Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
b. Disregard the assumptions in Part a. What is Shrieves' depreciable basis? What are the annual depreciation expenses? Annual Depreciation Expense
Depreciable Basis = Equipment + freight + installation Depreciable Basis = $240,000 Year 1 2 3 4 % 0.33 0.45 0.15 0.07 x Basis $240,000 $240,000 $240,000 $240,000 = Depr. $79,200 $108,000 $36,000 $16,800
c. Calculate the annual sales revenues and costs (other than depreciation). Why is it important to include inflation when estimating cash flows? d. Construct annual incremental operating cash flow statements. Annual Operating Cash Flows Units Unit price Unit cost Sales Costs Depreciation Operating income before taxes (EBIT) Taxes (40%) Net operating profit after taxes Depreciation Net Operating CF Year 1 1250 $200.00 $100.00 $250,000 $125,000 $79,200 $45,800 $18,320 $27,480 $79,200 $106,680 Year 2 1250 $206.00 $103.00 $257,500 $128,750 $108,000 $20,750 $8,300 $12,450 $108,000 $120,450 Year 3 1250 $212.18 $106.09 $265,225 $132,613 $36,000 $96,612 $38,645 $57,967 $36,000 $93,967 Year 4 1250 $218.55 $109.27 $273,188 $136,588 $16,800 $119,800 $47,920 $71,880 $16,800 $88,680
e. Estimate the required net operating working capital for each year, and the cash flow due to investments in net operating working capital. Annual Cash Flows due to Investments in Net Operating Working Capital Year 0 Sales NOWC (% of sales) CF due to investment in NOWC) f. Calculate the after-tax salvage cash flow. After-tax Salvage Value Salvage Value Tax on Salvage Value Net Terminal Cash Flow $25,000 $10,000 $15,000 $30,000 ($30,000) Year 1 $250,000 $30,900 ($900) Year 2 $257,500 $31,827 ($927) Year 3 $265,225 $32,783 ($956) Year 4 $273,188 $32,783
g. Calculate the net cash flows for each year. Based on these cash flows, what are the projects NPV, IRR, MIRR, and payback? Do these indicators suggest that the project should be undertaken?
Find MIRR
Net Cash Flows
0 ($270,000)
PV=
($270,000)
TV =
To find MIRR, we could now find the discount rate that equates the PV and TV. But it is easier to use the MIRR function. MIRR = 18.0%
Find Payback
0 Cumulative Cash Flow for Payback Cum. CF > 0, hence Payback Year: Payback found with Excel function = Payback = 2.5 ($270,000) FALSE 0 1 ($164,220) FALSE 0
h. What does the term risk mean in the context of capital budgeting, to what extent can risk be quantified, and when risk is quantified, is the quantification based primarily on statistical analysis of historical data or on subjective, judgmental estimates? Risk in capital budgeting really means the probability that the actual outcome will be worse than the expected outcome. For example, if there were a high probability that the expected NPV as calculated above will actually turn out to be negative, then the project would be classified as relatively risky. The reason for a worse-than-expected outcome is, typically, because sales were lower than expected, costs were higher than expected, or the project turned out to have a higher than expected initial cost. In other words, if the assumed inputs turn out to be worse than expected then the output will likewise be worse than expected. We use Excel to examine the project's sensitivity to changes in the input variables. i. (1.) What are the three types of risk that are relevant in capital budgeting? Answer: See Chapter 11 Mini Case Show (2.) How is each of these risk types measured, and how do they relate to one another? Answer: See Chapter 11 Mini Case Show
(3.) How is each type of risk used in the capital budgeting process? Answer: See Chapter 11 Mini Case Show
NPV
-20%
0%
20%
40%
(3.) What is the primary weakness of sensitivity analysis? What is its primary usefulness? Answer: See Chapter 11 Mini Case Show k. Assume that Sidney Johnson is confident of her estimates of all the variables that affect the projects cash flows except unit sales and sales price: If product acceptance is poor, unit sales would be only 900 units a year and the unit price would only be $160; a strong consumer response would produce sales of 1,600 units and a unit price of $240. Sidney believes that there is a 25 percent chance of poor acceptance, a 25 percent chance of excellent acceptance, and a 50 percent chance of average acceptance (the base case). (1.) What is scenario analysis? Scenario analysis extends risk analysis in two ways: (1) It allows us to change more than one variable at a time, hence to see the combined effects of changes in several variables on NPV, and (2) It allows us to bring in the probabilities of to see the combined effects of changes in several variables on NPV, and (2) It allows us to bring in the probabilities of changes in the key variables. (2.) What is the worst-case NPV? The best-case NPV? (3.) Use the worst-, most likely, and best-case NPVs and probabilities of occurrence to find the projects expected NPV, standard deviation, and coefficient of variation.
Scenario Analysis
Squared Deviation times probability
NPV
Expected NPV = Standard Deviation = Coefficient of Variation = Std Dev / Expected NPV =
l. Are there problems with scenario analysis? Define simulation analysis, and discuss its principal advantages and disadvantages. Answer: See Chapter 11 Mini Case Show
Monte Carlo simulation is similar to scenario analysis in that different values of key inputs are input. Unlike scenario analysis, Monte Carlo simulation draws the input values from a specified probability distribution and then computes the NPV. It repeats this process hundred, or even thousands, of times. It then averages the NPVs from each repetition. See the file FM11 Ch 11 Mini Case Simulation.xls for a detailed example. To use this spreadsheet, you will need to install the Excel Add-In Simtools.xla . See the file Explanation of Simulation.doc for an explanation of how to install the Add-In.
(3.) Are there any subjective risk factors that should be considered before the final decision is made? Answer: See Chapter 11 Mini Case Show
dgeting analysis is being unused space in Shrieves' shipping charges would be economic life of 4 years, lass. The machinery is
ental cost of $100 per unit s price and cost are et operating working s 40 percent, and its
al depreciation expenses?
Year 4
4 $184,777 FALSE 0
the expected outcome. For urn out to be negative, come is, typically, because a higher than expected put will likewise be worse
ni Case Show
e following chart: SALVAGE NPV $88,030 $84,956 $86,493 $88,030 $89,567 $91,103
## ## ## ## ##
jects cash flows except and the unit price would 240. Sidney believes that a 50 percent chance of
ble at a time, hence to see robabilities of to see the abilities of changes in the
cording the NPV (this is for each scenario, which ialog box, and it will encourage you to explore
l advantages and
put. Unlike scenario and then computes the m each repetition. See the ll need to install the Excel all the Add-In.
nalysis above.)
Scenario Summary
Current Values: Base Case Best Case Worst Case
Changing Cells: $D$31 1250 1250 1600 900 $D$32 $200 $200 $240 $160 Result Cells: $C$109 $88,030 $88,030 $278,965 ($48,514) $C$110 23.9% 23.9% 48.3% 1.0% Notes: Current Values column represents values of changing cells at time Scenario Summary Report was created. Changing cells for each scenario are highlighted in gray.