Urgent by Fax JODHPUR VIDHYUT VITRAN NIGAM LIMITED OFFICE OF SUPERINTENDING ENGINEER (RA&C)

No. JdVVNL/MD/CE(HQ)/SE(RA&C)/Ju/S.AAE(C) /2k11-12/D. Dt.

The Superintending Engineer(CC/DC/O&M), Jodhpur Discom, Jodhpur/Pali/Barmer/Jalore/ Bikaner/Sriganganagar/Hanumangarh/Churu. Sub.: Regarding detail of pending new & load extention applications for HT category. On the subject cited above, I am directed to enquire the status of pending HT new connection & load extention applications. As such, while enclosing the format for the desired information you are requested to kindly intimate the same by 5 th (detail as on end of previous month) & 20th (detail as on 15th of each month) day of each month, so that same may be apprised to higher authorities. Kindly treat it as urgent. Encl.: Format (MOHAMMED IQBAL) SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR Copy submitted to the Zonal Chief Engineer(O&M-JDZ/BKZ), Jodhpur Discom, Jodhpur/Bikaner for information and needful action. SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR

G:pending new

Urgent by Fax JODHPUR VIDHYUT VITRAN NIGAM LIMITED OFFICE OF SUPERINTENDING ENGINEER (RA&C)
No. JdVVNL/MD/CE(HQ)/SE(RA&C)/Ju/S.AAE(C) /2k11-12/D. Dt.

The Superintending Engineer(O&M), Jodhpur Discom, Bikaner/Churu. Sub.: Regarding pending new & load extension applications for HT category. Ref: Letter No.1229 dtd 09.06.11 of Zonal Chief Engineer(O&M-BKZ), Jodhpur Discom, Bikaner. While observing the information regarding subject cited above as send by Zonal Chief Engineer(O&M-BKZ), Jodhpur Discom, Bikaner vide letter under reference, it has been observed that estimate for some of the connections are pending beyond the permissible time limit as prescribed by RERC in TCOS-2004/Standard of Performance and DN has not been issued even after lapse of more than 3 months. As such, you are requested to kindly look into the matter personally and arrange to get released the connections within the specified time period as specified by Honble Commission. (MOHAMMED IQBAL) SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR Copy submitted to the Zonal Chief Engineer(O&M-BKZ), Jodhpur Discom, Bikaner for information and needful action. SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR

G:pending new

Urgent by Fax JODHPUR VIDHYUT VITRAN NIGAM LIMITED OFFICE OF SUPERINTENDING ENGINEER (RA&C)
No. JdVVNL/MD/CE(HQ)/SE(RA&C)/Ju/S.AAE(C) /2k11-12/D. Dt.

The Superintending Engineer(CC/DC/O&M), Jodhpur Discom, Jodhpur/Pali/Barmer/Jalore/ Bikaner/Sriganganagar/Hanumangarh/Churu. Sub.: Regarding detail of pending new & load extention applications for MIP & HT category. Ref: This office letter No.901 dtd 08.06.11 In continuation to this office letter under reference, vide which you were requested to send the status of pending HT new connection & load extention applications. In this context, the detail of MIP consumers has also been desired by higher authorities. As such, while enclosing the new format for the desired information you are requested to kindly intimate the same by 5 th (detail as on end of previous month) & 20th (detail as on 15th of each month) day of each month, so that same may be apprised to higher authorities. The position as on today be send today itself, by fax(0291-5106366), for appraisal. Kindly treat it as urgent. Encl.: Format (MOHAMMED IQBAL) SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR Copy submitted to the Zonal Chief Engineer(O&M-JDZ/BKZ), Jodhpur Discom, Jodhpur/Bikaner for information and needful action. SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR Urgent by Fax
G:pending new

JODHPUR VIDHYUT VITRAN NIGAM LIMITED OFFICE OF SUPERINTENDING ENGINEER (RA&C)


No. JdVVNL/MD/CE(HQ)/SE(RA&C)/Ju/S.AAE(C) /2k11-12/D. Dt.

The Superintending Engineer(CC/DC/O&M), Jodhpur Discom, Jodhpur/Pali/Barmer/Jalore/ Bikaner/Sriganganagar/Hanumangarh/Churu. Sub.: Regarding pendency of new & applications for MIP & HT category. load extension

While observing the status of pending new & load extension cases, a serious view has been taken by higher authorities regarding delay in releasing of the same. As such, you are requested to kindly monitor the status personally and instruct the concerns to get release the connections within the specified time period, as specified by Honble Commission and circulated vide booklet Standard of Performance and TCOS-2004. The copy of the relevant section is enclosed herewith for your ready reference. Encl: As above. (MOHAMMED IQBAL) SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR Copy submitted to the Zonal Chief Engineer(O&M-BKZ), Jodhpur Discom, Bikaner for information and needful action. SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR

G:pending new

JODHPUR VIDHYUT VITRAN NIGAM LIMITED


No. JdVVNL/MD/CE(HQ)/SE(RA&C)/Ju/S.AAE(C) /2k11-12/D. Dt.

