Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
4.1 INTRODUCTION
The decision made on the most appropriate option of project delivery will be closely followed by a decision on the most appropriate option for the contract price. The price payable under the contract to members of a project team for specific work and services may either be pre-ascertained in the form of a lump sum or price rates, or determined when a project has been completed. The former approach is known as a fixed-price contract while the latter is usually cost-plus. These two options for a contract price will now be discussed in more detail. There are other options that are used less often. In some forms of contract, for example BOOT, the price may depend on the earnings from the completed project or on a lease arrangement or another formula quite unrelated to the cost of construction. In these types of contract, there is usually no provision for progress payments for the construction work, and the contract price is often payable by the contractor to the principal.
said to be fixed at the start of the contract but it may change during its execution if the contract conditions allow cost adjustment. The most common contract conditions that allow cost to be adjusted are variations, latent site conditions, rise and fall, provisional or prime cost items, and clauses for other risks beyond the control of the contract party claiming such cost adjustments. In this scenario, the original contract price will be different (generally less) than the final contract cost. If the principal wants, for example, to fix the contract price of the main contractor for the entire contract period, the principal would need to delete from the contract any conditions that the contractor might otherwise use to claim for cost adjustments. The principals intent is to shift the risk of cost overruns onto the contractor. This practice may be justified in some situations but only when:
the project risk is very low the brief is complete the design documentation is accurate the principal will not make changes to the brief and the design the design consultants are competent.
While the principal may be able to draft a contract so that the contract price is indeed fixed for the entire project period, the principal may end up paying more for the work in the long run. This is because the contractor will estimate the likely cost of the risk of sustaining a fixed-price contract and will add it to the tender price in the form of a risk contingency. The problem for the principal is that the principal doesnt know the value of this risk contingency. If it is too high, the principal will clearly pay more for the work. If it is too low, the risk of the contractors financial losses is likely to increase. This event would in turn increase the principals risk of project cost overruns because in the effort to minimise the losses, the contractor would most likely:
compromise the quality of the work force subcontractors on lower subcontract prices, which in turn will further increase the risk of achieving poor-quality work in addition to the possibility of subcontractors becoming insolvent delay payments to subcontractors and suppliers proceed to develop a claim against the principal.
Fixing a contract price for the entire contract period may not be in the principals best interest. It is also worth noting that this practice is likely to lead to the development of an adversarial relationship between the parties to a contract.
61 Options for contract price
Fixed-price contracts consist either of a single sum or the aggregate of various prices or rates in the form of a schedule prepared by the bidding general contractor or prepared by the principal and priced by the bidding contractor.
Lump-sum contracts are not restricted to the activities of contractors and subcontractors. Consultants such as project managers or even designers may be engaged on lump-sum contracts. The decision on whether or not to engage consultants on a lumpsum contract should be based on the extent and accuracy of the information available.
described as a schedule of estimated quantities and rates but it is more commonly described simply as a schedule of rates. In order to reduce the risk for both contractual parties, some standard conditions of contract stipulate agreed limits of accuracy for estimated quantities.
One distinct advantage of cost-plus contracts is that construction can begin on site before design work is complete and without the usual preliminary arrangements. It also avoids most arguments over variations. Cost-plus contracts may be used in conjunction with the traditional method of delivery, but their main application is in managed delivery methods. In the traditional method of project delivery, contractors compete for work through a tender process. When the principal decides to award the main contract on a cost-plus basis, because of the unknown nature and extent of the work, the main selection criterion is the tender price or the fee (usually called a management fee), which includes overheads, profit and possibly the cost of preliminary items. The cost-plus contract will be formed between the principal and the contractor while subcontracts will usually be fixed-price. The winning contractor will be paid the fee and will be reimbursed for cost. From the operational point of view, the contractor may initially pay for all the costs as they occur. The contractor will then invoice those costs on a monthly basis to the principal who, after verifying their accuracy, will reimburse the contractor in full. The principal will pay the agreed portion of the fee to the contractor also on a monthly basis. So that the contractor will need the least possible capital to run the project, the contractor will usually invoice the principal before actually paying subcontractors and will negotiate terms of subcontract that make the time for payment of subcontractors after the date on which the principal must pay the contractor. Since the contractors risk in cost-plus contracts is very low, the principal needs to be aware of the possibility of the contractors complacency, which could have a detrimental effect on the contract performance. In choosing to use a cost-plus contract in combination with the traditional method of project delivery, the principal should:
select tendering only apply, apart from the tender price, other selection criteria such the contractors reputation, quality and quantity of resources both human and physical, financial strength, and the like engage a quantity surveyor or another suitably qualified consultant to monitor the contractors claims for cost consider inclusion in the contract of incentives for the contractor to keep costs low and expedite completion.
The risk can be reduced for both parties by including in the contract agreed limits of cost and time beyond which the lump sum will not apply.
implement. The contractor will be paid as a bonus an agreed percentage of the saving, if the saving was realised. Conversely, if the final cost is higher than the agreed estimate (also known as a target price or a guaranteed maximum), the contractor would incur a penalty by having the fee reduced accordingly. However, in practice this concept is often difficult to make work. The main problem lies in the difficulty of agreeing on the value of the guaranteed maximum price at the start of the project when only limited design information is available. If the guaranteed maximum price is overstated and the contractor is bound to earn a substantial profit, the principal may question its accuracy and relevance as a benchmark for assessing the contractors portion of the bonus. Conversely, if it is understated, the contractor would undoubtedly take defensive action to avoid the payment of a penalty for overrunning on cost. If the actions of the principal cause the contractor to fail to qualify for a bonus, the contractor may have a claim for breach of contract and the measure of damages may be the lost bonus. Therefore a contract provision for a bonus is only efficient where there is very little risk of interference by the principal with the work or progress.