Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1.1 project outline 4.1 basement & ground floor 8.1 energy cells
1.2 client 4.2 steel frame & circulation 8.2 pods key
1.3 urban context - high street 2012 4.3 pods & cinema 8.3 kalwall precedent
1.4 high street 2012 initiatives 4.4 facade 8.4 kalwall performance
1.5 64-68 whitechapel high street 4.5 steel frame 8.5 pod construction
1.6 proposed site 8.6 connection to superstructure
1.7 project timeline 5.0 FACADE 8.7 lighting strategy - night
1.8 urban context - failing high street 8.8 plugin cells
1.9 urban context - encroaching development 5.1 facade render 8.9 heating & cooling
1.10 urban strategy - historical grain 5.2 elgin marbles precedent
1.11 urban strategy - high street 5.3 historical photos 9.0 CINEMA
1.12 programme 5.4 breaking down facade
5.5 recreating the facade 9.1 hanging above the market
2.0 KEY SPACES 5.6 recreating the facade cont. 9.2 structure - shell
5.7 moment connections 9.3 suspended within frame
2.1 high street 5.8 key views - aldgate east 9.4 structure - suspension
2.2 market area 5.9 key views - osborn street 9.5 suspension steel connections
2.3 exhibition space 5.10 key views - whitechapel high street 9.6 exploded axonometric
2.4 cinema suspended 9.7 wall construction
2.5 energy cells 6.0 GROUND FLOOR 9.8 floor construction
2.6 gym - visual connection 9.9 roof construction
2.7 greenhouse - energy cultivation 6.1 link to high street 9.10 external cladding
2.8 circulation 6.2 market 9.11 cinema contrast
2.9 scheme diagram 6.3 exhibition space 9.12 acoustics
6.4 transformation 9.13 heating schematic
3.0 GENERAL ARRANGEMENT DRAWINGS 9.14 hall ventilation - heating
7.0 CIRCULATION 9.15 hall ventilation - cooling
3.1 basement plan 9.16 part m
3.2 ground floor plan 7.1 external space
3.3 first floor plan 7.2 movement 10.0 ENERGY SYSTEMS
3.4 second floor plan 7.3 foyer
3.5 third floor plan 7.4 structure 10.1 the body
3.6 section a 7.5 pressure pads 10.2 environmental overview
3.7 section b 7.6 exposed services 10.3 pavegen precedent
3.8 perspective section c 7.7 lighting strategy - day 10.4 pavegen - market
3.9 perspective section d 7.8 lighting strategy - night 10.5 walkway pressure pads
10.6 green gym - precedent
10.7 energy calculations
10.8 joint braces
10.9 masks
10.10 urine electrolysis
10.11 cooling system
10.12 fire performance
PART 1
INTRODUCTION
1.1 PROJECT OUTLINE
commercial St.
whitechapel high st.
C
B
mansell st.
leman St.
A
a. braham street park b. 64-68 whitechapel high street c. altab ali park
‘braham street park was completed in february 2010, funded by private ‘improvement works to the six buildings were concentrated on the front ‘a series of improvements are planned at altab ali park including new
sector s106 contributions and the lda. the new park sits on what was elevations and parts of the buildings that faced the high street. the tree planting, a better setting for the shaheed minar monument and new
previously part of a busy road system and now provides a more tranquil buildings have benefitted from extensive conservation repair’ seating areas that will trace the foundations of the church that used to
space for local residents, visitors and people who work in the area.’ high street 2012 stand on the site, bringing the history of the area to the surface.’
high street 2012 high street 2012
the project involved the complete rebuilding of the two facades that face
braham street park sits on a narrow strip of land, flanked on both onto whitechapel high street, the original brickwork had been render over the park was completed in november 2011 by muf architects. the project
sides by tall office buildings. the park has a very corporate feel, the and the stonework damaged and removed. the render and original brick aimed to recapture the history of the site and involve local residents.
hard landscaping and sharp angled lines within the design of the park work was completely stripped off the elevation and new brick slips put in a community archeological dig was held and the artefacts found in the
mimic those found within the city of london to the west. it is sold as a place. the project was more of a rebuild than a restoration with new stone dig were used by muf in installations in the park. the design of the park
park for residents but it is sparsely populated with smokers from the work and mouldings being created using historic photographs to mimic the created a layering effect of history; it is a new design yet it respects
adjoining office buildings and the occasional person eating their lunch. original building. there were no alterations to the interiors, or the rear what was their before. the past is represented in a way that can be used
it is overshadowed for most of the day by the surrounding buildings and elevations of the building, the project was merely a facelift. and appreciated by the local community but it is not a pastiche of what
has no link the whitechapel high street itself. it is not obvious to anyone has been.
passing along the high street that there is even a park there.
