PROJECT

CONTROL

NOTE

DATE FROM TO

20 June 2011 Bibin Krissandi KKDO Team Yogi Prasetyo Terence Stevenson Stale buri Lead Project Service Project Service Manager Area Manager Project Control Engineer

INTRODUCTION
To proposed the work processes and systems that will be used to execute the Project Controls functions and status of work progress for the KKDO Project-PCSB SBO Operations.

PLANNING & SCHEDULING (MS PROJECT AND PRIMAVERA P6)


Schedule Preparation ; early recognition of the importance of schedule to the project, to ensure identification of all required activities to complete the project, understanding critical path for the project, to ensure development of a Baseline Schedule which is consistent with the client expectations, and to presentation of the Proposed Baseline Schedule with System. Schedule Control ; to ensure the current schedule is routinely updated and reflects progress to date and forecast durations to complete, to ensure accurate and regular monitoring of progress versus Baseline Schedule, and to appropriate focus on critical path activities.

COST CONTROL (INCONTROL, GBS, PROCOMS, EXCELL)


to ensuring accurate, regular monitoring of actual costs and committed costs versus current budget, to ensuring regular assessment of the forecast (final) cost against the current budget, to ensure that no cost commitments are made on the project without correct approval and budget allocation.

TEAM COORDINATION
Coordination with Document Control, Project Manager, Project Engineer, Discipline Engineer, Client and other related parties.

REPORTING (MS WORD, EXCELL, ADOBE PDF, Power Point)


WEEKLY for Internal AND MONTHLY REPORT for External To prepare the reporting requirements reflect both the client's requirements and internal standard expectations and are formally documented including frequency and delivery dates and also reflect the status of all aspects of project.

The contract provides for the provision of services to PCSB Sabah facilities, and may include the following sites: Site SAMARANG Facility SMP-A, SMP-B,SMP-C, SMR-A,SMDP-A,SMG-A, SMQ-A, SMJT-C SMJT-D SMJT-E SMJT-F, SMJT-G, SMV-A, SMV-AA, SMV-B, SMV-C, SM-4 EWP-A, EWV-AA, EWG-A, EWQ-A, EWV-A, EWDP-B, EWVA KINDP-A TBG-A SUPG-B SBGAST

ERB WEST KINARUT TEMBUNGO SUMANDAK SABAH GAS TERMINAL

SUMMARY OF THE WORK PROGRESS


No Proposal No. PO Approved GBS Project No. Project Title Manhours Budget 1 2 3 4 402028-00745 402029-00002 402029-00003 402029-00004 3600053415 3600060241 3600060231 3600060244 Provision of Detailed Design for Lifeboat Installation at SMQ-A Provision of Installation new Air Compressor at Sabah 402029-00012 Gas Terminal 402029-00001 Provision of Detailed Design for Additional Loading 402029-00013 Bay at Tembungo-A Module 2 (FIP) 402029-00015 Call of technical assistant for PCSB SBO office Detail Design of Sumandak LQ SUPG-B internal renovation. 402029-0009 Detail Design for relocation of PL-140 launching Facilities from SMP-A to SMG-A Detailed Design for Upgrading of the C-620 1st stage discharge volume bottle maximum allowable working pressure to higher working pressure in TBG-A Detailed Engineering Design for Samarang pipeline rehabilitation project (PL-112 Pull Thru Method) 3600060243 402029-00014 Provision of Detailed Design for Lifeboat Installation at SMQ-A Tembungo A & B As-built drawing exercise. 342.0 2,287.0 1,558.0 Actual 613.0 Cost Budget 66,327.10 274,801.06 183,448.96 83,785.79 Productivity progress Plan 100% 2.97% Actual 100% 5.16% Issued Final Site Visit Report, Project to be closed Issued for IFC for Kick Off Meeting on 17/06/11 need check with diiference amount, PCSB approved for RM85,225.79 Cancelled-Received comment from PCSB on 3/05/11 to consider to put this quotation under UDESA in the future Project currently on-going but without PO, PCSB to release PO/RO Issued Proposal rev.0 on 14/06/11, Awaiting PO from PCSB Remark

402029-00005

8,276.0

1,176,606.00

402029-00006

2,308.0

801.5

285,584.99

402029-00007

1,840.0

212,549.00

402029-00008

142.0

104,124.77

Received quotation from Third Party for site visit only on 16/05/11 (RM 73,619.77) 3.91% 2.36% Kick Off Meeting on 16/06/11 Issued Proposal rev.0 for TBG-B on 16/06/11 Proposal stage, waiting input from Engineer for estimate MH Proposal stage, waiting input from Engineer for estimate MH Waiting Work Order from PCSB SBO Waiting Work Order from PCSB SBO Waiting Work Order from PCSB SBO Waiting Work Order from PCSB SBO

402029-00010

2,551.0

328,600.57

10

402029-00011

5,546.0

621,462.50

11

402029-00016

As-Built Drawings Exercise for SBGAST Provision of Installation of New Gas Lift Facility at Tembungo-TBG B Sumandak as-built drafting from red-line mark-ups on SUDP-A Detail Design for the installation of flow meter at Sumandak Detail Design for the relocation of instrument air dryer blocking vessel V-580 manhold at LGAST Tembungo as-built drafting from red-line mark-ups.

12 13 14 15 16

402029-00017

17

Additional fuel gas PCV at Samarang gas generator turbine

Currently PCSB project engineer is carrying out feasibility study to determine if this can proceed to detail design. If it is a simple process, it will only be as-built drafting workWaiting Work Order from PCSB SBO Waiting Work Order from PCSB SBO

18

Detail design of new vessel with higher temperature capability subject to cyclic loading and fluctuating pressure for vessel after the compressor vessel in Tembungo

See the details as attached

BRIEF PROJECT REPORT


KOTA KINABALU DESIGN OFFICE FOR PCSB SBO OPERATIONS 2011 AS OF 20 JUNE 2011

SUMMARY PROGRESS ACHIEVEMENT No


1 2 3 4 5

MANHOURS AND COST REPORT Cumm.Previous Plan Actual


100% 100% 1600

HSE Report Actual Manhours Cost


761.0 318.0 32.5 66,327.10

Project No
402029-00001 402029-00012 402029-00013 402029-00014 402029-00015

Project Title
Site Visit for LifeBoat Installation at SMQ-A Provision of Intallation New Air Compressor at Sabah Gas Provicion of DD for Additional Loading Bay at TBG-A Provision of DD for Lifeboat Inatallation at SMQ-A Technical Asisstant at PCSB

This Week Actual Plan


2.97% 3.91% 5.16% 2.36%

Up to This Week Plan Actual


100% 2.97% 3.91% 100% 5.16% 2.36%

Next Week Plan


7.22% 15.23%
2000

No

Project No
402029-00001 402029-00012 402029-00013 402029-00014 402029-00015 402029-00009

KKDO PCSB SBO- Spending Curve

Budget Manhours Cost


342.0 2,287.0 1,558.0 2,551.0 66,327.10 274,801.06 183,448.96 328,600.57 85,225.79

Balance Manhours Cost


-419.0 1,969.0 -

Onshore 296

Input Offshore

1 2 3 4 5 6

1478
Output

1800

704.5

-704.5

Fatality LTI = Lost Time Injury IWLT = Injury Without Lost Time

1400
1,327.05 1,256.06 1,201.65 Work Request Pending

1200

1000
936.96 Approved Work Request

800

Cummulative Actual Spending(Based on Actual % Progress) Cummulative Work Request (Pending Approval) Cummulative Approved Work Request

First Aid

(Thousands)

Cost

Safety report This Month


No Accident this week

KEY MILESTONE No
1 2 3 4 5

600

Project No
402029-00001 402029-00012 402029-00013 402029-00014 402029-00015

Project Title
Site Visit for LifeBoat Installation at SMQ-A Provision of Intallation New Air Compressor at Sabah Gas Provicion of DD for Additional Loading Bay at TBG-A Provision of DD for Lifeboat Inatallation at SMQ-A Technical Asisstant at PCSB

Plan Date
29-Apr-11 19-Jul-11 05-Aug-11 15-Aug-11

Forecast Date

Actual Date
29-Apr-11

537.21

400

200
0.00 66.33 46.43 66.33 66.33 Actual Spending

TOTAL

6,738.0

938,403.5

1,816.0

66,327.1

1,550.0

HIGHLIGHT ACTION LOG


May'11 Jun'11 Jul'11 Aug'11 Sep'11 Oct'11 Nov'11 Dec'11

Jan'11

Feb'11

Mar'11

Apr'11

Month

No
1 2

Project No.
402029-00001 402029-00009 402029-00009 402029-00009 402029-00009 402029-00009 402029-00009 402029-00009 402029-00009 402029-00009 402029-00012 402029-00012 402029-00012

Document No.
402029-00001-00-PM-REP 4P2001A 4J3501A 4J4501A 4J5801A 4J5901A 4J5401A 4L5101A 4L5101A 4L5501A 4P2001A 4L5101A 4L5501A

Document Title
Site Visit Report for Lifeboat Installation Process PFD/P&ID package for IFA Instrument Schedule List and datasheet for IFC Package Instrument MTO Instrument signal Diagram Instreument support and Details Instrument Cellar deck Layout Document /drawing list Piping plan 8" HHP Gas HDR BI directional P&ID Piping Plan and MTO Tie in Schedule

Due Date
20/06/2011 6/06/2011 6/06/2011 6/06/2011 6/06/2011 6/06/2011 6/06/2011 6/06/2011 6/06/2011 6/06/2011 1/07/2011 1/07/2011 1/07/2011

Action by
PRW PCSB PCSB PCSB PCSB PCSB PCSB PCSB PCSB PCSB PCSB PCSB PCSB

Remark
Closed Open Open Open Open Open Open Open Open Open Open Open Open

KKDO PCSB-SBO MANHOURS HISTOGRAM


9,000

3 4 5 6 7 8 9 10 11 12 13

8,000

7,000

6,000

5,000

Mhrs
Project Title Manhours Budget Actual 613.0 Cost Budget 66,327.10 274,801.06 183,448.96 83,785.79 Productivity progress Plan 100% 2.97% Actual 100% 5.16% Issued Final Site Visit Report, Project to be closed Issued for IFC for Remark 342.0 2,287.0 1,558.0

4,000

LIST OF PROJECT STATUS


No Proposal No. PO Approved GBS Project No.

