Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Outline
Introduction RealTime Analytics Overview of Joint Confidence Level Analysis NASAs Joint Confidence Level Policy Dynamic Integrated Cost Estimator (DICE) JCL Analysis Tool
Attempt at Humor
Introduction
Whether assessing/analyzing NASA, DoD or Intelligence Community owned projects, the story is the same each time: Programs are increasingly experiencing growth above and beyond their initial cost and schedule estimates This is not just a cosmetic problem: Cost and schedule growth delays capabilities and constraints the budgets of other programs causing a waterfall of instability Studies have examined the reasons behind this growth reaching similar conclusions 1. Early program optimism leading to optimistic estimates
RealTime Analytics
One of the challenges in performing cost and schedule analysis is the time required to run simulations Risk analysis, required for all cost estimates by 2009 Weapons System Acquisition Reform Act of 2009 and GAO, requires the use of simulations Run-times of minutes or hours prohibit most risk analyses models from being decision making tools as they can not be re-run during meetings RealTime Analytics (RTA) is a collection of technologies, tools and methodologies allowing complex analytics to be performed far faster than using currently available methods This presentation will focus on the Dynamic Integrated Cost Estimator (DICE) and the methodologies it addresses: Joint Confidence Level Analysis (Integrated Cost & Schedule Risk Analysis) RTA tools allow simulations to run up to 99.99% faster than comparable industry tools Simulations formerly taking minutes or hours to run now finish in under 1 second Allows decision makers to run an unlimited number of excursion scenarios without ever leaving the meeting room
Prioritize risks and other threats based on their overall impact to the program and not simply their anticipated local impact
Develop more precise risk mitigation plans
1Also
Cost
known as Integrated Cost & Schedule Risk Analysis or Joint Cost & Schedule Risk Analysis
6
Launch Date
4/11/11 9/23/10
$603 $803
$1,003
$1,203
1Joint
Cost Schedule Model (JCSM): Recent AFCAA Efforts to Assess Integrated Cost and Schedule Analysis. Hogan, Greg (et al). SCEA 2011 8
Final Results
7/24/14
Cost FOC
Launch Date
Joint Risk Analysis methods estimate cost and schedule simultaneously; JCL scatter plot produced directly from analysis
4/11/11 9/23/10
$603 $803
$1,003
$1,203
Cost Risk Analysis: Inputs-Based Simulation Outputs-Based Simulation Scenario Based Parametric Analysis
When Joint Risk Analysis methods are not used, cost and schedule risk analyses must be combined using a Monte Carlo simulation
7/24/14
Launch Date
4/11/11 9/23/10
$603 $803
$1,003
$1,203
When risk analyses are combined, care must be taken to ensure results are compatible
1Joint
Cost Schedule Model (JCSM): Recent AFCAA Efforts to Assess Integrated Cost and Schedule Analysis. Hogan, Greg (et al). SCEA 2011 9
Cost Estimate
A quantified risk register (probabilities, cost and schedule impacts) where each risk is mapped to a task in the IMS
A cost estimate with uncertainty bounds that maps to the schedule Creation of these artifacts requires communication between programs cost estimating, scheduling and risk management staff
10
NASA Policy Directive 1000.5 mandates that programs will be baselined at the 70 percent confidence level using a joint cost and schedule probability distribution2
NPD 1000.5 also stipulates that projects are funded at no less than 50% of the JCL or as approved by the decision authority, maintaining JCLs through the program lifecycle The goal is to provide stronger assurance that NASA can meet cost and schedule targets3
A recent GAO report cites NASAs JCL policy as an effort to provide transparency on the effects of funding changes on the probability of meeting cost and schedule commitments 4
NASA Cost Analysis Division (CAD) has developed a handbook to provide more information and guidance on this topic Programs conducting JCL Analysis include James Webb Space Telescope and SOFIA While the methodology has made substantial strides, the cost and schedule communities must overcome political and technical obstacles before full adoption
NPD 1000.5 - http://www.hq.nasa.gov/office/codeq/doctree/10005.htm - January 15, 2009 JCL Status Report - http://www.nasa.gov/pdf/421542main_JCL%20Status%20Report-2010%20Feb.pdf February 2010 4 GAO Report NASA Assessments of Selected Large-Scale Projects - http://www.gao.gov/new.items/d11239sp.pdf - March 2011
2 3
11
It is important to note that there are many tools that projects can use to develop JCLs, but DICE is optimized for this analysis
12
13
DICE
Opening Tool Import Schedule Load Risk File Initialize Correlation Run Simulation Export Data 0:02 0:03 0:03 0:02 0:09 0:08
Primavera
0:05 2:05:27 0:01 0:05 2:27 0:00
Schedule
Cost
Key Points Identical input parameters to ensure consistency in benchmarking Importing risks from 3rd party template
Correlation
14
DICE Demo
15
Conclusion
Booz Allens recent innovations in simulation technology enable analysts to support decision making in near real-time Decision makers can see the impact of changes to their program, real-time, without ever leaving the meeting room There is no longer a limit on the number of excursions that can be run on an analysis New Joint Confidence Level methods changes the way programs look at cost and schedule risk Analyses are no longer performed and viewed separately, but rather are integrated and optimized using a standard tool Decision makers have more insight into their program than ever before Opening of communication lines between cost, schedule and risk management staff results in better program management
16
Points of Contact
Eric Druker
Associate
Graham Gilmer
Associate
Colin Smith
Associate
Brandon Herzog
Consultant
17
Organizes project tasks, costs, constraints, schedule interrelationships, and adds uncertainty to individual cost and schedule items
18
DICE can load schedules with time-dependent and time-independent costs, generating standard outputs such as JCL scatter plots and iso-curves
19
DICE accounts for costs (and uncertainty) by fiscal year aids budget planning
20
21
22
Benefits:
Runtime savings of >99% vs. COTS tools Analysis can be run without ever leaving the meeting room Decreased simulation runtimes allows running of unlimited number of excursion scenarios
Not a numerical approximation approach such as Method of Moments, it simply runs simulations faster than existing tools
Uses: Cost estimating/risk analysis/risk management Insurance pricing/actuarial models Portfolio optimization/trade-off analysis Cash flow/profit analysis
23
File Size
265 MB
Baseline Scenario
~ ~
7 Hrs 48 Min
Crystal Ball
15 MB
RTA
Assumptions
Simulations include mix of triangular, normal, beta, lognormal and uniform distributions with same parameters in each model 444 correlated distributions with 9,620 forecasted values Baseline scenario is the time to prime the models; includes adding in correlation Each additional scenario is time to re-run model when a single distribution parameter is changed
100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0%
$25,000
$35,000
$45,000
$55,000 Cost
$65,000
$75,000
CB
RTA
'@ Risk
24