The Superintending Engineer(CC/DC/O&M), Jodhpur Discom, Jodhpur/Pali/Barmer/Jalore/ Bikaner/Sriganganagar/Hanumangarh/Churu. Sub.: Regarding pendency of new & applications for MIP & HT category. load extention

While observing the information regarding subject cited above, it has been observed that many connections are pending due to non-submission of L form/any other document by consumer. In this context, it is clarified that as per the provisions mentioned at Clause-4(5) of TCOS-2004 the applicant has to submit L form at the time of application. However, in case of HT connection, L form may be furnished later but before release of connection. It has also been mentioned at Clause-4(10) of TCOS-2004(amendment issued vide Comml.JDP/420) that, The Nigam will provide the receipt of the application/L form received from the applicant. In case deficiency or incomplete application, the Nigam, within seven days of the receipt of application, shall inform the applicant of the deficiency, including nonattachment of L-Form. If the deficiency is not removed by the applicant within 30 days from the date of receipt of such intimation by the applicant, the application will stand cancelled and the application fee forfeited. In this context, you are advised to ensure that such type of deficiency checked at the time of application, as any delay badly reflects the image of Nigam and also there is a great loss of revenue to the Nigam.

(D.C.BHURAT) CHIEF ENGINEER(HQ) JODHPUR DISCOM, JODHPUR Copy submitted to the Zonal Chief Engineer(O&M-JDZ/BKZ), Jodhpur Discom, Jodhpur/Bikaner for information and needful action. CHIEF ENGINEER(HQ) JODHPUR DISCOM, JODHPUR

G:pending new

JODHPUR VIDHYUT VITRAN NIGAM LIMITED OFFICE OF SUPERINTENDING ENGINEER (RA&C) No. JdVVNL/MD/CE(HQ)/SE(RA&C)/Ju/S.AAE(C) /2k11-12/D.

Dt.

The Superintending Engineer(CC), Jodhpur Discom, Jodhpur. Sub.: Regarding pending new & load extension applications for HT & MIP category. Ref: Your office letter No.1158 dtd 16.06.11. While observing the information regarding subject cited above as received vide letter under reference, it has been observed that DN for some of the connections are pending beyond the permissible time limit as prescribed by RERC vide Standard of Performance. S.No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Name of Consumer M/s Hindustan Gum & Chemical, Basni M/s Ganga Arts, Boranada M/s Indigo Paints, Boranada M/s Rawat Steel, Boranada M/s Geeta Handicraft, Boranada M/s Shree Nath Dye Chem, Basni M/s Angeera Timber, Basni M/s Angira Ind., Basni M/s Balaji Art Craft, Sangaria M/s Nakoda Spat Mental, Sangaria M/s Christater Ind., Sangaria M/s Shree Om Agro Products, Boranada M/s Nutritions Agro Food Product, Boranada M/s Rajasthan Gum Pvt. Ltd., Boranada Dt. of Application 25.04.11 26.04.11 04.05.11 04.05.11 09.05.11 03.05.11 11.05.11 11.05.11 12.01.11 19.01.11 23.03.11 31.03.11 21.04.11 10.02.11

As such, you are requested to kindly look into the matter personally and arrange to get released the connections within the specified time period as specified by Honble Commission. (MOHAMMED IQBAL) SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR Copy submitted to the Zonal Chief Engineer(O&M-JDZ), Jodhpur Discom, Jodhpur, for information and needful action. SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR

G:pending new

JODHPUR VIDHYUT VITRAN NIGAM LIMITED OFFICE OF SUPERINTENDING ENGINEER (RA&C)


No. JdVVNL/MD/CE(HQ)/SE(RA&C)/Ju/S.AAE(C) /2k11-12/D. Dt.

The Superintending Engineer(DC/O&M), Jodhpur Discom, Jodhpur/Pali/Jalore/Barmer Bikaner/Sriganganagar/Churu. Sub.: Regarding pending new & load extension applications for HT & MIP category. Ref: Your information as on dtd 15.06.11.

While observing the information regarding subject cited above as received vide letter under reference, it has been observed that DN for some of the connections are pending beyond the permissible time limit as prescribed by RERC vide Standard of Performance.

As such, you are requested to kindly look into the matter personally and arrange to get released the connections within the specified time period as specified by Honble Commission. (MOHAMMED IQBAL) SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR Copy submitted to the Zonal Chief Engineer(O&M-JDZ/BKZ), Jodhpur Discom, Jodhpur/Bikaner, for information and needful action. SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR

G:pending new

JODHPUR VIDHYUT VITRAN NIGAM LIMITED OFFICE OF SUPERINTENDING ENGINEER (RA&C)


No. JdVVNL/MD/CE(HQ)/SE(RA&C)/Ju/S.AAE(C) /2k11-12/D. Dt.

The Superintending Engineer(CC/DC/O&M), Jodhpur Discom, Jodhpur/Pali/Jalore/Barmer Bikaner/Sriganganagar/Churu. Sub.: Regarding pending new & load extension applications for HT & MIP category. Ref: Your information as on dtd 15.06.11.

While observing the status of pending new & load extension cases, a serious view has been taken by higher authorities regarding delay in releasing of the connections. In this context, I am directed to enquire the name of officers/official, on whom part the delay has occurred. As such, you are requested to kindly intimate the name of such officers/officials within a period of seven days, for further needful at this end.