3,000

2,000

1 2 3 4

402028-00745 402029-00002 402029-00003 402029-00004

3600053415 3600060241 3600060231 3600060244

402029-00001

Provision of Detailed Design for Lifeboat Installation at SMQ-A Provision of Installation new Air Compressor at Sabah 402029-00012 Gas Terminal Provision of Detailed Design for Additional Loading 402029-00013 Bay at Tembungo-A Module 2 (FIP)

1,000

Kick Off Meeting on 17/06/11 need check with diiference amount, PCSB approved for RM85,225.79 Cancelled-Received comment from PCSB on 3/05/11 to consider to put this quotation under UDESA in the future Project currently on-going but without PO, PCSB to release PO/RO Issued Proposal rev.0 on 14/06/11, Awaiting PO from PCSB

Mar-11

Apr-11

May-11

Jun-11

Jul-11

Aug-11

Sep-11

402029-00015 Call of technical assistant for PCSB SBO office Detail Design of Sumandak LQ SUPG-B internal renovation. 402029-0009 Detail Design for relocation of PL-140 launching Facilities from SMP-A to SMG-A Detailed Design for Upgrading of the C-620 1st stage discharge volume bottle maximum allowable working pressure to higher working pressure in TBG-A Detailed Engineering Design for Samarang pipeline rehabilitation project (PL-112 Pull Thru Method)

Project Management

Process & Safety

Mech/Piping

Period

Instrument

Electrical

Structural

Availability

CHANGE ORDER STATUS No Project No PCR No. Original Budget Cost Manhours Current Budget Manhours Cost Approval Status Concract PCR No. Remark

402029-00005

8,276.0

1,176,606.00

Availability = Total normal working hours per month (160 man-hours per months) - Holiday - Entitled Annual Leave (20days per year) - Entitle Sick Leave (14days per year) - 20% OT

1 2 3 4 5

402029-00006

2,308.0

801.5

285,584.99

402029-00007

1,840.0

212,549.00

402029-00008

142.0

104,124.77

Received quotation from Third Party for site visit only on 16/05/11 (RM 73,619.77) 3.91% 2.36% Kick Off Meeting on 16/06/11 Issued Proposal rev.0 for TBG-B on 16/06/11 Proposal stage, waiting input from Engineer for estimate MH Proposal stage, waiting input from Engineer for estimate MH Waiting Work Order from PCSB SBO Waiting Work Order from PCSB SBO Waiting Work Order from PCSB SBO Waiting Work Order from PCSB SBO

402029-00010

3600060243

402029-00014

Provision of Detailed Design for Lifeboat Installation at SMQ-A Tembungo A & B As-built drawing exercise.

2,551.0

328,600.57

INVOICE SUMMARY No
1 2 3 4 5

Project No.

Date award

PO Value

Invoice to date

Invoice No.

Date Paid

Balance Invoice

Remark

10

402029-00011

5,546.0

621,462.50

11

402029-00016

As-Built Drawings Exercise for SBGAST Provision of Installation of New Gas Lift Facility at Tembungo-TBG B Sumandak as-built drafting from red-line mark-ups on SUDP-A Detail Design for the installation of flow meter at Sumandak Detail Design for the relocation of instrument air dryer blocking vessel V-580 manhold at LGAST Tembungo as-built drafting from red-line mark-ups.

12 13 14 15 16

402029-00017

CLOSE OUT SUMMARY No


1 2 3 4 5

Project No.

Project Title

PO No

COC Request Date

COC Received Date

Performance Received Date

Remark

17

Additional fuel gas PCV at Samarang gas generator turbine

Currently PCSB project engineer is carrying out feasibility study to determine if this can proceed to detail design. If it is a simple process, it will only be as-built drafting workWaiting Work Order from PCSB SBO Waiting Work Order from PCSB SBO

18

Detail design of new vessel with higher temperature capability subject to cyclic loading and fluctuating pressure for vessel after the compressor vessel in Tembungo

KKDO PROJECT ENGINEERING SERVICE ACTION LOG


As Of June 2011

No.

Project No

CTR ID

Discipline

Document No.

Deliverable/Activity Description

Rev

Doc Type

Issue Date

Due Date

Actual date Client Comment

Status

Action Party

Action to Issue

Remark

402029-0001 4Z0001A 4Z0001A 402029-00001-00-PR-REP-00001 Site Visit Report for Lifeboat Installation at SMQ-A B REP 18-Apr-11 Closed PRW Final

II

402029-00009 SMP-A 4P2001A 4P2001A 4P2001A 4P2001A 4P2001A 4P2001A 4P2001A 4P2001A SMG-A 4P2001A 4P2001A 4P2001A 4P2001A 4P2001A 4P2001A 4P2001A 4P2001A 4P2001A Process Process Process Process Process Process Process Process Process SMG-A P-0001A SMG-A P-0019 (R) SMG-A P-0019 SMG-A P-0034 (R) SMG-A P-0034 SMG-A P-0019 (R) SMG-A P-0019 SMG-A P-0034 (R) SMG-A P-0034 SYMBOLS, LEGEND & ABBREVIATIONS LP RECEIVER AND SEPARATOR LP RECEIVER AND SEPARATOR VENT STACK AND SCRUBBER VENT STACK AND SCRUBBER LP RECEIVER AND SEPARATOR LP RECEIVER AND SEPARATOR VENT STACK AND SCRUBBER VENT STACK AND SCRUBBER A3/0 H4/0 H4/0 H2/0 H2/0 H5/0 H5/0 H3/0 H3/0 PID PID PID PID PID PID PID PID PID 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 IFA IFA IFA IFA IFA IFA IFA IFA IFA PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO Process Process Process Process Process Process Process Process Process 402029-00009-00-PR-LS-0001 SMP-A P-0002 (R) SMP-A P-0002 SMP-A P-0007 (R) SMP-A P-0007 SMP-A P-0009 (R) SMP-A P-0009 SMP-A P-0009 (R) SMP-A P-0009 DRAWING LIST SAMARANG FIELD PFD SMP-A SAMARANG FIELD PFD SMP-A LAUNCHER M-1001 & LAUNCHER/RECEIVER M-1002 LAUNCHER M-1001 & LAUNCHER/RECEIVER M-1002 DRAIN SYSTEM DRAIN SYSTEM VENT SYSTEM VENT SYSTEM A A6/0 A6/0 M6/0 M6/0 J5/0 J5/0 J5/0 J5/0 LS PFD PFD PID PID PID PID PID PID 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 IFA IFA IFA IFA IFA IFA IFA IFA IFA PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO

4J4001A 4J3501A 4J3501A 4J4501A 4J5801A 4J5801A 4J5801A 4J5801A 4J5901A 4J5901A 4J5901A 4J5901A

Instrument Instrument Instrument Instrument Instrument Instrument Instrument Instrument Instrument Instrument Instrument Instrument Instrument Instrument Instrument Instrument

402029-00009-00-IC-IDX-0001 402029-00009-00-IC-DAS-0001 402029-00009-00-IC-DAS-0002 402029-00009-00-IC-MTO-0001 I-2503 I-2503 I-2503 I-2503 I-3210 I-3210 I-3210 I-3210

DOCUMENT/DRAWING LIST DATA SHEET OF PRESSURE GAUGES DATA SHEET OF PIG SIGNALLER INSTRUMENT MTO INSTRUMENT SIGNAL DIAGRAM INSTRUMENT SIGNAL DIAGRAM INSTRUMENT SIGNAL DIAGRAM INSTRUMENT SIGNAL DIAGRAM COVER SHEET INDEX OF SHEETS SUMMARY OF MATERIALS ADDITIONAL FUSIBLE PLUG FOR M-1002

