Method of Statement for the Preparation of Pipe Tapping Works To The Existing Main Pipework.
Purpose
This procedure outlines the necessary actions and safety practises for preparation of pipe tapping work to the existing main pipework at Clean Room Area Support A - Level 3
Responsibility
Plumbing Work Foreman, Pipe Fitters, Construction Co-ordinator, Project Engineer, Site Supervisor, Project Manager & Safety Officer
Discussion
In order to ensure a correct connection to of the new pipeline the existing sprinkler riser. . The procedures also outline proper safety practises that must be followed in order to minimize risks.
Requirements
Tools and Equipment All personnel within the area shall be required to wear eye personnel protection equipment (PPE), hard hat, safety shoe & safety harness. Mechanical Couplings, Short piece of pipe with groove thread, plastic sheets, A-ladder.