1.5 64-68 WHITECHAPEL HIGH STREET
str
the chosen site is 64-68 whitechapel high
eet
street, which was one of the projects in
E the high street 2012 scheme. it is at the
very start of the high street 2012 route in
aldgate, adjacent to the city of london and
D new development on whitechapel high street.
C this project envisages a slightly different
et
re sequence of events during the high street
st
gh B 2012 project however [detailed overleaf]
l hi
a pe
ch the existing buildings are the only surviving
te
whi historical buildings on the south side of
A the high street between altab ali park and
the city so are an important set of buildings
for the character and history of the area.
the buildings have however fallen into
significant disrepair.
the project is set two years in the past, in 2010, when the it was announced that the already involved in the london 2012 olympics as the official energy supplier edf energy
london 2012 marathon route was no longer passing along the a11 through east london are looking to undertake projects along the olympic route and decide to take on the
and was going to take place in central london instead. the project envisages that after project at 64-68 whitechapel high street. the tight timescale between project inception to
this announcement the funding for the high street 2012 project aimed at improving the the start of the olympic games when it must be completed and ready for use has a number
high streets along the original marathon route is dramatically reduced. therefore the of effects on the professional context of the project which are described further on in
projects that were originally proposed on the route are suspended until new investors the report.
come forward to take on the projects.
1.8 URBAN CONTEXT - FAILING HIGH STREET
KEY SPACES
2.1 HIGH STREET
site boundary
public realm - market/exhibition area
2.2 MARKET AREA
rth
no
summer sunpath
on
no
market/exhibition area
ground floor circulation/foyer
vertical circulation
tickets/reception
gym pods
cinema
greenhouse pods
bar
basement basement plant and service areas
n
PART III
A B G
C
E
D D D
O N M L
Q
C
R R
A exhibition store
B market store
C lift
D rooflight above
P E unheated corridor
F office
G food store
H male changing/showers
I male wcs
J female changing/showers
K female wcs
L urine electrolysis
M hydrogen combustion
n energy store
o ventilation plant
p market/exhibition space
q tickets/reception
r rooflight to basement
s mesh walkway
t cinema
u gym pods
v bar
x external growing space
y heated greenhouses
U
V U U U C U
A exhibition store
B market store
C lift
D rooflight above
E unheated corridor
F office
G food store
H male changing/showers
T I male wcs
J female changing/showers
K female wcs
L urine electrolysis
M hydrogen combustion
n energy store
o ventilation plant
p market/exhibition space
q tickets/reception
r rooflight to basement
s mesh walkway
t cinema
u gym pods
v bar
x external growing space
y heated greenhouses
U
V U U U C U
A exhibition store
B market store
C lift
D rooflight above
E unheated corridor
F office
G food store
H male changing/showers
T I male wcs
J female changing/showers
K female wcs
L urine electrolysis
M hydrogen combustion
n energy store
o ventilation plant
p market/exhibition space
q tickets/reception
r rooflight to basement
s mesh walkway
t cinema
u gym pods
v bar
x external growing space
y heated greenhouses
X
Y A exhibition store
B market store
C lift
D rooflight above
E unheated corridor
F office
G food store
H male changing/showers
Y Y Y I male wcs
J female changing/showers
K female wcs
L urine electrolysis
M hydrogen combustion
n energy store
o ventilation plant
p market/exhibition space
Y q tickets/reception
r rooflight to basement
s mesh walkway
t cinema
u gym pods
v bar
x external growing space
y heated greenhouses
X Y
U S
T
3.6 SECTION A 1:100
A exhibition store
B market store
C lift
U S D rooflight above
E unheated corridor
F office
G food store
H male changing/showers
I male wcs
J female changing/showers
K female wcs
L urine electrolysis
M hydrogen combustion
n energy store
Q R P o ventilation plant
p market/exhibition space
q tickets/reception
r rooflight to basement
s mesh walkway
t cinema
u gym pods
v bar
x external growing space
B E M
y heated greenhouses
Y Y Y Y Y
A exhibition store
B market store
C lift
D rooflight above
E unheated corridor
F office
G food store
T H male changing/showers
I male wcs
J female changing/showers
K female wcs
L urine electrolysis
M hydrogen combustion