A A A A 0 0 0 0 0 0 0 0 E2/0 E2/0

IDX DAS DAS MTO DHU DHU DHU DHU DID DID DID DID DBD DAL

23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11

6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11

IFC IFC IFC IFC IFC IFC IFC IFC IFC IFC IFC IFC IFC IFC

PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO

INSTRUMENT SUPPORT AND INSTALLATION DETAILS - COVER SHEET INSTRUMENT SUPPORT AND INSTALLATION DETAILS - INDEX OF SHEET INSTRUMENT SUPPORT AND INSTALLATION DETAILS - SUMMARY OF MATERIALS INSTRUMENT SUPPORT AND INSTALLATION DETAILS - TYPICAL TUBING TRAY SUPPORT DIAGRAM FOR FUSIBLE PLUG TUBING (DELUGE SYSTEM) CELLAR DECK LAYOUT OF FUSIBLE TUBING (ROUTE PLAN, DELUGE SYSTEM)

4J5801A 4J5401A SMG-A 4L5101A 4L8510A 4L5101A 4L5101A 4L5101A 4L5101A 4L5101A

I-0816 I-0805

Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping

402029-00009-ME-LS-0001 402029-00009-ME-MTO-0001 P-0106 ( R ) P-0106 P-0110 ( R ) P-0110 P-0116

DOCUMENT/DRAWING LIST BULK MATERIAL TAKE OFF PIPING PLAN - BELOW UPPER DECK FLOOR AREA BU-1B PIPING PLAN - BELOW UPPER DECK FLOOR AREA BU-1B PIPING PLAN - BELOW UPPER DECK FLOOR AREA BU-3B PIPING PLAN - BELOW UPPER DECK FLOOR AREA BU-3B PIPING PLAN - ABOVE CELLAR DECK FLOOR AREA C-3B

B B F1/0 F1/0 H3/0 H3/0 F3/0

LST MTO DA DA DA DA DA

23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11

6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11

IFC IFC IFC IFC IFC IFC IFC

PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO

Page 1/2

KKDO PROJECT ENGINEERING SERVICE ACTION LOG


As Of June 2011

No.

Project No

CTR ID
4L5101A 4L5101A 4L5101A 4L5101A 4L5101A 4L5501A 4L5501A 4L5501A 4L5501A 4L5501A 4L5501A 4L5501A SMP-A 4L5101A 4L5101A 4L5101A 4L5101A 4L5101A 4L5501A 4L5501A

Discipline
Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping

Document No.
P-0121 ( R ) P-0121 P-0301 P-0315 P-0257 P-0258 P-0258 P-0258 ( R ) P-0258 P-0215( R ) P-0215 SMG-PL-402-280

Deliverable/Activity Description
PIPING PLAN - BELOW CELLAR DECK FLOOR AREA BC-3A PIPING PLAN - BELOW CELLAR DECK FLOOR AREA BC-3A EQUIPMENT LAYOUT - CELLAR DECK SAFETY EQUIPMENT & ESCAPE ROUTE - CELLAR DECK TIE-IN SCHEDULE 200-60-PG-1207 200-60-PG-1207 50-PD-2044-11430 50-PD-2044-11430 10-15-VL-2400-R1 10-15-VL-2400-R1 8-SPILL OVER-0017-T1

Rev
F3/0 F3/0 F2/0 A2/0 0 0 0 0 0 0 0 F1/0

Doc Type
DA DA DA DA LST ISO ISO ISO ISO ISO ISO ISO

Issue Date
23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11

Due Date
6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11

Actual date Client Comment

Status
IFC IFC IFC IFC IFC IFC IFC IFC IFC IFC IFC IFC

Action Party
PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO

Action to Issue

Remark

Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping

P-0105 ( R ) P-0105 P-0310 P-0311 P-0242 P-0731 ( R ) P-0731

PIPING PLAN - ABOVE SCRAPPER DECK AND PIPING SECTIONS PIPING PLAN - ABOVE SCRAPPER DECK AND PIPING SECTIONS EQUIPMENT LAYOUT - MAIN DECK, SCRAPPER DECK & SUMP DECK

B2/0 B2/0 C5/0

DA DA DA DA LST ISO ISO

23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11 23-May-11

6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11 6-Jun-11

IFC IFC IFC IFC IFC IFC IFC

PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO

SAFETY EQUIPMENT LAYOUT & ESCAPE ROUTES MAIN DECK, SCRAPPER DECK C5/0 & SUMP DECK TIE-IN SCHEDULE 8" HHP GAS HDR (6103X) BI DIRECTIONAL 8" HHP GAS HDR (61430) BI DIRECTIONAL 0 A1/0 A1/0

III

402029-00012 4P2001A 4P2001A 4P2001A 4L5101A 4L4501A 4L5101A 4L5101A 4L5101A 4L5101A 4L5101A 4L5501A 4L5501A 4L5501A 4L5501A Process Process Process Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping Mechanical/Piping 402029-00012-00-PR-LS-0001 SBGAST P-0076 SBGAST P-0076(R) 402029-00012-ME-LS-0001 402029-00012-ME-MTO-0001 P-0114-B(R) P-0114-B P-0114-E(R) P-0114-E P-0203 P-UA54005-1(R) P-UA54005-1 P-UA54006-1(R) P-UA54006-1 DRAWING LIST INSTRUMENT AND UTILITY AIR SYSTEM INSTRUMENT AND UTILITY AIR SYSTEM DOCUMENT/DRAWING LIST BULK MATERIAL TAKE OFF PIPING PLAN - AREA B3B PIPING PLAN - AREA B3B PIPING PLAN - UTILITY AND INSTRUMENT AIR RECEIVER AREA - B3E PIPING PLAN - UTILITY AND INSTRUMENT AIR RECEIVER AREA - B3E TIE-IN SCHEDULE 50-UA54005-11020 50-UA54005-11020 50-UA54006-11020 50-UA54006-11020 B 1A1 1A1 A A A1 A1 A1 A1 0 A1 A1 A1 A1 LS PID PID LST MTO DA DA DA DA LST ISO ISO ISO ISO 17-Jun-11 17-Jun-11 17-Jun-11 17-Jun-11 17-Jun-11 17-Jun-11 17-Jun-11 17-Jun-11 17-Jun-11 17-Jun-11 17-Jun-11 17-Jun-11 17-Jun-11 17-Jun-11 1-Jul-11 1-Jul-11 1-Jul-11 1-Jul-11 1-Jul-11 1-Jul-11 1-Jul-11 1-Jul-11 1-Jul-11 1-Jul-11 1-Jul-11 1-Jul-11 1-Jul-11 1-Jul-11 IFC IFC IFC IFC IFC IFC IFC IFC IFC IFC IFC IFC IFC IFC PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO PCSB-SBO

Legend :

Due Date with red color is behind schedule Due Date with blue color is on progress

Page 2/2

Proposal Tracking
Project Client Title Period End PROJECT NUMBER : MDO Project : Petronas Carigali Sdn Bhd-Sabah Operations (PCSB-SBO) : Maintenance ENG SERVICES : 14-June-2011 PE PRW PCSB SBO DATE REC'D Work Order CLARIFICATIONS COMPLETE 0 01 402028-00745 Provision of Detail Design of SMQ-A Lifeboat Installation Danilo R Villanueva M Afni hamudi B Fauzi 10-Feb-11 14-Feb-11 02 03 04 0 01 Provision of Installation new Air Compressor at Sabah Gas Terminal Danilo R Villanueva 02 Imelda Isti Hartini 28-Mar-11 04-Apr-11 03 04 05 0 12-May-11 18-May-11 18-May-11 01-Apr-11 12-May-11 18-May-11 18-May-11 NS 12-May-11 18-May-11 18-May-11 28-Mar-11 12-May-11 18-May-11 18-May-11 NS 12-May-11 18-May-11 18-May-11 NS 12-May-11 18-May-11 18-May-11 NS 12-May-11 18-May-11 18-May-11 01-Apr-11 12-May-11 18-May-11 18-May-11 04-Apr-11 12-May-11 18-May-11 18-May-11 04-Apr-11 2,305.0 2,287.0 2,287.0 1,614.0 283,239.02 279,086.86 274,801.06 205,440.00 08-Jun-11 Comment Client on 16/05/11 Comment Client on 16/05/11 Received PO No.3600060241 with GBS new Project No.40202900012 Comment client on 17/04/11 23-Feb-11 08-Mar-11 13-Mar-11 16-Mar-11 01-Apr-11 19-Apr-11 06-May-11 Instrument 14-Feb-11 23-Feb-11 08-Mar-11 13-Mar-11 16-Mar-11 31-Mar-11 19-Apr-11 06-May-11 ENGINEERING INPUT REC'D Structural 14-Feb-11 23-Feb-11 08-Mar-11 13-Mar-11 16-Mar-11 31-Mar-11 19-Apr-11 06-May-11 Electrical 14-Feb-11 23-Feb-11 08-Mar-11 13-Mar-11 16-Mar-11 30-Mar-11 19-Apr-11 06-May-11 Mech/Piping 14-Feb-11 23-Feb-11 08-Mar-11 13-Mar-11 16-Mar-11 30-Mar-11 19-Apr-11 06-May-11 Process 14-Feb-11 23-Feb-11 08-Mar-11 13-Mar-11 16-Mar-11 30-Mar-11 19-Apr-11 06-May-11 PROJ SVCS SUMMARY 14-Feb-11 24-Feb-11 09-Mar-11 14-Mar-11 17-Mar-11 02-Apr-11 19-Apr-11 06-May-11 EM APPROVAL 14-Feb-11 24-Feb-11 09-Mar-11 14-Mar-11 17-Mar-11 04-Apr-11 19-Apr-11 06-May-11 SENT TO PCSB SBO 14-Feb-11 24-Feb-11 09-Mar-11 14-Mar-11 17-Mar-11 04-Apr-11 19-Apr-11 06-May-11 3,588.0 2,343.0 2,407.0 2,305.0 509,063.22 331,771.00 339,032.00 299,765.00 25-Mar-11 DATE P.O. REC'D
Comment from PCSB SBO to use Proposal rate for MDO as per signed by PRW Comment from PCSB SBO to use personnel as per Organization Chart approved Comment from PCSB SBO to reduce Hours and Cost and need to go site surveys before 21st March 2011 Comment from PCSB SBO to reduce hours site visit and management and NonLabour Cost