(MOHAMMED IQBAL) SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR Copy submitted to the Zonal Chief Engineer(O&M-JDZ/BKZ), Jodhpur Discom, Jodhpur/Bikaner, for information and needful action. SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR

G:pending new

Details of delay in new/load extension application of MIP & HT category


Information as on 15.06.11

Jodhpur Zone, SE(CC), Jodhpur


S.No. Name of Consumer 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 Dt. of Dt of Application DN M/s Hindustan Gum & 300 to 450HP, CD 25.04.11 Chemical, Basni 225 to 390KVA M/s Ganga Arts, Boranada 59 to 90HP 26.04.11 M/s Indigo Paints, CD 80 to 125 KVA 04.05.11 Boranada M/s Rawat Steel, Boranada 15 to 100 HP 04.05.11 M/s Geeta Handicraft, 20 to 59 HP 09.05.11 Boranada M/s Shree Nath Dye 24 to 70 HP 03.05.11 Chem, Basni M/s Angeera Timber, 24 to 35 HP 11.05.11 Basni M/s Angira Ind., Basni 24 to 40 HP 11.05.11 M/s Balaji Art Craft, 25 to 59 HP 12.01.11 Sangaria M/s Nakoda Spat Mental, 5 to 40 HP 19.01.11 Sangaria M/s Christater Ind., 25 to 150HP CD 23.03.11 Sangaria 125KVA M/s Shree Om Agro 1200HP CD 31.03.11 Products, Boranada 1000KVA M/s Nutritions Agro Food 400 HP 21.04.11 Product, Boranada M/s Rajasthan Gum Pvt. 4350 HP CD 10.02.11 Ltd., Boranada 2400KVA M/s G.G.Udhyog, Basni 70 HP 16.12.10 12.01.11 M/s Vinay Udhyog 35 HP 31.03.11 04.04.11 M/s Pawan Putra Ind. 25 to 40HP 17.01.11 15.02.11 Basni M/s M.Y. Textiles Basni 47 to 57 HP 25.01.11 25.01.11 M/s Dungar Ram Pal 14.7 to 35 HP 23.12.10 14.02.11 M/s India Art & 40 to 50 HP 22.10.10 08.11.10 Emporium M/s Parag Products 59 to 125 HP 17.01.11 08.03.11 M/s Hanuman Industries 59 to 125 HP 07.03.11 11.03.11 Applied Load Dt of SCO -

Job Job Job Job Job Job Job Job

G:pending new

Details of delay in new/load extension application of MIP & HT category


Information as on 15.06.11

Jodhpur Zone, SE(DC), Jodhpur

S.No. Name of Consumer 1 2 3 4 5 6 7 8 9 10

Applied Load Dt. of Application M/s Baba Ramdev Chem 550HP 19.11.10 M/s PHED 360KW 22.02.07 M/s PHED XEN DDI 1394KW 22.02.07 M/s PHED XEN DDI 484KW 22.02.07 M/s AEN PHED 310 KW 25.02.10 M/s AEN PHED 600 KW 31.12.10 M/s AEN PHED 160 KW 31.12.10 M/s AEN PHED 160 KW 05.01.11 M/s AEN PHED 160 KW 06.01.11 M/s AEN PHED 160 KW 31.12.10

Dt of DN 03.05.11 28.03.07 28.03.07 28.03.07 05.03.10 Tech.San. T.S. T.S. T.S. T.S.

Dt of SCO 25.05.11 Job Job Job Job

Jodhpur Zone, SE(O&M), Jalore


1 M/s Narpat Singh 59 HP 21.04.11 2 M/s Shree Ganesh Granite, Jalore 25 to 60HP 26.04.11 3 M/s Ratneshwar Ind. 60 to 120 HP 05.05.11

G:pending new

Details of delay in new/load extension application of MIP & HT category


Information as on 15.06.11

Jodhpur Zone, SE(O&M), Pali


S.No. Name of Consumer 1 2 3 4 5 6 7 8 9 10 11 12 Applied Load Dt. of Application 03.05.10 14.09.10 14.09.10 29.09.10 13.04.11 06.09.10 28.12.10 23.12.10 18.04.11 15.03.11 11.03.11 17.03.11 26.04.11 14.01.11 Dt of Dt of DN SCO 03.09.10 L form PPM to TCC

M/s Shiv Agrico, Rani 250 HP M/s Panchsil Globe, Abu 10 MW Road M/s J.B.Licene Steel, Abu 25 MW Road M/s Gulsan Polymers, Abu 2000 KVA Road M/s Puran Prakash, Pali 59 to 85 HP M/s Sharda Udhyog, Pali 1350 to 1485 HP M/s Ma Kripa Ind., Pali 55 to 80 HP M/s Shree Nath Minerals, 59 to 120 HP Sojat City M/s Shiv Jyoti P Ltd. 22 HP to 400KVA M/s Minerals Orientals, 125 to 200 HP Reodar M/s Shiv Marbles, Reodar 59 to 150 HP M/s Shri Nath Stone Crusher, 59 to 175 HP Reodar

Job

Jodhpur Zone, SE(O&M), Barmer


1 2 3 4 5 6 M/s Hukma Ram, Guda M/s Raj Minerals, Barmer M/s Ganpati Plaster, Baytoo M/s Valkoo Jaisalmer Road, Barmer M/s Karni Marbel, Barmer M/s Rajwest Power 45 HP 59 HP 35 HP 50 to 149 HP 40 to 59 HP 4MVA 13.10.10 04.02.11 15.03.10 07.01.11 15.02.11 16.11.10 25.02.11 17.03.11 21.05.10 Job Job 04.01.11

G:pending new

Details of delay in new/load extension application of MIP & HT category


Information as on 15.06.11

Bikaner Zone, SE(O&M), Bikaner


S.No. Name of Consumer 1 2 3 4 5 6 7 Applied Load M/s Welcome Oxizen Ind., 325 Salasar M/s Anupurna Ind. Godwala 400 M/s Sipani Woolen Pvt. Ltd., 200 Palana M/s Balaji Woolen Textile, 59 Bikaner M/s Quartz India, Bikaner 59 M/s Balaji Mines & Minerals, 59 Bikaner M/s Agarwal Packaging, 50 to 80 Bikaner Dt. of Dt of DN Application 15.03.11 12.07.10 28.03.11 05.05.11 02.05.11 04.05.11 03.05.11 Dt of SCO

