to be used on the project, how HLMR intend to comply with the requirements and the compliance documentation which will be produced: Estidama Material Credits Credit Credit Requirements Indoor Environmental Quality Evidence that mineral fiber or glass wool suspended ceiling will not contribute in the increase in the pollutants. ADIEQ4: Indoor Air Quality Comply with VOC content for adhesives & sealants, paints & coatings used on the project. Plan for Compliance Documentation Estidama Compliance sheet filled & stamped with supporting documentation in form of manufacturer datasheets, test reports, etc. Estidama Compliance sheet filled & stamped with supporting documentation such as MSDS or tests.
Page 6 of 15

For any suspended ceiling produced from mineral fiber or glass wool, discussion with manufacturer will take place to select a product that minimizes indoor pollution. All adhesives, sealants, paints and coatings used on the project will meet the VOC content as per the project specs.

Estidama Implementation Plan


Al Mafraq Hospital

Waste Management Plan

No added urea formaldehyde in composite wood & Agrifibre products. ADIEQ4: Indoor Air Quality High Performance Cleaning

Any composite wood or Agrifibre product used on the project shall not contain added urea formaldehyde Manufacturer recommendation for cleaning will be obtained for finishing or furniture items that may cause dust accumulation.

Estidama compliance sheet filled & stamped by the supplier/manufacturer confirming no added formaldehyde Cleaning recommendation report by the manufacturer of items such as ceiling, carpet & furniture.

Material Regional Material: Minimum 10% (by cost) of the material should be extracted and manufactured within 800 KM from the project. (Note that the specs call for calculation by volume. Since this is not practical, we propose doing the calculations by cost) Recycled Content: Minimum 10% (by cost) of the materials should be made of recycled content. (Note that the specs doesn t call for specific percentage of recycled content, thus we are proposing 10% by cost recycled content) All indoor floor finishes are to be approved in writing by the future occupants. HLMR to submit samples of full range of each material for selection by Employer and Operator. Review of the sustainable procurement policy and procedures, ensuring that these encompass key aspects of sustainability. Use only thermal insulants and refrigerants that are free from ozone depleting substances in either manufacture or composition which means that they have an Ozone Depleting Potential (ODP) of zero. No asbestos to be used within the development.

ADM1: Material Specifications, Major Building Elements

Based on our experience in the market, we have identified possible materials that can comply with the 10% regional & recycled content requirements. This is attached in appendixD.

1- Estidama compliance sheet filled & stamped by the supplier /manufacturer in addition to any required supporting documentation. 2- Material tracking document to track & demonstrate the achieved percentage of recycled and regional material.

ADMAT3: Indoor Floor Finishes

As part of our normal approval procedures, all finishes will be submitted for approval by the Engineer with sample provided if required. This plan constitutes the sustainable procurement policy for the project with specific sustainable criteria for materials.

None.

ADMAT5: Sustainable Material Sourcing

None.

ADMAT7: Insulating Materials

Confirmation will be obtained from thermal insulants and refrigerants manufacturers confirming zero ODP

Confirmation will be obtained from all material suppliers / manufacturers confirming no asbestos is used.

Estidama compliance sheet filled & stamped by the supplier /manufacturer in addition to any required supporting documentation.

Page 7 of 15

Estidama Implementation Plan


Al Mafraq Hospital

Waste Management Plan

Certified Wood

Provide a minimum of 50 percent (by cost) of woodbased materials that are produced from wood obtained from forests certified by an FSC-accredited certification body

50% by cost of the wood products used on the project will be FSC certified.

Estidama compliance sheet filled & stamped by the supplier /manufacturer in addition to any required supporting documentation such as CoC certificates. Estidama compliance sheet filled & stamped by the supplier /manufacturer confirming material is recyclable.

Waste Management Procurement strategy which includes review of materials sourcing for longevity, waste minimization and recyclability We will identify will our suppliers the possibility of recycling the building materials and preference will be given to recyclable material.

ADWAS1: Reduction of Waste

4.0 Roles & Responsibilities


The entire project team will play a part in the achievement of the project s sustainability objectives, every workforce will be trained to objectives related to waste management, Indoor Air Quality, etc... we envisage that by the project s mid phase the workforce overall environmental awareness will reach a level where constant monitoring won t be necessary and sustainable practices will be built in within the normal habits of the staff, nevertheless a lot have to be done to see this transformation and this shall be detailed in section 8.0 education and training. This is mind; there are a number of key leadership roles within the projects team which have defined responsibility for delivering the sustainability objectives of the project, these are presented next and their roles and responsibilities will be explained. Name: Position: Mobile No.: E-mail: Name: Position: Mobile No.: E-mail: Wissam Yassine Sustainability Manager 050-9122338 Wissam.Yassine@hlg.ae Name: Position: Mobile No.: E-mail: Name: Position: Mobile No.: E-mail: Stephen Lapsley HSE Manager Stephen.Lapsley@hlg.ae Mike McDonnell QA/QC Manager 050-6670284 Mike.McDonnell@hlg.ae