PROJECT TITLE

DATE REQ'D

Rev

MHRS

COST

REMARKS

Received PO No: 3600053415 for Site Visit and Drawing search only with MH:342 and Cost RM66,327.10 Project Number ; 402029-00001 Comment Client on 19/04/11 Comment Client on 27/04/11 Comment Client on 11/05/11

402029-00002

01 402029-00003 Provision of Detailed Design for Additional Loading Bay at Tembungo-A Module 2 (FIP) Danilo R Villanueva W Hariz Fadli B W Shafie 28-Mar-11 04-Apr-11 02

18-Apr-11

NS

18-Apr-11

NS

NS

NS

18-Apr-11

18-Apr-11

18-Apr-11

1,548.0

189,916.00

Comment client on 29/04/11 comment client on 11/05/11 to take out the tax (rates already include tax as per contract) 08-Jun-11 Received PO No.3600060231with GBS new Project No.40202900013 Received comment from PCSB on 29/04/11 to revise duration of service for 2 years (currently duration of service 1 year first (June11 May12)). Received comment on 9/05/11 08-Jun-11 Received PO No.3600060244 with GBS new Project No.40202900015 Cancelled-Received comment from PCSB on 3/05/11 to consider to put this quotation under UDESA in the future Received client comment on 14/04/11 and to additional Instrument scope Received client comment on 29/04/11 to reduce manhours

04-May-11

NS

04-May-11

NS

NS

NS

04-May-11

04-May-11

04-May-11

1,528.0

185,941.00

03

12-May-11

NS

12-May-11

NS

NS

NS

12-May-11

12-May-11

12-May-11

1,558.0

183,448.96

0 402029-00004 Call of technical assistant for PCSB SBO office (Marchaya Bt Sarif) Danilo R Villanueva Sri Lisaharnie bt Mustapa 01-Apr-11 12-Apr-11 01 02 402029-00005 Detail Design of Sumandak LQ SUPG-B internal renovation. Danilo R Villanueva Jason Lee Kee Foo 04-Apr-11 12-Apr-11 0 0 402029-00006 (Project No GBS 402029-00009) Detail Design for relocation of PL-140 launching Facilities from SMP-A to SMG-A Danilo R Villanueva

04-Apr-11

NS

NS

NS

NS

NS

21-Apr-11

21-Apr-11

21-Apr-11

1,960.0

144,737.00

06-May-11 10-May-11 07-Apr-11 08-Apr-11

NS NS 07-Apr-11 11-Apr-11

NS NS 07-Apr-11 11-Apr-11

NS NS 07-Apr-11 11-Apr-11

NS NS 09-Apr-11 11-Apr-11

NS NS 09-Apr-11 11-Apr-11

06-May-11 10-May-11 21-Apr-11 12-Apr-11

06-May-11 10-May-11 21-Apr-11 12-Apr-11

06-May-11 10-May-11 21-Apr-11 12-Apr-11

3,920.0

293,056.00 83,785.79

8,276.0 2,171.0

1,176,606.00 279,118.00

Syamaizar B Wahed

07-Apr-11

12-Apr-11

01

15-Apr-11

15-Apr-11

15-Apr-11

15-Apr-11

15-Apr-11

15-Apr-11

15-Apr-11

15-Apr-11

15-Apr-11

2,389.0

307,878.00

02 Detailed Design for Upgrading of the C-620 1st stage discharge volume bottle maximum allowable working pressure to higher working pressure in TBG-A Detailed Engineering Design for Samarang pipeline rehabilitation project (PL-112 Pull Thru Method) Provision of Detail Design of SMQ-A Lifeboat Installation Danilo R Villanueva Danilo R Villanueva Danilo R Villanueva Danilo R Villanueva Danilo R Villanueva Danilo R Villanueva

04-May-11

04-May-11

04-May-11

04-May-11

04-May-11

04-May-11

11-May-11

11-May-11

11-May-11

2,308.0

285,584.99

Awaiting PO from PCSB

402029-00007 402029-00008

Martin Huan Syamaizar B Wahed

29-Apr-11 06-Apr-11

09-May-11 15-Apr-11

0 0 0

16-May-11 17-May-11 05-May-11 12-May-11 16-Jun-11

NS 17-May-11 05-May-11 12-May-11 27-May-11

16-May-11 17-May-11 05-May-11 12-May-11 27-May-11

NS 17-May-11 05-May-11 12-May-11 27-May-11

16-May-11 17-May-11 05-May-11 12-May-11 27-May-11

NS 17-May-11 05-May-11 12-May-11 27-May-11

14-Jun-11 17-May-11 05-May-11 12-May-11 12-Jun-11

14-Jun-11 17-May-11 05-May-11 12-May-11 16-Jun-11

14-Jun-11 17-May-11 05-May-11 12-May-11 16-Jun-11

1,840.0 142.0 2,551.0 2,551.0 5,546.0

212,549.00 104,124.77 349,459.63 328,600.57 621,462.50 08-Jun-11

Awaiting PO from PCSB Received quotation from Third Party for site visit only on 16/05/11 (RM 73,619.77) comment client on 11/05/11 to take out the tax (rates already include tax as per contract) Received PO No.3600060243 with GBS new Project No.40202900014 Awaiting PO from PCSB Proposal stage

402029-00010

Martin Huan

10-Feb-11

14-Feb-11 01

402029-00011 402029-00016 402029-00017

Tembungo A & B As-built drawing exercise. As-Built Drawings Exercise for SBGAST Provision of Installation of New Gas Lift Facility at TembungoTBG B Sumandak as-built drafting from red-line mark-ups on SUDPA Detail Design for the installation of flow meter at Sumandak Detail Design for the relocation of instrument air dryer blocking vessel V-580 manhold at LGAST

Imelda Isti Hartini Imelda Isti Hartini Mohd Hasrol Ramli

11-May-11 15-Jun-11 17-Jun-11

23-May-11

20-May-11

Proposal stage Waiting Work Order from PCSB SBO Waiting Work Order from PCSB SBO Waiting Work Order from PCSB SBO Currently PCSB project engineer is carrying out feasibility study to determine if this can proceed to detail design. If it is a simple process, it will only be as-built drafting work-Waiting Work Order from PCSB SBO Waiting Work Order from PCSB SBO

Additional fuel gas PCV at Samarang gas generator turbine

Detail design of new vessel with higher temperature capability subject to cyclic loading and fluctuating pressure for vessel after the compressor vessel in Tembungo PO Approved PO projected 6,738.0 9,836.0 936,963.48 1,223,721.26

NS

= No Scope

20/06/2011 KK Office Proposal Tracking

PROJECT No.402029-00001

402029-00001 - Site Visit For Lifeboat Installation At SMQ-A


Manhours CTR ID.

CTR Activity

Budget

Actual

Balance

COST, TIME AND RESOURCE CATALOGUE 4Z0001A 0002 MAN 4Z0002A 4Z0002A 4Z0002A 4Z0002A

PROJECT MANAGEMENT SITE VISIT & DOCUMENT SEARCH Drawings / Document Search Site visit Site visit Reports Quality Assurance/ Design Review 46.0 164.0 93.0 39.0 342.0

57.0

-57.0 Overun 0.0

40.0 284.0 380.0

6.0 -120.0 Overun -287.0 Overun 39.0

SUB-TOTAL - SITE VISIT AND DOCUMENT SEARCH

704.0

-362.0 Overun

TOTAL MANHOURS

342.00

761.0

-419.0 Overun

PROJECT No.402029-00009

402029-00009 - Provision of DD for relocation of PL-140 launching facilities from SMP-A to SMG-A
Manhours CTR NO.