Bikaner Zone, SE(O&M), Sriganganagar


1 M/s Mani Ram, Keshrisinghpur 59 to 70 HP 20.01.11 2 M/s GE Army, 2440 to 4900KVA 18.09.09 3 M/s Gurmel Singh, Raisinghpur 20 to 80HP 27.12.10 23.03.11 Job

Bikaner Zone, SE(O&M), Churu


1 2 3 4 5 6 7 8 9 M/sXEN(PHED), Ratangarh M/s Balaji Stone Ind., Bidasar M/s Minral Plaster, Sardarsahar M/s Shri Ram Gril Udhyog, Rajaldesar M/s Kanhaya Lal, Ladnun M/s Kishan Lal Ladnun M/s Ganesh Repairing, Ladnun M/s Laxmi Crusher Udhyog, Sujangarh M/s Ganga Crusher, Ladnun 2500 HP 55 HP 59 HP 150HP 24 to 59 HP 20 to 40 HP 44 to 132HP 120 to 250 HP 120 to 220 HP 27.02.11 21.10.10 02.01.11 30.01.11 30.06.10 03.03.11 02.03.11 30.03.11 15.12.10 26.11.10 02.06.11 31.05.11 Job

Bikaner Zone, SE(O&M), Hanumangarh Nil

G:pending new

As per Standard of performance Regulation, 2003 issued by RERC

DN to be issued for load up 60 HP Loads 60HP to 300 KW(402 HP)

21 days

G:pending new

Urgent by Fax JODHPUR VIDHYUT VITRAN NIGAM LIMITED OFFICE OF SUPERINTENDING ENGINEER (RA&C)
No. JdVVNL/MD/CE(HQ)/SE(RA&C)/Ju/S.AAE(C) /2k11-12/D. Dt.

The Superintending Engineer(CC/DC/O&M), Jodhpur Discom, . Sub.: Regarding detail of pending new & load extention applications for MIP & HT category. Ref: This office letter No.1014 dtd 15.06.11 On the subject captioned above and this office letter under reference, vide which you were requested to send the status of pending HT & MIP category new connection & load extention applications by 5 th (detail as on end of previous month) & 20th (detail as on 15th of each month) day of each month. The desired information as on 30.06.11 has not been received till date, as such you are again requested to kindly arrange to send the same today itself, by fax(0291-5106366), for appraisal. Kindly treat it as urgent. (MOHAMMED IQBAL) SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR Copy submitted to the Zonal Chief Engineer(O&M-JDZ/BKZ), Jodhpur Discom, Jodhpur/Bikaner for information and needful action. SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR

G:pending new

Details of delay in new/load extension application of MIP & HT category


Information as on 15.07.11

Jodhpur Zone, SE(CC), Jodhpur


S.No. Name of Consumer 1 M/s Hindustan Gum & Chemical, Basni M/s Angeera Timber, Basni M/s Angira Ind., Basni M/s Balaji Art Craft, Sangaria M/s Nakoda Spat Mental, Sangaria M/s Dungar Ram Pal M/s Indra Art & Emp M/s Parag Product M/s Prakash Stone M/s Bhawal Export M/s S.K.Stone M/s Sun Moon Stone M/s Radiant Stone M/s Mahaveer Sand stone M/s Mukal Stone M/s Champa Lal M/s Shanti Enterprises M/s Shree Ram Agro M/s Quart N Craft M/s Richa Textile M/s Tak Udhyog M/s Hanuman Ind. M/s Veenith Oil Ind Boranada Applied Load Dt. of Dt of Dt of Remarks Application DN SCO 300 to 450HP, 25.04.11 24.06.11 CD 225 to 390KVA 24 to 35 HP 11.05.11 12.07.11 24 to 40 HP 25 to 59 HP 5 to 40 HP 14.7 to 35 HP 40 to 50 HP 59 to 125 HP 59 HP 18 to 59 HP 59 HP 59 HP 59 HP 59 HP 59 HP 59 HP 150 to 250HP 50 to 85 HP 25 to 45 HP 70 to 150 HP 11.05.11 12.01.11 19.01.11 23.12.10 22.10.10 17.01.11 27.10.10 03.03.11 21.12.10 28.01.11 09.03.11 11.05.11 17.05.11 31.05.11 01.06.11 10.02.11 08.04.11 17.03.11 08.03.11 03.05.11 02.05.11 03.05.11 11.03.11 28.04.11 24.06.11 CTPT req. 22.06.11 MIP box 15.06.11 CTPT req 26.05.11 MIP box Job 26.05.11 Not rele. 12.07.11 27.06.11 13.06.11 14.02.11 08.11.10 08.03.11 13.12.10 08.03.11 15.02.11 15.02.11 13.04.11 12.07.11 Not released Job Job Job 07.06.11 Not 25.05.11 released Job Job Job