Sustainability & Environment Officer

Title

Sustainability Manager

Sustainability Team & Responsibilities Roles and Responsibilities 1- Overall responsibility for delivering sustainability objectives of the project. 2- Developing the Contractor s sustainability Management plans, presenting the procedures and measures to achieve the sustainable requirements. 3- Develop & update an Estidama Electronic Notebook with all documentations for demonstrating compliance. 4- Issuing monthly Estidama progress reports.

Availability

Part time

Page 8 of 15

Estidama Implementation Plan


Al Mafraq Hospital

Waste Management Plan

EHS Manager

QA/QC Manager

Sustainability & Environment Officer

1- Overall responsibility of all environmental aspects on site. 2- Responsible for the ensuring the Environmental Management plans are being adhered to during construction. 3- Insure Environmental awareness and provide training to employees. 1- Coordinate with suppliers/sub-contractors to insure Estidama Compliance sheet is filled, stamped and attached with submittals. 2- Responsible for reviewing material submittals against the developed sustainable procurement strategy to insure sustainable criteria are adhered to. 1- Responsible for monitoring the site on a daily basis to ensure all measures and procedures are being followed as detailed in the individual plans. 2- Carry out inspections as detailed in the Estidama Implementation plan.

Full time

Full time

Full time

The sustainability manager will prepare and issue an Estidama monthly report at the beginning of each month. This will allow the Engineer/Employer to assess the status of compliance with the sustainability requirements throughout the project duration. The report will include the following information: Material tracking log to track recycled content, regional material and certified wood credits. Other Estidama Materials registers. Material submittals and their Estidama compliance sheets. Construction Waste Management Monthly report. Copies of monthly IAQ, Waste management inspections. CD of the Estidama Electronic Notebook with all supporting documentation.

5.0 Monitoring & Inspecting


We realize that the current workforce culture and work habits will present an obstacle in reaching the sustainability objectives of Al Mafraq Hospital. A Sustainability & Environment officer have been assigned as part of the HSE team, his responsibilities will be to daily monitor all activities on site and ensure measures and recommendations presented in the management plans are being adhered to by the workforce. Daily visits by the HSE Manager will ensure all staff are aware of the management commitment to the environmental objectives of the project. The Sustainability Manager will also conduct regular site walks to ensure the overall compliance with the sustainability management plans, and evaluate the need to develop new measures to cover the changing conditions of the project site. In addition to daily monitoring, documented inspection will be carried out to document any concerns in the procedures and any lack of compliance by a certain trade. Inspection requirements have been addressed in each individual plan and are summarized here:

Page 9 of 15

Estidama Implementation Plan


Al Mafraq Hospital

Waste Management Plan

Inspections Schedule Report Waste Management Inspection Description Inspection of the waste collection infrastructure and the waste collection/segregation/transportation procedure will be carried out by the Sustainability & Environment officer to ensure and document compliance with the waste management plan. Inspection to ensure that the Indoor Air Quality Management Plan is implemented correctly and achieved its objectives. The Sustainability & Environment officer will be responsible for monitoring and inspecting the IAQ measures detailed in the IAQ plan Frequency

IAQ Inspection

Inspections will be conducted internally each week. Monthly inspections carried out in the last week on each month will be included in the Estidama monthly report.

Inspection templates will be included in the respective management plans.

6.0 Education & Training


Achieving the sustainability objectives of the project requires a collaborative effort by the entire project team. Currently the general culture of the workforce doesn t support this and environmental awareness is something that needs to be introduced. This section outlines the training and education requirements of the project and measures whereby the environmental awareness of all staff involved in the project will be raised to ensure the project sustainability objectives are met. HLMR are hopeful that by the mid phase of the project we would have developed a competent workforce that is fully versed on the environmental requirements of the project. The need for specific environmental training (waste management, IAQ, pollution prevention etc.) was evaluated and a proper training program was developed to address these needs. Environmental issues are also discussed with the workers at the Toolbox Meetings which are to be held once a week on site. These meetings will be used to review compliance with environmental requirements, communicate lessons learnt from environmental incidents, and make recommendations for correcting or minimizing non-compliance. In addition to construction personnel, all temporary visitors to the construction site who s activities have the potential to cause significant environmental impacts (such as fuel delivery personnel) will be required to undergo an abbreviated version of Sustainability/Environmental induction to ensure they are aware of environmental requirements. Training sessions will be organized by the HSE department. A proper record of the training schedule and attendance is to be kept for future reference. The register in included in appendix-E and will be used in recording attendance at training sessions. Training records will be maintained by the HSE Manager and reviewed periodically. Our training & Education program is attached in appendix-E Training session s content will be based on the approved management plans developed to address the individual environmental concerns; this will ensure all measures addressed in these plans are covered and that the workforce shares a common understanding of the project s objectives.