n energy store
o ventilation plant
p market/exhibition space
q tickets/reception
P r rooflight to basement
s mesh walkway
t cinema
u gym pods
v bar
x external growing space
y heated greenhouses
O N M L J H
Y Y Y Y
A exhibition store
B market store
C lift
D rooflight above
E unheated corridor
F office
G food store
H male changing/showers
I male wcs
J female changing/showers
K female wcs
T L urine electrolysis
M hydrogen combustion
n energy store
o ventilation plant
p market/exhibition space
q tickets/reception
r rooflight to basement
s mesh walkway
t cinema
u gym pods
v bar
x external growing space
P y heated greenhouses
O N M L J H
X Y
S U
T S U
SUPER STRUCTURE
4.1 BASEMENT & GROUND FLOOR
the basement will be constructed from in situ reinforced concrete. although a the ground floor will be constructed from a one way reinforced in situ
basement already existing on the site this will be dug out and completely rebuilt slab with integral supporting beams. it will span between the external
to create a stable base for the new building that can support all the new loads. walls and the central corridor walls on the basement. five columns
the basement will be constructed as two large concrete spaces separated by will be positioned in the basement where extra support is required.
a concrete corridor. the basement partitions will be constructed from timber
studs allowing for flexibility in the space in the future
4.2 STEEL FRAME & CIRCULATION
a braced steel frame will provide the super-structure for the the circulation walkways will sit on the steel super-structure, they will
building above ground. the steel frame will sit along the lines of the be constructed of galvanized steel to differentiate them from the painted
concrete basement walls and on the lines of the floor slab beams to steel frame. they will be one of the first parts of the structure to go in
create a continuity of the structural load forces. allowing the construction team platforms to work from.
4.3 PODS AND CINEMA
cinema pods
the cinema will be suspended in a void in the steel super-structure. the gym, bar and greenhouse pods will be constructed from lightweight,
it will hanging from the third floor section of the steel frame and insulated kalwall panels within a lightweight steel frame. the walls,
be braced back to the frame at a lower level. its shell will be a floors and roofs will all be constructed from the same system allowing
lightweight steel construction, braced to create a rigid box. quick, simple construction. they will be supported within the steel
superstructure with bolted bracket connections.
4.4 FACADE
facade
FACADE
5.1 FACADE RENDER
5.2 ELGIN MARBLES PRECEDENT
niall mclaughlin architects have undertaken The Parthenon stones were made in a particular the casts elude to a history without becoming
a project at the london 2012 olympic park place at a particular time. Their deracination a pastiche of the parthenon. this projects
where they have clad the building with casts and constant re-idealisation has made them into has the same aim to recreate and celebrate a
concrete friezes of the elgin marbles from the something else – something iconic that people historical facade on whitechapel high street
parthenon. the elgin marbles which are housed recognise, like a picture of Elvis that sits within a conservation area. the facade
at the british museum, were digitally scanned niall mclaughlin, concrete quarterly will be recreated in concrete casts and broken
then grp lined rubber moulds were produced autumn 2011 up to elude to the history of the site by turning
for the concrete casting process. the casts the facade into more of a sculpture than a
were made using a white cement to give them a pastiche.
brighter appearance.
5.3 HISTORICAL PHOTOS
expanded polystyrene moulds will be cnc cut using the virtual 3d model. the mould will be cast from a white cement to emphasise the play of light the precast panels will be fixed to the steel superstructure of the
due to the variety of different casts required it would not be worth across the historical details. the fixing brackets will be cast into the building.
creating rubber or grp moulds as each mould will only be used a maximum precast panels
of three times. once the moulds have been used they will be recycled
where they can be broken down and used in the packaging industry or as
an additive in lightweight concrete.
steel fixing brackets will be added to the mould before the concrete is
poured.