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

20 to 45 HP 18.04.11 59 to 125 HP 07.03.11 10 to 630 HP 14.03.11 CD 460KVA

G:pending new

Details of delay in new/load extension application of MIP & HT category


Information as on 15.07.11

Jodhpur Zone, SE(DC), Jodhpur


S.No. Name of Consumer 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 M/s PHED XEN DDI M/s AEN PHED M/s AEN PHED M/s AEN PHED M/s AEN PHED M/s AEN PHED M/s AEN PHED M/s Dinesh Fregrance M/s Contemparary Furnitures M/s Manidhari Gums and Chem M/s AEN PHED Osian M/s AEN PHED Osian M/s AEN PHED Baori M/s K.D. Stone M/s Mahadev Stone M/s Jakhar Stone M/s Santosh Stone M/s Bheru Singh M/s Inder Singh M/s Om Stone M/s Hawa Kanwar M/s Sona Textile M/s A.B.Block & Brick M/s Laxmi Stone Works Applied Load 1394KW 310 KW 600 KW 160 KW 150 KW 150 KW 160 KW 25 to 300 HP 15 to 200 HP 10 to 500HP 60KW 80 KW 100KW 42 HP 59 HP 59 HP 59 HP 59 HP 30 HP 59 HP 59 HP 30 to 49 HP 48 to 132 HP 25 to 55 HP Dt. of Dt of DN Application 22.02.07 28.03.07 25.02.10 31.12.10 31.12.10 05.01.11 06.01.11 31.12.10 15.12.10 12.01.11 08.03.11 29.12.10 06.01.11 31.12.10 09.12.10 21.12.10 24.11.10 28.12.10 10.03.11 13.04.11 21.04.11 04.05.11 29.12.10 28.02.11 15.11.10 05.03.10 Dt of Remarks SCO Job Job Tech.San T.S. T.S. T.S. T.S. Under sanction Job Under sanction Under sanction Under sanction Under sanction

30.05.11

08.03.11

Job

06.07.11 29.06.11

Job Job Under san

G:pending new

Jodhpur Zone, SE(O&M), Jalore


S.No. 1 2 Name of Consumer M/s Narpat Singh M/s Mamta Polymers Applied Load 59 HP 47.5 HP

Information as on 15.07.11

Dt. of Dt of DN Dt of Remarks Application SCO 21.04.11 07.10.10 09.11.10 18.01.11 (fitting not complete)

In the information of Jalore Circle for many applications it has been mentioned that factory construction work not completed. In many case the Job order not completed even than have requested that transformer, meter, meter box required. Details of delay in new/load extension application of MIP & HT category
Information as on 15.07.11

Jodhpur Zone, SE(O&M), Pali


S.No. Name of Consumer 1 2 3 4 5 6 7 8 9 10 11 12 12 13 M/s Shiv Agrico, Rani M/s Panchsil Globe, Abu Road M/s J.B.Licene Steel, Abu Road M/s Varun Ind M/s Gulsan Polymers, Abu Road M/s Puran Prakash, Pali M/s Sharda Udhyog, Pali M/s Shiv Jyoti P Ltd. M/s Minerals Orientals, Reodar M/s Shiv Marbles, Reodar M/s R.K. International, Falna M/s Bhavika Ispat, Rani M/s Khandelwal Minerals M/s Parswanath Ent Applied Load 250 HP 10 MW 25 MW 16.825 MW 2000 KVA 59 to 85 HP 1350 to 1485 HP 22 HP to 400KVA 125 to 200 HP 59 to 150 HP 95 HP Dt. of Dt of DN Appl. 03.05.10 03.09.10 14.09.10 14.09.10 15.02.11 29.09.10 13.04.11 06.09.10 18.04.11 15.03.11 11.03.11 04.04.11 16.06.11 16.06.11 13.07.11 Under Estimate L form pending Job Dt of Remarks SCO Job PPM to TCC PPM to TCC PPM to TCC 20.06.11 06.07.11 PPMb Under Sanction

124 to 149 04.05.11 HP 400 HP 29.03.11 56 to 95 HP 18.05.11

04.04.11

G:pending new

Details of delay in new/load extension application of MIP & HT category


Information as on 15.07.11

Jodhpur Zone, SE(O&M), Barmer


S.No. Name of Consumer 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Applied Load M/s Hukma Ram, Guda 45 HP M/s Ramasar Stone 59 HP Crusher, Barmer(R) M/s Ganpati Plaster, 35 HP Baytoo M/s Valkoo Jaisalmer 50 to 149 Road, Barmer HP M/s Karni Marbel, 40 to 59 Barmer HP M/s Rajwest Power 4MVA M/s Vimloxi Products 40 HP M/s Mahadev Minerals, 85 HP Baytoo M/s Pooniya Minerals, 94 HP Baytoo M/s Khiljee Ice, Barmer 59 to 149 HP M/s Nakoda Minerals 55 HP M/s Mahadev Minerals, 75 HP Bhadkha, Baytoo M/s Laxmi Granite, 59 to 350 Jaisalmer M/s R.K.Stone 59 HP M/s Jaishree/Gopal Das 59 HP M/s Balaji Granite 59 HP M/s Neelkanth Granite 59 HP M/s Kohinoor Shilpgram 106 to 166 HP Dt. of Application 13.10.10 24.05.10 15.03.10 07.01.11 15.02.11 16.11.10 20.05.11 18.04.11 27.04.11 05.07.10 11.10.10 05.01.11 15.11.10 22.02.11 08.02.11 12.10.10 20.04.11 04.06.10 18.11.10 30.12.10 02.02.11 12.05.11 21.03.11 27.05.11 31.12.10 20.05.11 30.12.10 27.06.11 Not rele. Job 26.06.11 Not rele. 11.06.11 Not rele. Job 06.01.11 09.04.11 21.06.11 Dt of Dt of Remarks DN SCO 25.02.11 Job 14.08.10 07.02.11 21.05.10 04.01.11