Page 10 of 15

Estidama Implementation Plan


Al Mafraq Hospital

Waste Management Plan

APPENDIX A

Estidama Material Compliance Sheet

Page 11 of 15

Estidama Compliance Sheet Al Mafraq Hospital


Material: Supplier/Sub contractor: Product Manufacturer: Relevant Credit(s): CREDIT TITLE DESCRIPTION RESPONSE Company stamp & authorized signature here

ADM1: Material Post consumer recycled content Specifications Recycled Content Pre consumer recycled content ADWAS1: Reduction of Waste What is the life time of the product Confirm if the product is easily recyclable after the its life time Raw material (extraction) source location & distance to project

ADM1: Material Specifications Manufacturing location & distance to project Regional Material % of material by weight that is extracted & manufactured within 800 KM from the site Is the product FSC certified? Certified Wood Provide COC certification number ADIEQ 4: Indoor VOC Content Air Quality Adhesives, Sealants, Paint or Allowable VOC Content (as per specs) Coating Mineral Fiber & Glass wool suspended Ceiling: Confirm product will not contribute to increase in pollution ADIEQ 4: Indoor Composite Wood & agrifibre products: Air Quality Confirm no added urea formaldehyde Finishes & Furniture: Provide cleaning procedure recommendation Thermal Insulants: Confirm product have an Ozone Depletion Potential of Zero Refrigerants: Confirm refrigerant have an Ozone Depletion Potential of Zero

ADMAT7: Insulating Materials

Estidama Implementation Plan


Al Mafraq Hospital

Waste Management Plan

APPENDIX B

Estidama Material Tracking Document

Page 12 of 15

Al Mafraq Hospital ESTIDAMA MATERIALS TRACKING DOCUMENT


Product Name and Company, Source of Information (attach cut sheets)
Total Construction Cost
AED

Labor Cost

Equipment Cost

MATERIAL
DIVISION 2: SITE WORK
02302 02900 03200 03300 09221 Earthwork Planting Concrete Reinforcement Cast-in-Place Concrete Plaster Screed Masonry Units Structural Steel Steel Stair and Railings Glas Supported Railings Misc Metal Fabrications Int/Ext Expansion Joint Covers Wood Trellis (Rough Carpentry) Panelling Interior Arch. Woodwork Plastic Laminate

Material Cost (Less Labor & Equipment)


AED

Recycled Content
Percentage Amount of of total Material material cost Procured as off

Regional Materials Value


AED

Certified Wood New Wood-Based Materials


AED

PostConsumer
[%]

PreConsumer
[%]

Regional Material [%]


-

Value AED
-

Certified Wood
AED

% Certified Wood

AED

AED

Forest Stewardship Council Chain of Custody Certificate Number

#DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!

DIVISION 3: CONCRETE

DIVISION 4: MASONRY
04200 05120 05502 05722 05501 05800 06000 06420 06402 06600 07100 07210 07212 07224 07242 07422 07430 07500 07600 08100 08200 08300 08310 08312 08360 08362 08522 08710 08721 08804 08800 08816 08900 08600 09201 09221 09230 09250 09312 09506 09510 09545 09636 09644 09666 09690 09705 09735 09706 09771 09775 09904 09960 09900

DIVISION 5: METALS

DIVISION 6: WOODS AND PLASTICS

DIVISION 7: THERMAL & MOISTURE PROTECTION


Waterproofing - PVC Membrane (Excluding Screed) Building Insulation Cellular Glass Insulation Spray Applied Thermal Ins Exterior Insulation (Excluding Plaster) Aluminium Comp Panels Metal Column Covers Modified Bit Membrane WP Flashing and Sheet Metal HM Doors & Frames Wood Doors Smoke Containment Systems Manual Sliding Doors Access Panels and Doors Operable Glass Walls Over head coiling doors Aluminium Windows Door Hardware/ironmong Auto Sliding Doors Interior Glass Glazing Exterior Glass Glazing Decorative Glass Curtain Wall System Skylights Metal Furring and Lathing PC Plaster (excluding Plaster) Glass Reinforced Gypsum Gypsum Wall Board Ceramic Tile (Excluding Screed) Acosutic Plaster Ceiling Acoustic Ceiling Tile Wood Ceiling System Stone Flooring (Excluding Screed) Athletic Wood Flooring (Excluding Screed) Sheet Rubber Flooring (Excluding Screed) Carpet (Excluding Screed) Epoxy Flooring (Excluding Screed) Thin Set Terrazzo Flooring (Excluding Screed) Urethane Flooring (Excluding Screed) Fabric Wrapped Panels (Excluding Plaster) Metal Column Covers Interior Interior Painting (Excluding Plaster) Wall Covering (Excluding Plaster) Wood Flooring (Excluding Screed)