5.6 RECREATING FACADE
5.6 TITLE
the facade panels will be fixed to a steel ‘i’ section ring beam that will the facade panels will be fixed using two types of connection. the bottom single glazed timber window frame will be fitted to the precast panels.
terminate the cantilevered sections of the projecting steel frame. connection will be load bearing and the top connections will be for the windows will be a play on the idea of the broken facade as they won’t
restraint. the bottom connection is made up of a steel plate, strengthened actually be doing any work in sealing the building but will add to the
with flanges which bolts directly to the steel frame. the steel plate is rhythm of the facade.
drilled with elongated bolt holes to allow for alignment of the panel
and steel structure. the top connections do not take any load but just
tie the panels back to the frame. they allow movement in three directions
via the elongated bolt holes and nylon or teflon washers. the aim of the
top connections is to decouple the different movement of the steel from
that of the concrete.
5.7 MOMENT CONNECTIONS
GROUND FLOOR
6.1 LINK TO HIGH STREET
C
F
H
6.2 MARKET A visual connection to walkways above e cinema black box hangs above market in contrast to white steel frame
B diffused light coming through gym pods above f back of site opened up to footpath at rear
C white painted steel frame allows colours of g plots will be rented to independent local traders
market to define the space h small plots allow affordable solutions for traders that can’t afford
D steel frame allows traders to hang objects plots at the more expensive spitalfields or whitechapel high street markets
B
C F
A
6.3 EXHIBITION SPACE A cinema ticket office glows and acts as a beacon d double height space under seating rake for exhibitions
B the gym pods glow when in use identifying that e underside of cinema can be used as a projection screen
there is energy being created within them. f walk on roof light to basement
C the high street lighting leaks into the building g high street floor finish extends into ground floor
blurring the building’s boundary. creating a seamless space.
6.4 TRANSFORMATION
basement
PART VII
CIRCULATION
7.1 EXTERNAL SPACE
market area
circulation walkways
external space
n
7.2 MOVEMENT
A steel super-structure
c B energy producing pressure pads
C steel support channels
f e d D service zone under walkway
b E grp mesh and clamping sections
F galvanised steel ‘c’ & ‘i’ section beams
spanning between superstructure
G galvanized balustrade fixing bracket
H galvanized balustrade vertical elements
I grp mesh infill panels
J galvanised hand rail support
K galvanised steel handrail
A
7.5 PRESSURE PADS
A
A
B
A
G
C
A
C
GYM
solar energy
GREENHOUSE PODS
the grown produce into high energy
drinks and food to be consumer by
the users of the gym pods where
the energy they expel is converted
into electrical energy and heat to
GYM PODS
JUICE BAR
power the building.
the specification for the gym pods will be part l maximum u-values:
a panel with a high insulation value, low walls 0.35 w/m2k
solar heat gain coefficient and medium light roof 0.25 w/m2k.
transmission value [the solar heat gain floor 0.25 w/m2k.
coefficient increases with light transmission
so a medium light transmission value with give light transmittance
a low heat gain coefficient but still provide depending on the type of insulation specified
the translucent qualities required] the diffuse light transmission of the panels
varies between 3 - 63%. the solar heat gain
this specification would be a 100mm thick coefficients range from 0.1 to 0.65.
panel with the white coating to the exterior
face and crystal coating to the interior fire
face with fibreglass insulation which would kalwall is a thermoset material which is
provide a u-value of 0.20 w/m2k, a light unaffected by heat meaning it will not drip
transmission value of 18% and heat gain shatter or melt in a fire. they are 1 hour fire
coefficient of 0.24. rated.
8.5 POD STRUCTURE
A restraint bracket
the pods will be lit with led tubes which will hang
directly from the internal steel frame of the pod.
they will be exposed light tubes with no shades
so the light is dispersed evenly around through
pod allowing it to glow from the floor, roof and
walls. the lights will be fitted with motion sensors
so the pods only light up when in use. if people are
in the pods but not moving to create energy the
lights will go off until they start moving again.
A
B
C
8.8 PLUGIN CELLS
the gym pods will be mechanically ventilated through the use of a heat exchanger. to allow
to allow greater control than with a natural a maximum harvest of the heat from the body
ventilation system. the pods will be unheated the pods have been designed as small entities
spaces heated only by the body heat of the that do not need a large number of people
users and the heated produced by the exercise to heat them. this means that if only a small
D machines. number of people are using the gym they can
use the same pod and will efficiently heat the
B cool external air, or air from the evaporative space instead of having one person working
cooling system when the outside air out in a huge room that they wouldn’t possible
temperature is high, will be enter the pods at be able to warm with body heat.
low level and will be warmed by the users of
A the gym [the average person gives out 100w the constant supply of cool air from either
of heat whilst exercising] and then the warm outside the building or the evaporative cooling
C air will be extracted through an extract duct system and the removal of the warm air will
at high level. the extracted air will then be keep the users of the gym at a cool temperature
utilised to heat other parts of the building and remove odours from the pods.