02.02.11

24.02.11

G:pending new

Details of delay in new/load extension application of MIP & HT category


Information as on 15.07.11

Bikaner Zone, SE(O&M), Bikaner


S.No. Name of Consumer 1 2 3 4 5 6 7 8 9 10 11 Applied Load M/s Welcome Oxizen 325 Ind., Salasar M/s Anupurna Ind. 400 Godwala M/s Gajanand Sunder 59 lal M/s Balaji Woolen 59 Textile, Bikaner M/s Maheswari Ind., 37 to 59 Napasar HP M/s Balaji Mines & 59 Constr., Bikaner M/s Agarwal Packaging, 50 to 80 Bikaner M/s National Ind. 20 to 110 J.K. Industires KIA Dt. of Dt of DN Application 15.03.11 12.07.10 03.03.11 05.05.11 30.04.11 04.05.11 03.05.11 16.05.11 09.06.11 24.05.11 30.06.11 13.07.11 Under Estimate Under sanction Under sanction Under sanction Dt of Remarks SCO Under sanction

35 to 59 26.05.11 HP M/s Shyam Sweet KIA 25 To 24.02.11 BKN 35 HP M/s Bansal Udhyog 35 HP 06.07.11

Under Sanction Under Estimate

Bikaner Zone, SE(O&M), Sriganganagar


S.No. Name of Consumer 1 2 3 4 5 6 Applied Load M/s Mani Ram, 59 to 70 Keshrisinghpur HP M/s GE Army, 2440 to 4900KVA M/s Gurmet Singh, 20 to Raisinghpur 80HP M/s Rajesh Kumar/ 22 to 55 Harbans Lal HP M/s Mahipal Food 80 to 250 HP M/s M.D. Industries 301 HP 170 KVA Dt. of Dt of DN Dt of Remarks Application SCO 20.01.11 Notice for CD 18.09.09 23.03.11 Job 27.12.10 01.03.11 01.02.11 19.11.10 14.06.10 07.03.11 10.01.11 Under sanction L form due L form 27.06.11 Job issued on21.06.11

G:pending new

Details of delay in new/load extension application of MIP & HT category


Information as on 15.07.11

Bikaner Zone, SE(O&M), Churu


S.No. Name of Consumer 1 2 3 4 5 6 7 8 9 10 M/sXEN(PHED), Ratangarh M/s Shri Ram Grit Udhyog, Rajaldesar M/s Farien Ind. Khanpur M/s Ganpati Marble, Charwas M/s Kanhaya Lal, Ladnun M/s Kishan Lal Ladnun M/s Ganesh Repairing, Ladnun M/s Laxmi Crusher Udhyog, Sujangarh M/s Ganga Crusher, Ladnun M/s Pawan Crusher, Sarothia Applied Load 2500 HP 150HP 59 HP 150 HP 24 to 59 HP 20 to 40 HP 44 to 132HP 120 to 250 HP 120 to 220 HP 140 to 200 HP Dt. of Dt of DN Appl. 27.02.11 30.01.11 20.05.11 24.06.10 30.06.10 03.03.11 02.03.11 30.03.11 15.12.10 11.05.11 06.07.11 21.07.11 Blue print not provide Under sanction Under Estimate Under Estimate 31.05.11 Dt of Remarks SCO Under sanction Job Estimate Revised estimate Blue print not provide

28.10.10

Bikaner Zone, SE(O&M), Hanumangarh Nil

G:pending new

Details of delay in release of new/load extension application of MIP & HT category


Information as on 15.07.11

SE(M&P), Jodhpur
S.No. Name of Consumer 1 2 3 4 5 6 7 8 9 10 M/s Tak Udhyog, Basni M/s Prakash Stone, Basni M/s Veenith Oil, Basni Applied Dt. of Load Application 20 to 45 18.04.11 HP 59 HP 27.10.10 630 14.03.11 59 03.03.11 85 10.02.11 45 08.04.11 150 17.03.11 22.02.11 12.10.10 20.04.11 Dt of Dt of Remarks DN SCO 03.05.11 26.05.11 13.12.10 28.04.11 08.03.11 08.03.11 03.05.11 02.05.11 21.03.11 31.12.10 20.05.11 07.06.11 26.05.11 25.05.11 25.05.11 22.06.11 MIP box req 15.06.11 CTPT req 27.06.11 26.06.11 11.06.11

10 to HP M/s Bhawal Export, 18 to NPH HP M/s Shree Ram Agro 59 to Product, Boranada HP M/s Quart N Craft, 25 to Boranada HP M/s Richa Textile, 70 to Basni HP M/s R.K.Stone, 59 HP Jaisalmer M/s Balaji Granite, 59 HP Jaisalmer(R) M/s Neelkanth Granite, 59 HP Pokran

G:pending new

Urgent by Fax JODHPUR VIDHYUT VITRAN NIGAM LIMITED OFFICE OF SUPERINTENDING ENGINEER (RA&C)
No. JdVVNL/MD/CE(HQ)/SE(RA&C)/Ju/S.AAE(C) /2k11-12/D. Dt.

The Superintending Engineer(CC/DC/O&M), Jodhpur Discom, . Sub.: Regarding detail of pending new & load extention applications for MIP & HT category. Ref: This office letter No.1081 dtd.20-06-11, 1095 dtd.22-06-11, 1096 dtd.22-06-11. On the subject captioned above and letters under reference, vide which you were requested to ensure for release of connections within specified time period and to send the names of officers/officials on whom part the delay has occurred. While observing the information of pending MIP and HT categories, new and load extension applications, as on 15th July, 2011, it has been noticed that delay has occurred in release of connections in so many cases. As such, while enclosing the list of some such applications, where delay has occurred, you are, requested to kindly look into the matter personally and arrange to get released the connections at the earliest. Further, it is again, requested to kindly intimate the names of officers/officials on whom part the delay has occurred. Kindly treat it as urgent. Encl.:As above (MOHAMMED IQBAL) SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR Copy submitted to the Zonal Chief Engineer(O&M-JDZ/BKZ), Jodhpur Discom, Jodhpur/Bikaner, for information and needful action. SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR Urgent by Fax
G:pending new

JODHPUR VIDHYUT VITRAN NIGAM LIMITED OFFICE OF SUPERINTENDING ENGINEER (RA&C)


No. JdVVNL/MD/CE(HQ)/SE(RA&C)/Ju/S.AAE(C) /2k11-12/D. Dt.