DIVISION 8: DOORS & WINDOWS

DIVISION 9: FINISHES

Al Mafraq Hospital ESTIDAMA MATERIALS TRACKING DOCUMENT


Product Name and Company, Source of Information (attach cut sheets)
Total Construction Cost
AED

Labor Cost

Equipment Cost

MATERIAL
DIVISION 10: SPECIALTIES
10260 10266 10400 10503 10800 00000 Wall Protection Specialties High Density Wall Protection Signage Phenolic Lockers and Bench Toilet Accessories Landscaping/ External Works

Material Cost (Less Labor & Equipment)


AED

Recycled Content
Percentage Amount of of total Material material cost Procured as off

Regional Materials Value


AED

Certified Wood New Wood-Based Materials


AED

PostConsumer
[%]

PreConsumer
[%]

Regional Material [%]


-

Value AED
AED 0

Certified Wood
AED

% Certified Wood

AED

AED

Forest Stewardship Council Chain of Custody Certificate Number

AED 0.00 AED 0.00 AED 0.00 AED 0.00

#DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!

AED 0

TOTAL

AED 0

0.00

0.00

Recycled Achieved: Content =

#DIV/0!

Regional Material =

#DIV/0!

Estidama Implementation Plan


Al Mafraq Hospital

Waste Management Plan

APPENDIX C

Estidama Material Registers

Page 13 of 15

Al Mafraq Hospital Estidama Credit Register: ADIEQ 4 Indoor Air Quality Adhesives, Sealants, Paints & Coatings
Product Manufacturer Product Name Product VOC Content Allowable VOC Content Source of data

Al Mafraq Hospital Estidama Credit Register: ADIEQ 4 Indoor Air Quality Thermal Insulants & Refrigerants
Product Manufacturer Product Name Confirm Product have Zero Ozone Depletion Potential Source of data

Estidama Implementation Plan


Al Mafraq Hospital

Waste Management Plan

APPENDIX D

Expected Recycled/Regional Material

Page 14 of 15

Recycled content & Regional Material Based on our experience with sustainable projects and our market knowledge we expect the following materials to make contribution towards achieving the 10% recycled content requirement: Expected Material that will contribute to Recycled Content Material Expected Recycled Content Steel Reinforcement 100% Cast-in-Place Concrete 20% Structural Steel 50% Curtain Wall System 50% Aluminum Composite Panels 50% Door Hardware / Ironmongery 50% Gypsum Wall Board 20%

Division 03200 03300 05120 08900 07422 08710 09250

In addition the following materials are expected to contribute towards achieving the 10% regional material requirement: Expected Material that will contribute to Regional Material Material Expected Regional Percentage Concrete 90% Screed 100% Ordinary Portland Cement 100% Masonry Units 100% Mineral Fiber Insulation 100% Plaster 100% Ceramic Tiles 80% Interior Painting 70%

Division 03300 xxxxx 03300 04200 04200 09221 09312 09904

Estidama Implementation Plan


Al Mafraq Hospital

Waste Management Plan

APPENDIX E

Training program & register

Page 15 of 15

Al Mafraq Hospital Training & Education Program


Training Module Estidama Introduction & project objectives General Environmental Awareness Trainer Sustainability Manager HSE Manager Sustainability & Environment Officer Sustainability & Environment Officer Sustainability & Environment Officer Sustainability & Environment Officer Targeted Audience All project team & Major Subcontractors All project team & Major Subcontractors Workforce Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11

General Environmental Awareness

Waste Management Plan Erosion & Sedimentation Control BMPs Indoor Air Quality Management

Workforce

Workforce

Workforce

Training Record & Attendance Form


Al Mafraq Hospital
Training Title: ___________________________ Venue : Presenter : Training Ref: ________________ Training Date:

Brief Description of the Training:

No. 1 2 3 4 5 6 7 8 9 10 11 12 13 15 16 17 Signed:

Name

Designation

Code No.

Signature

Department Head

Date:

Cc: Notification to PD, PM, CM and Project File Bcc: HR- Training Department
ASP

Potrebbero piacerti anche