CINEMA
9.1 HANGING ABOVE THE MARKET
B C
a 600mm castellated steel beam 9.2 STRUCTURE - SHELL the suspended cinema structure will be beam is an appropriate solution to reduce the
b 200mm uc rolled steel ‘i’ section constructed from a steel shell. steel is very overall weight.
c steel ‘c’ section cross bracing to all bays, except; strong in tension which is important when
d steel ‘c’ section symmetrical portal bracing to bays with door openings designing a hanging structure. the series of steel rings will be braced together
using ‘c’ section steel cross bracing. every bay
the shell will be made up of a series of steel in the walls, floor and roof of the structure
rings constructed from rolled steel sections. will be braced to create a rigid structure that
the roof and floor beams which have a maximum will not deform when suspended from the steel
span of 8m will be constructed from 600mm superstructure. where openings are needed in
deep castellated beams. by cutting a standard the frame for the two entrances to the cinema
beam to create a castellated beam its depth is cross bracing will be replaced with symmetrical
almost doubled whilst its self weight remains portal bracing to allow room for the openings
the same. in the hanging structure the weight of beneath.
the structure is very important so a castellated
9.3 SUSPENDED WITHIN FRAME
C
to suspend the cinema the steel super-
structure of the building will need to be
braced. by cross bracing the bays above the
cinema the third floor structure that spans
across the void that the cinema hangs in
will effectively become a 1 storey deep beam
creating a rigid structure to suspend the
A
cinema from. a hanging structure will always
have a tendency to swing or displace under
force so the cinema structure, as well as
being hung from the structure above, will
be braced to the structure below to prevent
any movement.
F
E
G
H
I
J
K
L
A B D C K L M N O P Q
H
realistically the hall should only need to be heated for short when the external air temperature is higher or very similar to the internal
periods of time, once it is filled with over 100 people their combined temperature of the cinema then cooling using untreated external air will
body heat should keep the space at a warm temperature. the cooling not be possible. the building will use an evaporative cooling system that
system will be used to stop the cinema overheating when it is filled adds a mist of water vapour to the external air before it enters the cinema,
with people. the water vapour takes some of the heat out of the air, cooling it and
then cool air enters the cinema to cool the space. the system works much
when the external air temperature is lower than the required like the human body uses sweat to cool down, as the sweat evaporates
comfort temperature inside the building [17o - 20o] then fresh from the body it removes heat from the surface of the skin. this concept
outside air can be ventilated into the cinema space to reduce the fits with the overall concept of the building which takes ideas of energy
internal temperature. this will be ventilated at different speeds production from the movement and interaction of the human body within
depending on the relative temperatures of the external air and the it [more information on evaporative cooling is contained in the energy
internal environment - if the external air temperature is very low systems section of this report]. the high level extracts remove the air
and the hall is not at full capacity the air change in the hall will as it is warmed in the space and ensures a sufficient air flow to keep the
be lower than if the external air temperature is higher and the hall moisture in the air building up in the space.
is at capacity.
9.16 PART M
access to the cinema space will be at two
points, one at first floor level into the
bottom of the seating rake at the front of
the cinema and the other at the back of the
cinema into the top row of seating. each
floor is accessible by the lift in the building
and two ambulant disabled staircases.
removable seating
ENERGY SYSTEMS
B
10.1 THE BODY
1 force of footfall over walkway a grp mesh walkway the most common piezo electric material
2 force causes pressure pad to compress b galvanised steel c section walkway supports used is lead zirconate titanate but due to
3 piezo electric material is compressed creating c steel bearing pad bolted to; the increasing concern about the toxic
a current within the material d walkway support pressure pad properties of lead a new material developed
4 electricity output to battery store e piezo electric material in 2004, sodium potassium niobate, is being
5 sensor activates lighting at night f pressure pad bolted to steel superstructure used to replace it. this has similar properties
g electricity output to the lead compound and will be used in
h sensor output for lighting this project.