The Superintending Engineer(M&P), Jodhpur Discom, Jodhpur Sub.: Regarding detail of release of new & load extention applications for MIP & HT category. On the subject captioned above, while observing the information of pending MIP and HT categories, new and load extension applications, as on 15th July, 2011, it has been noticed that delay has occurred in release of connections in so many cases. As such, while enclosing the list of some such applications, where delay has occurred, you are, requested to kindly look into the matter personally and arrange to get released the connections at the earliest. Further, it is requested to kindly intimate the names of officers/officials on whom part the delay has occurred. Kindly treat it as urgent. Encl.:As above (MOHAMMED IQBAL) SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR

G:pending new

Urgent by Fax JODHPUR VIDHYUT VITRAN NIGAM LIMITED OFFICE OF SUPERINTENDING ENGINEER (RA&C)
No. JdVVNL/MD/CE(HQ)/SE(RA&C)/Ju/S.AAE(C) /2k11-12/D. Dt.

The Superintending Engineer(CC/DC/O&M), Jodhpur Discom, . Sub.: Regarding detail of pending new & load extention applications for MIP & HT category. Ref: This office letter No.1014 dtd 15.06.11 On the subject captioned above and this office letter under reference, vide which you were requested to send the status of pending HT & MIP category new connection & load extention applications by 5 th (detail as on end of previous month) & 20th (detail as on 15th of each month) day of each month. The desired information as on 15.07.11 has not been received till date, as such you are again requested to kindly arrange to send the same today itself, by fax(0291-5106366), for appraisal. Kindly treat it as urgent. (MOHAMMED IQBAL) SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR Copy submitted to the Zonal Chief Engineer(O&M-JDZ/BKZ), Jodhpur Discom, Jodhpur/Bikaner for information and needful action. SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR

G:pending new

Details of delay in new/load extension application of MIP & HT category


Information as on 15.09.11

Jodhpur Zone, SE(CC), Jodhpur


S.No. Name of Consumer 1 2 3 4 5 6 7 8 9 10 M/s Rajasthan Gum Pvt. Ltd. Boranada 11 M/s Sunita Hydro Colloides Boranada M/S Chopara Strcts Ltd. Borananda M/s Radiant Packing Boranada M/s Sardar Espises Boranada M/s Relience Matal Sangariya M/s Gopal Sand Stone M/s Mahaveer send Ston M/s Mukal Stone Art S.S. M/s Champa Lal S.S. M/s N.K. Stone S.S. M/s R.S. Stone & Art M/s Gashi Ram S.S. M/s Chand Mandi Stone S.s. M/s Kirshan Stone Art M/s Marwar Stone Art Applied Load Dt. of Dt of DN Dt of Remarks Appl. SCO Under Job 59 HP 11.05.11 25.07.11 work Under Job 59 HP 17.05.11 25.07.11 work Under Job 59 HP 31.05.11 25.07.11 work Notice for 59 HP 06.07.11 open plot Notice for 59 HP 07.07.11 open plot Under Garece 59 HP 12.07.11 13.09.11 period Under Notice 59 HP 13.07.11 open your plot Under Job 59 HP 19.07.11 13.09.11 work Under 59 HP 26.07.11 objection L Form & 4350 HP consumer side CD 2400 10.02.11 29.06.11 job work not KVA carried out Under 8900 HP 16.03.11 Revised CD 3500 estimate 1700 HP 29.06.11 Notice for CD 800 open plot Under Job 58 HP 18.05.11 04.08.11 work Notice for 59 HP 11.07.11 ownership 75 HP Under 28.07.11 CD 50 K observation 150 HP Under Job 05.07.11 25.07.11 CD 90 work

12 13 14 15 16

G:pending new

Details of delay in new/load extension application of MIP & HT category


Information as on 15.09.11

Jodhpur Zone, SE(DC), Jodhpur


S.No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 Name of Consumer M/s PHED XEN DDI M/s AEN PHED M/s AEN PHED M/s AEN PHED M/s AEN PHED M/s AEN PHED M/s AEN PHED M/s Dinesh Fregrance M/s AEN PHED Osian M/s AEN PHED Osian M/s AEN PHED Baori M/s Maa Kripa M/s Jakhar Stone M/s Om Stone M/s Sona Textile M/s A.B.Block & Bric M/s Laxmi Stone Work M/s Shivam Chemical, Piparcity M/s Laxmi Ice, Bilara M/s Barfa Zinning, Bilara M/s Dudi Stone, Bilara M/s Jai Shankar Stone M/s Dev Dasrath Stone M/S New Jagdamba Send Sto M/S Kusum Send St M/S Puja Stone M/S Veer Teja Stone M/S B.S. Stone M/S Ashapurna Send Stone Keru M/S Lotus Engitech Contact Electricts Indian Go Direct M/S Raj Chemicals Rinya(Re-Open) M/S Prince Chemicals Jawasiy Applied Load 1394KW 310 KW 600 KW 160 KW 150 KW 150 KW 160 KW 25 to 300 60KW 80 KW 100KW 59 HP 59 HP 59 HP 30 to 49 H 48 to 132 25 to 55 H 140 to 275 HP 35 to 50H 40 to 59 HP 59 HP 59 HP 150 HP 59 59 59 59 125 55 89 35 TO 45H 35 To55H 59 To 80HP 30 To 59HP Dt. of Application 22.02.07 25.02.10 31.12.10 31.12.10 05.01.11 06.01.11 31.12.10 15.12.10 29.12.10 06.01.11 31.12.10 08.04.11 24.11.10 21.04.11 29.12.10 28.02.11 15.11.10 11.11.10 11.04.11 11.04.11 15.03.11 10.06.11 24.06.11 7.7.11 12.7.11 12.7.11 18.7.11 13.7.11 8.07.11 11.7.11 13.7.10 15.7.10 27.7.11 13.7.11 Under Estimate Estimate Estimate Estimate Estimate Under Estimate Estimate Estimate Estimate Under Estimate Under Estimate Dt of DN 28.03.07 05.03.10 Dt of SCO Remarks Job Job Tech.San T.S. T.S. T.S. T.S. Under sanct Under sanct Under sanct Under sanct Job 14.09.11