CTR Activity

Budget

Actual

Balance

COST, TIME AND RESOURCE CATALOGUE

0001 MAN 4Z0001A 4Z0001A 4Z0001A 4Z0001A 4Z0001A 0002 MAN 4Z0002A 4Z0002A 4Z0002A 4Z0002A 0004 MAN 4Z0001A 0001 DES 4P2001A 4P4001A

PROJECT MANAGEMENT Project Management Kick Off Meeting Design Review Interface Meeting Review Conceptual Studies 61.5 26.0 172.0 61.5

SUB-TOTAL - PROJECT MANAGEMENT SITE VISIT & DOCUMENT SEARCH Drawings / Document Search Site visit Site visit Reports Quality Assurance/ Design Review

SUB-TOTAL - SITE VISIT AND DOCUMENT SEARCH PROJECT CLOSE OUT REPORT Project Close Out Report

198.0

SUB-TOTAL - PROJECT CLOSE OUT REPORT PROCESS ENGINEERING Studies and P&ID mark up Schedules and Lists/Hazardous area cert/Dem.dwg

41.0 16.0

SUB-TOTAL - B. PROCESS 0002 DES 4L2001A 4L3001A 4L4001A 4L4501A 4L5001A 4L5101A 4L5501A 4L5601A 4L8501A MECHANICAL/PIPING ENGINEERING Studies Calculations Schedules and Lists MTO's PFD/P&ID Drafting Plot Plans & Site Layouts Isometrics Pipe Support Construction Support (Scope of Work)

57.0

56.0

184.0

SUB-TOTAL - C. MECHANICAL 0003 DES 4J2001A 4J2501A 4J3501A 4J4001A 4J4501A 4J5401A 4J5701A 4J5801A 4J5901A INSTRUMENT ENGINEERING Studies PFD/P&ID Mark-up Maintenance Specification & Data Sheets Schedules and Lists MTO's Drawings - Arrangement And Details Demolition Drawings Schematic & Connection diagram Installation Details

240.0

44.0 3.0

37.0

SUB-TOTAL - D. INSTRUMENT 0005 DES 4S3001A 4S5401A STRUCTURAL ENGINEERING Calculations & MTO Drawings - Arrangement And Details

84.0

64.0 64.0 -

SUB-TOTAL - F. CIVIL/STRUCTURAL 0006 DES 4R8001A 4R8001A SUB-TOTAL - HAZOP SAFETY-HAZID HAZID-KL HAZID Workshop

TOTAL MANHOURS

704.5

PROJECT No.402029-00012

402029-00012 Provision of Installation New Air Compressor at Sabah Gas Terminal CTR Activity
Manhours Budget Actual Balance

CTR NO.

COST, TIME AND RESOURCE CATALOGUE

0001 MAN 4Z0001A 0002 MAN 4Z0002A 4Z0002A 4Z0002A 0001 DES 4P2001A 4P2501A 4P4001A 4P5701A

PROJECT MANAGEMENT Project Management 562.0 562.0 20.0 96.0 40.0 156.0 75.0 16.0 16.0 9.0 9.0 25.0 25.0 125.0 46.0 46.0 16.0 16.0 100.0 100.0 60.0 30.0 30.0 252.0 86.0 166.0 86.0 -26.0 47.0 78.0 60.0 47.0 28.0 60.0 96.0 96.0 466.0 466.0

SUB-TOTAL - PROJECT MANAGEMENT SITE VISIT & DOCUMENT SEARCH Drawings / Document Search Site visit Site visit Reports

20.0 36.0 40.0 96.0

SUB-TOTAL - SITE VISIT AND DOCUMENT SEARCH PROCESS ENGINEERING Studies / Calculation PFD/P&ID Mark-up Maintenance Schedules and Lists Demolition Drawings/Hazard. Area Cert/C&E Matrix

SUB-TOTAL - B. PROCESS 0002 DES 4L2501A 4L4501A 4L5101A 4L5501A 4L8501A MECHANICAL/PIPING ENGINEERING PFD/P&ID Drafting MTO's Plot Plans & Site Layouts Isometrics Scope of Work

SUB-TOTAL - C. MECHANICAL 0003 DES 4J4001A 4J4501A 4J5401A 4J5701A 4J5801A 4J5901A INSTRUMENT ENGINEERING Schedules and Lists MTO's Drawings - Arrangement And Details Demolition Drawings Schematic & Connection diagram Installation Details

15.0 15.0 15.0 15.0 37.0 37.0 44.0 44.0 26.0 26.0 41.0 41.0 178.0 178.0

SUB-TOTAL - D. INSTRUMENT 0004 DES 4E3001A 4E3501A 4E4501A 4E5101A 4E5401A 4E5701A 4E5801A 4E5901A ELECTRICAL ENGINEERING Calculations, Schedule & Lists Specification & Data Sheets MTO's Plot Plans & Site Layouts Drawings - Arrangement And Details Demolition Drawings Schematic & Connection Diagram Installation Details and Scope of Work

92.0 48.0

4.0 88.0 48.0

44.0 44.0 124.0 124.0 48.0 48.0 50.0 50.0 164.0 164.0 36.0 36.0 606.0 4.0 602.0

SUB-TOTAL - E. ELECTRICAL 0005 DES 4S3001A 4S5401A STRUCTURAL ENGINEERING Calculations Drawings - Arrangement And Details

100.0 100.0 308.0 408.0 25.0 283.0 25.0 383.0

SUB-TOTAL - F. CIVIL/STRUCTURAL

TOTAL MANHOURS

2,287.0

318.0

1,969.0

MASTER DELIVERABLES REGISTER : Provision of Installation New Air Compressor at Sabah Gas Terminal
Rev No. CTR No. Document No. Description Commencement of activity Start - (10%) Plan Actual Inter Discipline Check (IDC - 50%) Plan Actual Issued for Comment (IFC - 70%) Plan Actual Issued for Approval (IFA - 90%) Plan Actual

Project No. Contract No. Period End Issued for AFC (100%) Plan Actual

402029-00012 SBO/2009/SRE/056
10-Jun-11

TPC to issue

Progress (%) Actual Last This 0.80% 0.80% Actual To date 0.80% 0.80% 100.00% Plan To date 10.72% 10.72% 10.00% 100.00% 10.00% 2.42% 10.00%
Remarks

1. GENERAL 1 Project Management 4Z0001A 4Z0001A 4Z0001A

4Z0001A 4Z0001A 4Z0001A

General Coordination and Monitoring Project Project Schedule Baseline Monthly Report

0 0 0

8-Jun-11 9-Jun-11 8-Jun-11

9-Jun-11

22-Jun-11 9-Jun-11 22-Jun-11

6-Jul-11 10-Jun-11 6-Jul-11

20-Jul-11 10-Jun-11 20-Jul-11

4-Aug-11 10-Jun-11 4-Aug-11

9-Jun-11

100.00%

2. PROCESS 0 General Coordination and Site Visit 4P0001A 4P0001A-001 Coordination, Monitoring Progress, and Meetings with client, and etc 0 8-Jun-11 22-Jun-11 6-Jul-11 20-Jul-11 4-Aug-11

10.00%

Studies and Calculations 4P2001A 4P2001A-0001 Line sizing calculation for compressor skid to main air header 0 15-Jun-11 17-Jun-11 24-Jun-11 1-Jul-11 8-Jul-11

PFD/P&ID Mark-up Maintenance 4P2501A 4P2501A-001 Prepare P&ID for Air Tie-ins (estimate 2 off) 0 17-Jun-11 18-Jun-11 24-Jun-11 1-Jul-11 8-Jul-11

Schedule and List 4P4001A

4P4001A-001

Line schedule update

23-Jun-11

24-Jun-11

28-Jun-11

3-Jul-11

8-Jul-11

Demolitions Drawings/Hazard Area Certif/C&E Matrix 4P5701A 4P5701A-001 Prepare demolition drawing for existing Air Compressor P&ID and C&E 0 23-Jun-11 24-Jun-11 28-Jun-11 3-Jul-11 8-Jul-11

1. MCHANICAL PIPING 0 General Coordination and Site Visit 4L0001A 4L0001A 4L0001A 4L0001A 1 PFD/P&ID Drafting 4L2501A MTO's 4L4501A Plot Plan and Site Layout 4L5101A 4L5101A 4L5101A Isometrics 4L5501A Scope Of Work 4L8501A 4L0001A-001 4L0001A-002 4L0001A-004 4L0001A-005 Coordination, Monitoring Progress, and Meetings with client, and etc Drawing search and Data Gathering Site Visit Site Visit report 0 0 0 0 8-Jun-11 9-Jun-11 15-Jun-11 22-Jun-11 9-Jun-11 15-Jun-11 22-Jun-11 10-Jun-11 17-Jun-11 23-Jun-11 9-Jun-11 15-Jun-11 6-Jul-11 11-Jun-11 18-Jun-11 24-Jun-11 9-Jun-11 15-Jun-11 20-Jul-11 13-Jun-11 20-Jun-11 26-Jun-11 9-Jun-11 15-Jun-11 4-Aug-11 14-Jun-11 21-Jun-11 27-Jun-11 9-Jun-11 15-Jun-11

13.41% 57.89%

13.41% 57.89%

3.78% 16.32% 10.00%

100.00% 100.00%

100.00% 100.00%

50.00%

4L2501A-001

Asisst process UFD/P&ID drafting

21-Jun-11

22-Jun-11

27-Jun-11

3-Jul-11

8-Jul-11

4L4501A-001

Material Take Off List (MTO's)

1-Jul-11

2-Jul-11

7-Jul-11

13-Jul-11

18-Jul-11

4L5101A-001 4L5101A-002 4L5101A-003

Equipment Layout Hazardous Layout Piping Plan and Section

0 0 0

22-Jun-11 22-Jun-11 22-Jun-11

27-Jun-11 27-Jun-11 27-Jun-11

4-Jul-11 4-Jul-11 4-Jul-11

11-Jul-11 11-Jul-11 11-Jul-11

18-Jul-11 18-Jul-11 18-Jul-11

4L5501A-001

Isometrics

27-Jun-11

29-Jun-11

5-Jul-11

11-Jul-11

18-Jul-11

4L8501A-001

Scope of Work

27-Jun-11

29-Jun-11

5-Jul-11

11-Jul-11

18-Jul-11

C:\Documents and Settings\bibin.krissandi\My Documents\Bibin\Work\Project\12.402029-00012\402029-00012-Master Deliverable Register