10.6 GREEN GYM - PRECEDENT through the use of dynamos it is possible the green microgym in portland has utilised
to capture the energy of a person’s gym this technology to provide some of its energy
workout. most gym equipment is based around requirement and a company called ‘plug-out’
rotating or oscillating parts which work have been developing gym equipment for both
well with dynamos. These dynamos can be the home and commercial gyms which plugs
attached to a battery which is used to store into a standard electric socket and feeds
the electricity for later use. electricity directly back into the buildings
electrical system, effectively reversing
‘a dynamo uses rotating coils of wire and the electricity meter. if you produce more
magnetic fields to convert mechanical electricity than you are using it will feed
rotation into a pulsing direct electric the electricity back into the grid. this
current through faraday’s law of induction. technology means that the equipment will
a dynamo machine consists of a stationary work straight out of the box with no retro
structure, called the stator, which provides fitting of existing electrical systems. in the
a constant magnetic field, and a set of proposed building excess energy will be
rotating coils called the armature which stored in sets of batteries in the basement
turn within that field. the motion of the wire energy store.
within the magnetic field causes the field to
push on the electrons in the metal, creating a person in decent shape can produce
an electric current in the wire.’ between 60 to 120 watts of electricity during
http://en.wikipedia.org/wiki/Dynamo strenuous exercise using this gym equipment.
10.7 ENERGY CALCULATIONS
the following calculations are a comparison the quoted energy consumption per square the cinema would only be in use for a few hours a day if the gym is open for 15 hours a day then during
between the energy that can be produced by foot per hour of assembly buildings is; when a film is showing, so this requirement will only be each hour it is open on average 20 people will need
exercise equipment fitted with a dynamo in the over a short period of time. to be using the gym to provide the energy for 2 films
gym pods and the required energy to power the 20.5 btu to be shown per day.
cinema energy production in the gym:
1 btu = 1055 joules this is achievable with the capacity of the gym but
the energy requirement for A standard building of during a hard workout one human is capable of it is possible that the gym could fall short of this
this type can be roughly calculated from available therefore, producing 120 watts. requirement.
statistics of energy use by building type available
from the ‘energy information administration; 20.5 btu = 21627.5 joules this means that the number of hours exercise required the statistics used for the calculations were based
commercial buildings energy consumption survey to create the 5,850 watts of energy required by the on a standard building. this building will be more
1999’ in the usa. to convert this to power [watts] we can use; cinema for one hour is: efficient that a standard building by using heat
recover to reduce energy consumption for heating
the survey provides information on energy power [watts] = energy [joules]/time 49 hours. which makes up for a large proportion of the power
consumption per square foot per hour for multiple [seconds] requirement.
building types. the cinema seats 126 people so at full capacity if each
power = 21627.5/3600 person using the cinema provided energy by using the by reducing the energy consumption of the cinema the
to calculate the amount of energy used by the gym they would each only have to do: required power will be significantly reduced meaning
cinema i will use the statistics for public assembly power = 6w per square foot the required energy output in the gym will be reduced.
buildings. 23 minutes of exercise per hour
converted to square metres this is; other sources of energy harvesting are also being
if the cinema is open for 3 hours [allowing 2 hours for used and tested within the building to add to the
65w per square metre a film and an hour for opening and closing] then to energy output including masks that capture the wind
power it for the entire time each person will need to do: energy from breathing, knee braces that produce
using the ‘energy administration information’ energy from the motion of the knee, urine electrolysis
data the performance venue will require 65w 69 minutes of exercise and pressure pads that produce energy under
of electrical power per square metre of the footfall.
building. so the audience will get to see a 2 hour film in turn for
just over an hours workout. the above calculations we based on purely the energy
the areas of the cinemA is: that could be harvested from using standard gym
if two films are shown in the cinema per day the cinema equipment with an added dynamo. by including all of
90 sqm will be open for 6 hours meaning to obtain its power the other technologies it is possible that the overall
requirement the number of hours exercise in the gym energy harvested in the building could come very
the total power requirement of the cinema will need to be: close the required energy input. the concept of the
would be: building is to test out these theories and developing
294 hours technologies as an experiment.
