Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
SECTION I:
INTENT
This CBA provides an overview of the planning and scheduling process on capital projects and presents project management responsibilities for initiating and verifying the successful execution of that process. The planning and scheduling process starts in the Conceptual phase and continues throughout the life of a project. Planning and scheduling activities help project teams: Gain alignment with management. Align and focus on delivering project objectives. Develop target dates for completing work based on logically sequenced activities. Manage work against these target dates and logic. Renegotiate and revise the plan as project conditions change Determines the critical path activities to provide focus for the team This CBA also provides project management approaches for planning and scheduling by presenting: Planning and scheduling principles, The planning and scheduling development process, Guidelines for implementation
PAGE: 2
Figure 81 illustrates the process for initial schedule development. Additional information about each activity shown in the flowchart is available. The process is applicable for the various schedules produced in each phase of a project.
Team & Management Align to project objectives, success criteria, & key assumptions.
PLANNING
Team Identifies the logic (sequence & interdependencies) for the activities.
Team Identifies the duration & activity owners required for each activity. The critical path is determined. Produce Schedule.
SCHEDULE DEVELOPMENT Does the schedule completion date match with project objectives ? YES Team Assesses the risk of not achieving the needed completion date.
NO
YES
NO
Can team identify risk mitigation/contingency plans that do not require management approval?
Is the Risk acceptable ? NO YES Team Uses the Schedule to control the work and deliver the project objectives. If changes are required, appropriate parts of this process will need to be repeated.
PAGE: 3
PAGE: 4
PAGE: 5
EXECUTIONAL SCHEDULES
Project Teams use Executional Schedules to plan and control the work of each project phase to meet the overall Product Supply and Business timing needs. Three levels of schedule are used to satisfy different Project Management needs: Level 1, Level 2, and Level 3. Level 1 Schedule: An overview or summary schedule displaying major milestones, duration of significant blocks of work, and fundamental logic relationships. These schedules are often referred to as management summary or Milestone schedules. Level 2 Schedule: A schedule with moderate detail which breaks major work blocks into key sub-tasks or systems. Typically arranged by project phase, these schedules show start and finish dates for tasks and key task interdependencies. Level 3 Schedule: A detailed schedule displaying all activities for an individual or work group. These schedules show start and end dates, all pertinent relationships among activities, and an indication of how activities are progressing against the target plan. The schedule is often called the control schedule.