Page 1 of 3

MASTER DELIVERABLES REGISTER : Provision of Installation New Air Compressor at Sabah Gas Terminal
Rev No. CTR No. Document No. Description Commencement of activity Start - (10%) Plan Actual Inter Discipline Check (IDC - 50%) Plan Actual Issued for Comment (IFC - 70%) Plan Actual Issued for Approval (IFA - 90%) Plan Actual

Project No. Contract No. Period End Issued for AFC (100%) Plan Actual

402029-00012 SBO/2009/SRE/056
10-Jun-11

TPC to issue

Progress (%) Actual Last This 9.02% 27.27% Actual To date 9.02% 27.27% Plan To date 2.03% 6.14% 10.00%
Remarks

4. Instrument 0 General Coordination and Site Visit 4J0001A 4J0001A 4J0001A 2 Schedule and Lists 4J4001A 4J4001A MTO's 4J4501A Drawings - Arrangement Details 4J5401A 4J5401A 4J5401A 4J5401A Demolition Drawing 4J5701A 4J5701A 4J5701A Schematic and Connection Diagram 4J5801A 4J5801A 4J5801A Installation Details 4J5901A 4J5901A 4J0001A-001 4J0001A-002 4J0001A-003 Coordination, Monitoring Progress, and Meetings with client, and etc Site Visit Site Visit report 0 0 0 8-Jun-11 15-Jun-11 22-Jun-11 15-Jun-11 22-Jun-11 17-Jun-11 23-Jun-11 15-Jun-11 6-Jul-11 18-Jun-11 24-Jun-11 15-Jun-11 20-Jul-11 20-Jun-11 26-Jun-11 15-Jun-11 4-Aug-11 21-Jun-11 27-Jun-11 15-Jun-11

100.00%

100.00%

4J4001A-001 4J4001A-002

Instrument Schedule/IO List Instrument Cable Specification

0 0

1-Jul-11 1-Jul-11

7-Jul-11 7-Jul-11

14-Jul-11 14-Jul-11

21-Jul-11 21-Jul-11

28-Jul-11 28-Jul-11

4J4501A-001

MTO

30-Jun-11

6-Jul-11

20-Jul-11

27-Jul-11

3-Aug-11

4J5401A-001 4J5401A-002 4J5401A-003 4J5401A-004

Instrument /Junction Box Layout Fusible Plug Layout Instrument tubing/Air Supply Cable Routing/Ladder routing

0 0 0 0

22-Jun-11 22-Jun-11 22-Jun-11 22-Jun-11

29-Jun-11 29-Jun-11 29-Jun-11 29-Jun-11

13-Jul-11 13-Jul-11 13-Jul-11 13-Jul-11

23-Jul-11 23-Jul-11 23-Jul-11 23-Jul-11

28-Jul-11 28-Jul-11 28-Jul-11 28-Jul-11

4J5701A-001 4J5701A-002 4J5701A-003

Instrument Location Wiring Diagram Block Diagram

0 0 0

22-Jun-11 22-Jun-11 22-Jun-11

27-Jun-11 27-Jun-11 27-Jun-11

4-Jul-11 4-Jul-11 4-Jul-11

11-Jul-11 11-Jul-11 11-Jul-11

18-Jul-11 18-Jul-11 18-Jul-11

4J5801A-001 4J5801A-002 4J5801A-003

DCS Marshaling cabinet wiring diagram IPS Marshaling cabinet wiring diagram Fire & Gas wiring diagram

0 0 0

1-Jul-11 1-Jul-11 1-Jul-11

8-Jul-11 8-Jul-11 8-Jul-11

20-Jul-11 20-Jul-11 20-Jul-11

27-Jul-11 27-Jul-11 27-Jul-11

3-Aug-11 3-Aug-11 3-Aug-11

4J5901A-001 4J5901A-002

Instrument Installation and Mouting Details Pneumatic Hook Up and Impulse Line Details

0 0

28-Jun-11 28-Jun-11

5-Jul-11 5-Jul-11

19-Jul-11 19-Jul-11

27-Jul-11 27-Jul-11

3-Aug-11 3-Aug-11 3.08% 13.79% 3.08% 13.79% 1.67% 7.47% 10.00% 15-Jun-11 100.00% 100.00%

5. ELECTRICAL 0 General Coordination and Site Visit 4E0001A 4E0001A 4E0001A 1 Calculations, Schedule and List 4E3001A 4E3001A Specification & Datasheets 4E3501A MTO's 4E4501A Plot Plans & Site Layouts 4E5101A 4E0001A-001 4E0001A-002 4E0001A-003 Coordination, Monitoring Progress, and Meetings with client, and etc Site Visit Site Visit report 0 0 0 8-Jun-11 15-Jun-11 22-Jun-11 15-Jun-11 22-Jun-11 17-Jun-11 23-Jun-11 15-Jun-11 6-Jul-11 18-Jun-11 24-Jun-11 15-Jun-11 20-Jul-11 20-Jun-11 26-Jun-11 15-Jun-11 4-Aug-11 21-Jun-11 27-Jun-11

4E3001A-001 4E3001A-002

Cable & MCC Calculation Cable Schedule

0 0

26-Jun-11 26-Jun-11

27-Jun-11 27-Jun-11

4-Jul-11 4-Jul-11

11-Jul-11 11-Jul-11

18-Jul-11 18-Jul-11

4E3501A-001

Prepare TRP for MCC modification

30-Jun-11

30-Jun-11

5-Jul-11

11-Jul-11

18-Jul-11

4E4501A-001

MTO's

26-Jun-11

27-Jun-11

4-Jul-11

11-Jul-11

18-Jul-11

4E5101A-001

Cable & Tray Routing Layout

22-Jun-11

27-Jun-11

4-Jul-11

11-Jul-11

18-Jul-11

C:\Documents and Settings\bibin.krissandi\My Documents\Bibin\Work\Project\12.402029-00012\402029-00012-Master Deliverable Register

Page 2 of 3

MASTER DELIVERABLES REGISTER : Provision of Installation New Air Compressor at Sabah Gas Terminal
Rev No. CTR No. Document No. Description Commencement of activity Start - (10%) Plan Actual Inter Discipline Check (IDC - 50%) Plan Actual Issued for Comment (IFC - 70%) Plan Actual Issued for Approval (IFA - 90%) Plan Actual

Project No. Contract No. Period End Issued for AFC (100%) Plan Actual

402029-00012 SBO/2009/SRE/056
10-Jun-11

TPC to issue

Progress (%) Actual Last This Actual To date Plan To date


Remarks

4E5101A 4E5101A 5 Drawings-Arrangement and details 4E5401A 4E5401A Demolition Drawings 4E5701A 4E5701A 4E5701A 4E5701A Schematic and Connection Diagram 4E5801A 4E5801A 4E5801A 4E5801A

4E5101A-002 4E5101A-003

Earthing Cable Electrical Equipment

0 0

22-Jun-11 22-Jun-11

27-Jun-11 27-Jun-11

4-Jul-11 4-Jul-11

11-Jul-11 11-Jul-11

18-Jul-11 18-Jul-11

4E5401A-001 4E5401A-001

Multiple Transit Earthing Details

0 0

25-Jun-11 25-Jun-11

3-Jul-11 3-Jul-11

13-Jul-11 13-Jul-11

20-Jul-11 20-Jul-11

27-Jul-11 27-Jul-11

4E5701A-001 4E5701A-001 4E5701A-001 4E5701A-001

Single Line Diagram Cable/light/earthing/IO/layout Cable Schedule MCC Control panel/single line/wiringdiagram (MSB/DB/MCC)

0 0 0 0

26-Jun-11 26-Jun-11 26-Jun-11 26-Jun-11

27-Jun-11 27-Jun-11 27-Jun-11 27-Jun-11

4-Jul-11 4-Jul-11 4-Jul-11 4-Jul-11

11-Jul-11 11-Jul-11 11-Jul-11 11-Jul-11

18-Jul-11 18-Jul-11 18-Jul-11 18-Jul-11

4E5801A-001 4E5801A-001 4E5801A-001 4E5801A-001

Single Line Diagram Interconnection Diagram Motor Control Schematic Wiring Diagram

0 0 0 0

6-Jul-11 6-Jul-11 6-Jul-11 6-Jul-11

7-Jul-11 7-Jul-11 7-Jul-11 7-Jul-11

12-Jul-11 12-Jul-11 12-Jul-11 12-Jul-11

18-Jul-11 18-Jul-11 18-Jul-11 18-Jul-11

25-Jul-11 25-Jul-11 25-Jul-11 25-Jul-11

Installation Details and Scope Of Work 4E5901A 4E5901A-001

Installation Details

26-Jun-11

3-Jul-11

11-Jul-11

18-Jul-11

25-Jul-11

6. STRUCTURAL 0 General Coordination and Site Visit 4S0001A 4S0001A 4S0001A 1 Calculation 4S3001A 4S3001A Drawings - Arrangement and Details 4S5401A 4S5401A 4S5401A 4S5401A 4S5401A 4S0001A-001 4S0001A-002 4S0001A-003 Coordination, Monitoring Progress, and Meetings with client, and etc Site Visit Site Visit report 0 0 0 8-Jun-11 15-Jun-11 22-Jun-11 15-Jun-11 22-Jun-11 17-Jun-11 23-Jun-11 15-Jun-11 6-Jul-11 18-Jun-11 24-Jun-11 15-Jun-11 20-Jul-11 20-Jun-11 26-Jun-11 15-Jun-11 4-Aug-11 21-Jun-11 27-Jun-11 15-Jun-11