5,850 watts
‘many devices take advantage of human power capacity to
produce electricity, including hand-crank generators
as well as wind-up flashlights, radios, and mobile phone
cyclic motion cyclic motion & continuous cyclic motion & generative chargers. a limitation of these conventional methods is that
generation braking
users must focus their attention on power generation at
limb continually generator resists generator only assists the expense of other activities, typically resulting in short
accelerates [+} & acceleration & assists deceleration bouts of generation. for electrical power generation over
decelerates [-} deceleration
longer durations, it would be desirable to harvest energy
from everyday activities such as walking.’ 10.8 JOINT BRACES
max donelan, professor of kinesiology, simon fraser university
wearable components will be engineered into the
researchers from simon fraser university in british gym equipment such as braces which are worn over
columbia have developed a device which, worn much like a the moving joints whilst exercising. these braces
knee support, generates electricity from the natural motion will produce electricity whilst the exercise is being
of walking. the device harvests energy from the end of a undertaken with only a small impact on the user as
walker’s step, when the muscles are working to slow the they exercise.
movement of the leg, the biomechanical energy harvester
uses sensors and a real-time control system to assist the one such technology that has been developed at simon
hamstring muscles in slowing the knee motion. the system fraser university. the technology will be tested and
only turns on power generation at the end of the walker’s developed by edf in conjunction with them in this test
+ swing phase. building
work rate
work rate
work rate
the aluminium chassis contains a gear train converting low the graphs show a comparison between the metabolic
- velocity and high torque at the knee into the high velocity energy consumed by the body and the electric energy
and low torque for the generator A one-way roller clutch produced for three situations; without the knee brace,
allows for selective engagement of the gear train during with the knee brace generating energy in both the
knee extension only and no engagement during knee flexion. acceleration and deceleration stage of a stride and
max donelan, professor of kinesiology, simon fraser university just in the deceleration stage of a stride.
electric power
electric power
electric power
wearing a device on each leg, an individual can generate when the brace is generating energy during both stages
up to 5 watts of electricity with normal physical effort. of the stride the increase in metabolic energy used is
walking quickly, however, generates as much as 13 watts. at significant; the body will be burning a lot of energy
that rate, when the energy is stored in a battery, one minute in proportion to the electrical energy being produced.
of walking time could provide enough electricity to sustain this is because the wearer has to fight against the force
30 minutes of talk-time on a mobile phone. of the generator when they accelerate their leg at the
beginning of a stride. they will notice a considerable
energy
additional energy
additional energy
people are an excellent source of portable power, an difference; they will have to exert more effort into
average-sized person stores as much energy in fat as a taking each stride.
1,000 kg battery. people recharge their ‘body batteries’
with food and, lucky for us, there is about as much useful when the brace is just producing electricity during the
energy in a 35-gram granola bar as in a 3.5 kg lithium-ion deceleration stage it is actually aiding the deceleration,
battery. the only increase in metabolic energy used is due to
max donelan, professor of kinesiology, simon fraser university the extra weight of the brace on the leg as the wearer
walks. although the generator will only produce
the device comprises an aluminium chassis and generator half the amount of electricity the additional energy
mounted on a customized orthopaedic knee brace. with one consumed by the body is greatly reduced making this
metabolic metabolic electric metabolic electric worn on each leg, its total mass is 1.6 kg but the developers the most efficient configuration. this was the aim of the
are working on using lighter weight materials, such as brace; to produce as much energy as possible without
carbon fibre to bring this down. effecting the mobility of the wearer; a passive system.
10.9 MASKS
us researchers have developed an efficient the process of electrolysis of urine the main component of urine is urea which currently there is no efficient way to remove
way of producing hydrogen from urine - a releases hydrogen atoms which can then be contains four hydrogen molecules. the urine from water and other waste when it
feat that could not only fuel the cars of captured and burnt in a combustion chamber important factor in urea is that the hydrogen is flushed in a standard toilet. until these
the future, but could also help clean up to produce large amounts of energy. the use molecules are bond less strongly than in systems are developed the urine will only
municipal wastewater. of hydrogen fuel has already bee proven water meaning less energy is required to be be harvested from waterless urinals in the
by its use as a fuel for vehicles. burning input into the electrolysis process than in male wcs. this will produce relatively small
using hydrogen to power cars has become an of hydrogen can produce large amounts of the electrolysis of water. quantities of hydrogen but this technology
increasingly attractive transportation fuel, energy which can be converted into electrical will be used as more of an experiment to
as the only emission produced is water - but a energy to power the building. during the electrolysis process inexpensive develop the system within the building. the
major stumbling block is the lack of a cheap, nickel based electrodes. during the process hydrogen that is created will be burnt in
renewable source of the fuel. gerardine hydrogen has to be produced in its elemental hydrogen is given off at the cathode which a specialist hydrogen boiler that will in
botte of ohio university may now have found state from its compounds that occur natural. can be collected and burnt to generate turn be used to power turbines and create
the answer, using an electrolytic approach the most common processes to obtain electricity. carbon dioxide is produced during electricity which will be used by the rest of
to produce hydrogen from urine - the most hydrogen are the electrolysis of water the reaction but this reacts with potassium the building
abundant waste on earth - at a fraction of which requires relatively large amounts of hydroxide in the electrolyte solution to
the cost of producing hydrogen from water. energy to be input and the steam reforming produce potassium carbonate. other waste
royal society of chemistry, http://www.rsc.org, of methane but this process produces both products are nitrogen and oxygen which
july 2009 carbon dioxide and carbon monoxide which both occur naturally in the atmosphere.
are harmful to the environment.
urine also contains phosphorous which acts
the electrolysis of urine has been developed as a fertiliser, once the electrolysis has
in the past few years and is being identified been completed the phosphorous left in the
as a more efficient and environmentally solution can be used as a fertiliser in the
friendly process for creating hydrogen. greenhouses.
10.11 COOLING
f the heating system of using body heat the filter pads also have the benefit of filtering
collected in the gym and a heat exchanger out small particles including dust and pollen
has already been discussed in previous parts which will be beneficial in the urban environment
of this report. of the site giving a better air quality within the
building. the pads last up to 5 years but the
when the outside air temperature is lower system needs to be cleaned every 6 months.
than the inside air temperature cool fresh
air will be mechanically ventilated into the the energy required to run the system is 90% less
gym and cinema spaces to provide space than the energy required for air conditioning
e cooling but when the outside air temperature units. they use just 20 watts of electricity - when
is similar or high than the required internal you consider that a single person working out in
comfort level than another system will be the gym will be outputting 120 watts of power
b d used. this system will use a very small fraction of the
a energy that is being created in the building.
C the ventilation system will use evaporative
cooling to effectively ‘sweat’ when there is a the system will work well in the uk climate as it
high external air temperature. this will mimic works well in temperature climates which have
the action of the human body, when it needs a low humidity when the outside air temperature
a warm external air drawn in mechanically to cool down we sweat and in the process is hot. if the outside air is of a high humidity
b warm air passes through moist filter pads of evaporating it extracts heat from the such as in tropical climates the system is very
c evaporative process removes heat from the air surface of our skin. inefficient at cooling the air.
d filter pads remove dust and pollen particles
e cooled air enters internal spaces at low level an evaporative cooling system works by the system will slightly raise the humidity of
f high level mechanical extract draws moist air out passing the external air through a series of the internal environments but the levels will be
of the building moist filter pads, as the water in the pads unnoticeable to the users of the building and
evaporates it takes heat from the air reducing by providing a sufficient number of air changes
its temperature. this air then enters the within the internal spaces by mechanically
building at a lower temperature providing extracting the air no humidity will build up within
the required cooling. the structure.
10.12 FIRE PERFORMANCE
the cinema construction, pods and basement corridor will all be 1 hour
fire rated construction. the basement corridor will be a protected
corridor providing escape from the basement. each room in the basement
is accessed directly from the protected corridor, there are no internal
rooms. the partitions between the plant rooms also be will be 1 hour
fire rated to prevent the spread of fire from these high risk areas.
smoke vents activated by the fire alarm system will open to vent the
basement at the external walls if there is a fire.
the ground floor and circulation above is all external space, the
circulation zone in the centre of the building will allow smoke a free
path to rise straight out of the building , not collecting anywhere.
all the circulation including the two stairs located at either end of
the building providing two escape routes is external. the circulation
walkways will be constructed from a grp mesh which is more stable and
retains its structural integrity better than a standard galvanized steel
mesh. to protect the circulation space from fire spread the individual
gym pods and cinema structure will provide 1 hour fire protection,
where possible smoke vents of the cinema and pods will vent to the outer
perimeter of the site to reduce the amount of smoke in the circulation
space. each pod will be 1 hour fire protected and the kalwall panels
are constructed from a thermoset plastic which will not melt, drip or
shatter when exposed to fire.
all the steelwork will be painted with intumescent paint giving it the
required protection from fire.
1 hour fire rated construction
smoke ventilation