4.82% 26.67%

4.82% 26.67%

1.29% 7.11% 10.00%

100.00%

100.00%

4S3001A-001 4S3001A-002

Foundation design Calculation Structural Framing Analysis

0 0

24-Jun-11 24-Jun-11

27-Jun-11 27-Jun-11

4-Jul-11 4-Jul-11

11-Jul-11 11-Jul-11

18-Jul-11 18-Jul-11

4S5401A-001 4S5401A-002 4S5401A-003 4S5401A-004 4S5401A-005

Site Layout and details Excavation details Foundation layout and details Anchor bolt setting details Roofing layout/details

0 0 0 0 0

27-Jun-11 27-Jun-11 27-Jun-11 27-Jun-11 27-Jun-11

1-Jul-11 1-Jul-11 1-Jul-11 1-Jul-11 1-Jul-11

8-Jul-11 8-Jul-11 8-Jul-11 8-Jul-11 8-Jul-11

15-Jul-11 15-Jul-11 15-Jul-11 15-Jul-11 15-Jul-11

22-Jul-11 22-Jul-11 22-Jul-11 22-Jul-11 22-Jul-11

TOTAL
TPC to issue

5.16%

5.16%

2.97%

C:\Documents and Settings\bibin.krissandi\My Documents\Bibin\Work\Project\12.402029-00012\402029-00012-Master Deliverable Register

Page 3 of 3

2011 June 10 17 24 1 8 July 15 22 29 Aug 5 12

100

90

80

Percent progress Deliverable per Week

70

60

50

40

30

20

10

0
% Deliverable Plan Plan Actual Actual % Total

0.00 0.00

Project No.: 402029-00012 Client Ref. Page: 1 Report Date: 17/06/2011-04:40:00 PM

PETRONAS CARIGALI SDN BHD (39275-U)

Signature Originator Review Approval Client

date

Provision of Install New Air Compressor at Sabah Gas Terminal

402029-00012 Prov. of Installation New Air Compressor at Sabah Gas Terminal


Project No. Project Title Original Planned Duration Start Planned Finish 04-Aug-11 Physical % Complete May 2011 09 16 23 30 06 June 2011 13 20 27 04 11 July 2011

Period Ending: 8 June 11

August 2011 18 25 01 08

Prov. of Installation New Air Compressor at Sabah Gas 59 13-May-11 Sa... Terminal
Project Milestones
A1008 A1009 A1010 A1020 A1030 Pre-Site Visit Project Award Latest IFC Package issued Latest IFA Package Issued Latest AFC Package

58 13-May-11 03-Aug-11 1 13-May-11 13-May-11 0 08-Jun-11 0 0 0 44 08-Jun-11 1 08-Jun-11 2 09-Jun-11 1 04-Aug-11 15 09-Jun-11 4 09-Jun-11 6 15-Jun-11 5 22-Jun-11 38 15-Jun-11 20 15-Jun-11 28-Jun-11 12-Jul-11 03-Aug-11 04-Aug-11 08-Jun-11 10-Jun-11 04-Aug-11 27-Jun-11 14-Jun-11 21-Jun-11 27-Jun-11 03-Aug-11 08-Jul-11 08-Jul-11 08-Jul-11 08-Jul-11 08-Jul-11 18-Jul-11 08-Jul-11 18-Jul-11 18-Jul-11 18-Jul-11 18-Jul-11 03-Aug-11 26-Jun-11 28-Jul-11 03-Aug-11 28-Jul-11 18-Jul-11 03-Aug-11 03-Aug-11 25-Jul-11 18-Jul-11 18-Jul-11 18-Jul-11 18-Jul-11 25-Jul-11 18-Jul-11 25-Jul-11 25-Jul-11 22-Jul-11 18-Jul-11 22-Jul-11 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%

Project Management
A1040 A1050 A1060 Kick Off Meeting Project Schedule Baseline Project Close Out

Drawing Search & Site Visit


A1070 A1080 A1090 Drawing Search Site Visit Site Visit Report

Engineering
Process
4P2001A 4P2501A 4P4001A 4P5701A Studies PFD/P&ID Mark-up & Maintenance Schedules And Lists Demolition drawing & Hazardous Area Cert.

20 15-Jun-11 18 17-Jun-11 13 23-Jun-11 13 23-Jun-11 21 21-Jun-11

Mechanical
4L2501A 4L4501A 4L5101A 4L5501A 4L8501A PFD/P&ID Drafting MTO Plot Plan & Site Layouts Isometrics Scope of Work

15 21-Jun-11 12 01-Jul-11 20 22-Jun-11 16 27-Jun-11 16 27-Jun-11 33 21-Jun-11

Instrument
4J2501A 4J4001A 4J4501A 4J5401A 4J5701A 4J5801A 4J5901A PFD/P&ID Input Schedules & Lists MTO Drawings- Arrangement & Details Demolition drawings Schematic & Connection Diagram Installation Details

5 21-Jun-11 20 01-Jul-11 25 30-Jun-11 28 22-Jun-11 20 22-Jun-11 24 01-Jul-11 27 28-Jun-11 25 22-Jun-11

Electrical
4E3001A 4E3501A 4E4501A 4E5101A 4E5401A 4E5701A 4E5801A 4E5901A Calculations and Schedule & list Specifications & Data Sheets MTO Plot Plans & Site Layouts Drawing- Arrangement and Details Demolition drawings Schematics & Connection Diagrams Installation Details

17 26-Jun-11 13 30-Jun-11 17 26-Jun-11 20 22-Jun-11 22 26-Jun-11 17 26-Jun-11 14 06-Jul-11 22 26-Jun-11 22 24-Jun-11

Structural
4S3001A 4S5401A Calculations Drawings- Arrangement & Details

18 24-Jun-11 20 27-Jun-11

Date 08-Jun-11

Revision Rev.0

Checked Danilo R Villanueva

Approved Stale Buri

Primary Baseline Third Baseline

Revised Baseline Milestone

% Complete Summary

TASK filter: All Activities Primavera Systems, Inc.

PROJECT No.402029-00014

402029-00014 - Provision For Detailed Design For Lifeboat Installation At SMQ-A


Manhours CTR NO.

CTR Activity

Budget

Actual

Balance

COST, TIME AND RESOURCE CATALOGUE

0001 MAN 4Z0001A 4Z0001A 4Z0001A 4Z0001A

PROJECT MANAGEMENT Project Management Kick Off Meeting Design Review Interface Meeting 363.0 20.0 40.0 40.0 106.0 569.0 24.0 24.0 48.0 24.0 200.0 272.0 9.5 353.5 9.5 353.5

Review Conceptual Studies 4Z0001A GN1005 SUB-TOTAL - PROJECT MANAGEMENT 0004 MAN 4Z0001A 0002 DES 4L3001A 4L4001A 4L5101A PROJECT CLOSE OUT REPORT Project Close Out Report

SUB-TOTAL - PROJECT CLOSE OUT REPORT MECHANICAL/PIPING ENGINEERING Calculations Schedules and Lists Plot Plans & Site Layouts

SUB-TOTAL - C. MECHANICAL 0004 DES 4E3001A 4E3501A 4E4501A 4E5401A ELECTRICAL ENGINEERING Calculations Specification & Data Sheets MTO's Drawings - Arrangement And Details

24.0 68.0 54.0 206.0 352.0 8.0 8.0 -

SUB-TOTAL - E. ELECTRICAL 0005 DES 4S3001A 4S5401A 4S8501A STRUCTURAL ENGINEERING Calculations Drawings - Arrangement And Details Construction Support

396.0 792.0 64.0 1,252.0 50.0 32.0 15.0 15.0

SUB-TOTAL - F. CIVIL/STRUCTURAL 0006 DES 4R8001A 4R8001A SUB-TOTAL - HAZOP SAFETY-HAZID HAZID-KL HAZID Workshop

82.0 TOTAL MANHOURS :

2,551.0

32.5

353.5

MASTER DELIVERABLES REGISTER : Provision for Detailed Design Lifeboat Installation at SMQ-A PCSB SBO
Commencement of activity Start Rev - (10%) No. CTR No. Document No. Description Plan Actual Inter Discipline Check (IDC - 50%) Plan Actual Issued for Comment (IFC - 70%) Plan Actual Issued for Approval (IFA - 90%) Plan Actual

Project No. Contract No. Period End Issued for AFC (100%)

402029-00014 SBO/2009/SRE/056
23-Jun-11

TPC to issue

Progress (%) Actual Last This 11.14% 11.14% 10.00% 100.00% Actual To date 11.14% 11.14% 10.00% 100.00% Plan To date 11.14% 11.14% 10.00% 100.00%
Remarks

Plan

Actual

1. GENERAL 1 Project Management 4Z0001A 4Z0001A 4Z0001A 4Z0001A 4Z0001A 4Z0001A

4Z0001A 4Z0001A 4Z0001A 4Z0001A 4Z0001A 4Z0001A

General Coordination and Monitoring Project Kick Off meeting Design Review Meeting Interface Meeting Review Conceptual basis Project Schedule Baseline

0 0 0 0 0 0

16-Jun-11 16-Jun-11 24-Jun-11 15-Jul-11 29-Jun-11 16-Jun-11

16-Jun-11 16-Jun-11

16-Jun-11

1-Jul-11 16-Jun-11 24-Jun-11 15-Jul-11 4-Jul-11 16-Jun-11

16-Jun-11

16-Jun-11

16-Jul-11 16-Jun-11 24-Jun-11 15-Jul-11 9-Jul-11 16-Jun-11

16-Jun-11

16-Jun-11

31-Jul-11 16-Jun-11 24-Jun-11 15-Jul-11 14-Jul-11 16-Jun-11

16-Jun-11

16-Jun-11

17-Aug-11 16-Jun-11 8-Jul-11 5-Aug-11 19-Jul-11 16-Jun-11

16-Jun-11

16-Jun-11

100.00%

100.00%

100.00%

1. MCHANICAL PIPING 1 Calculations 4L3001A Schedule and List 4L4001A 4L4001A Plot Plan and Site Layout 4L5101A 4L5101A

4L3001A-001

Calculations

6-Jul-11

13-Jul-11

27-Jul-11

3-Aug-11

11-Aug-11

4L4001A-001 4L4001A-001

Tie- In Schedules Drawing List/Index (LOT)

0 0

6-Jul-11 6-Jul-11

13-Jul-11 13-Jul-11

27-Jul-11 27-Jul-11

3-Aug-11 3-Aug-11

12-Aug-11 12-Aug-11

4L5101A-001 4L5101A-001

Plot plan for optimisation of location of equipment Escape route and safety equipment plan

0 0

29-Jun-11 29-Jun-11

3-Jul-11 3-Jul-11

10-Jul-11 10-Jul-11

17-Jul-11 17-Jul-11

21-Jul-11 21-Jul-11

2. ELECTRICAL 1 Calculations 4E3001A 4E3001A Specification & Datasheets 4E3501A MTO's 4E4501A Drawings-Arrangement and details 4E5401A

4E3001A-001 4E3001A-002

Calculation report Lighting studies report

0 0

6-Jul-11 6-Jul-11

12-Jul-11 12-Jul-11

19-Jul-11 19-Jul-11

26-Jul-11 26-Jul-11

2-Aug-11 2-Aug-11

4E3501A-001

Specification and Datasheets

13-Jul-11

16-Jul-11

23-Jul-11

30-Jul-11

4-Aug-11

4E4501A-001

Long Lead Item/Bulk MTO/MR

13-Jul-11

16-Jul-11

23-Jul-11

29-Jul-11

4-Aug-11

4E5401A-001

Installation detail drawing

13-Jul-11

14-Jul-11

21-Jul-11

28-Jul-11

4-Aug-11

3. STRUCTURAL 1 Calculation 4S3001A 4S3001A 4S3001A 4S3001A 4S3001A 2 Drawings - Arrangement and Details 4S5401A 4S5401A-001 Detail drawings (support details, handrail, grating, ladder, lifting and platform details) 0 29-Jun-11 6-Jul-11 20-Jul-11 3-Aug-11 16-Aug-11

3.16% 10.00% 10.00% 10.00% 10.00% 10.00% 10.00%

4S3001A-001 4S3001A-002 4S3001A-003 4S3001A-004 4S3001A-005

Topside In-place Analysis/Report Substructure In-place Analysis/Report Review/update existing Sacs model and PSI model, under water inspection report Strenghtening Design/Analysis Lifting Analysis/Procedure

0 0 0 0 0

17-Jun-11 17-Jun-11 17-Jun-11 17-Jun-11 17-Jun-11

24-Jun-11 24-Jun-11 24-Jun-11 24-Jun-11 24-Jun-11

12-Jul-11 12-Jul-11 12-Jul-11 12-Jul-11 12-Jul-11

26-Jul-11 1-Aug-11 1-Aug-11 1-Aug-11 1-Aug-11

9-Aug-11 15-Aug-11 15-Aug-11 15-Aug-11 15-Aug-11

C:\Documents and Settings\bibin.krissandi\My Documents\Bibin\Work\Project\4.402029-00014\402029-00014-Master Deliverable Register

Page 1 of 2

MASTER DELIVERABLES REGISTER : Provision for Detailed Design Lifeboat Installation at SMQ-A PCSB SBO
Commencement of activity Start Rev - (10%) No. CTR No. Document No. Description Plan Actual Inter Discipline Check (IDC - 50%) Plan Actual Issued for Comment (IFC - 70%) Plan Actual Issued for Approval (IFA - 90%) Plan Actual

Project No. Contract No. Period End Issued for AFC (100%)

402029-00014 SBO/2009/SRE/056
23-Jun-11

TPC to issue

Progress (%) Actual Last This Actual To date Plan To date


Remarks

Plan

Actual

Construction Support 4S8501A 4S8501A-001 Construction Support 0 29-Jun-11 30-Jun-11 7-Jul-11 14-Jul-11 21-Jul-11

4. SAFETY 0 HAZOP FACILITATOR 4R2001A 4R8001A 4R0001A 4R2001A-001 4R8001A-001 4S0001A-001 Review Conceptual basis KL HAZID-KL HAZID-Workshop 0 0 0 29-Jun-11 20-Jul-11 27-Jul-11 1-Jul-11 20-Jul-11 28-Jul-11 8-Jul-11 22-Jul-11 28-Jul-11 13-Jul-11 24-Jul-11 28-Jul-11 19-Jul-11 26-Jul-11 28-Jul-11

TOTAL
TPC to issue

2.36%

2.36%

3.91%

C:\Documents and Settings\bibin.krissandi\My Documents\Bibin\Work\Project\4.402029-00014\402029-00014-Master Deliverable Register

Page 2 of 2

2011 June 17 24 1 July 8 15 29 5 Aug 12 19 26

100

90

80

Percent progress Deliverable per Week

70

60

50

40

30

20

10

0
% Deliverable Plan Plan Actual Actual % Total

0.00 0.00

Project No.: 402029-00014 Client Ref. Page: 1 Report Date: 16/06/2011-12:00:00 AM

PETRONAS CARIGALI SDN BHD (39275-U)

Signature Originator Review Approval Client

date

Provision for Detailed Design for Lifeboat Installation at SMQ-A

402029-00014 Prov. Of Det. Design For Lifeboat Installation at SMQ-A


Project No. Project Title Original Planned Duration Start 53 08-Jun-11 52 08-Jun-11 0 08-Jun-11 0 0 0 47 16-Jun-11 1 16-Jun-11 2 17-Jun-11 1 17-Aug-11 45 17-Jun-11 33 29-Jun-11 Calculation Schedule and List Plot Plans & Site Layouts 28 06-Jul-11 28 06-Jul-11 17 29-Jun-11 22 06-Jul-11 Calculations Specification and datasheets MTO's Drawings - Arrangement and Details, Installation Details 20 06-Jul-11 17 13-Jul-11 17 13-Jul-11 17 13-Jul-11 45 17-Jun-11 Calculations Drawings- Arrangement and Details Construction Support 40 17-Jun-11 35 29-Jun-11 17 29-Jun-11 22 29-Jun-11 Review conceptual studies HAZID -KL HAZID Workshop 15 29-Jun-11 5 20-Jul-11 2 27-Jul-11 18-Jul-11 03-Aug-11 16-Aug-11 17-Aug-11 16-Jun-11 19-Jun-11 17-Aug-11 16-Aug-11 12-Aug-11 12-Aug-11 12-Aug-11 21-Jul-11 04-Aug-11 02-Aug-11 04-Aug-11 04-Aug-11 04-Aug-11 16-Aug-11 09-Aug-11 16-Aug-11 21-Jul-11 28-Jul-11 19-Jul-11 26-Jul-11 28-Jul-11 Planned Finish 17-Aug-11 16-Aug-11 June 2011 06 13 20 27 04 July 2011 11 18 25

Period Ending: 8 June 11


August 2011 01 08 15 22

Prov. Of Det. Design For Lifeboat Installation at SMQ-A ...


Project Milestones
A1000 A1010 A1020 A1030 Project Award Last IFC package Last IFA package Last AFC Package

Project Management
A1050 A1060 A1070 Kick Off Meeting Develop Project Schedule Baseline Project Close Out

Engineering
Mechanical
4L3001A 4L4001A 4L5101A

Electrical
4E3001A 4E3501A 4E4501A 4E5401A

Structural
4S3001A 4S5401A 4S8501A

Safety
4R2001A 4R8001A 4R8002A

Date Revision 08-Jun-11 Rev.0

Checked Danilo R Villanueva

Approved Stale Buri

Primary Baseline Third Baseline

Revised Baseline Milestone

TASK filter: All Activities Primavera Systems, Inc.