06.07.11 08.03.11 29.06.11

G:pending new

Jodhpur Zone, SE(O&M), Jalore


S.No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Name of Consumer
M/s Veer Teja Granite M/s Suraj Stone, Bhagli M/s Jai Rana Stone M/s Dhanlaxmi Stone, Madalpura M/s Maa Sundha Granite, Madalpura M/S Om Granite, Bishnagarh M/S Rajesh Granite, Bishangarh M/s Harsh Bherav Granite Ind. Madalpura M/s Maruti Grani Marmo, Bhagli M/s Natural Granite, Bhagali M/s Ratan Deep Granite, Madalpura M/s Hanuman Stoneo, Madalpura M/s Nagneshi Granite M/s Vikas Grani Marmo M/s Shiv Granite M/s S.R.Granite M/s Mukul Granite M/s Vijay Shree Granite M/s Natraj Industries M/s Om Shiv Granite M/s Choudhary Brothers M/sJai Guru Dev Industries M/s Dig Vijay granite M/s Gaja Nand granite M/s Shree Granite

Information as on 15.09.11

Applied Load
60 HP 60 HP 60 HP 60 HP 60 HP 45 HP 40 HP 150 HP 150 HP 150 HP 135 HP 60 HP 59 HP 125 HP 60 HP 60 HP 60 HP 149 HP 25HP 60HP 60HP - 120 HP 60HP - 120 HP 60HP - 150 HP 60HP - 120 HP 60HP - 149 HP 60HP - 125 HP

Dt. of Dt of DN Dt of Remarks Application SCO 25.05.10 09.08.11 Job 11.04.11 02.09.11 Job 25.04.11 Job 09.08.11
10.06.11 27.04.11 10.06.11 23.06.11 8.07.11 20.04.11 24.05.11 01.06.11 09.06.11 06.07.11 25.04.11 13.06.11 17.06.11 20.06.11 11.07.11 12.07.11 18.04.11 31.03.11 19.04.11 30.05.11 06.06.11 06.07.11 25.07.11 09.08.11 09.08.11 18.08.11 16.06.11 27.07.11 1.09.11 1.09.11 2.09.11 23.08.11 9.09.11 2.09.11 2.09.11 2.09.11 2.09.11 23.08.11 30.06.11 13.07.11 8.09.11 12.08.11 -

Job Job Job Job


T/F, Met & M. Box req.

Job Job Job Job Job Job Job Job Job Job Job Job Job Job Job Job Job

G:pending new

Details of delay in new/load extension application of MIP & HT category


Information as on 15.09.11

Jodhpur Zone, SE(O&M), Pali


S.No. Name of Consumer 1 2 3 4 5 6 7 M/s Shiv Agrico, Rani M/s Varun Ind M/s Sidhi Vinayak Cement, Jaitaran M/s Puran Prakash, Pali M/s Sharda Udhyog, Pali M/s Parswanath Ent M/s Vikas Heena
M/s. Anamika

Applied Load 250 HP 16.825 MW 1500 KVA 59 to 85 HP

Dt. of Dt of DN Appl. 03.05.10 03.09.10 15.02.11 28.05.11 13.04.11 06.07.11

Dt SCO

of Remarks Job PPM TCC PPM to

1350 to 06.09.10 1485 HP 56 to 95 HP 18.05.11 59 to 70 HP 03.01.11


22to100 HP 06.07.11

PPM

05.03.11

03.08.11

Trf req

Details of delay in new/load extension application of MIP & HT category Information as on 15.09.11 Jodhpur Zone, SE(O&M), Jaisalmer S.No. Name of Consumer 1 2 3 4 5 6 7 8 9 Mishri khan/Valia khan M/s Resopower M/s Rajasthan solar urja M/s Rajlaxmi Minrals Lakh Singh Bhati Shivkumar/Ramanlal, Kohinoor Madhvi Stone 59 to 150 15.07.11 Raj West 4Nos Applied Load 149 40 100 59 59 59 106 to 166 Dt. of Dt Appl DN 06.06.11 10.06.11 14.06.11 22.07.11 02.08.11 07.06.11 04.06.10 30.12.10 30.08.11 30.08.11 of Dt of SCO Remarks No construct of meter room Under Grace period Under Grace period Under estimate Under estimate Under estimate Work in Progress Under Estimate Long pending

G:pending new

Details of delay in new/load extension application of MIP & HT category Information as on 15.09.11 Jodhpur Zone, SE(O&M), Sirohi S.No. Name of Consumer 1 2 3 4 5 6 M/s Panchsil Globe, Abu Road M/s J.B.Licene Steel, Abu Road M/s Shiv Jyoti P Ltd. M/s Shiv Marbles, Reodar M/s Jayanti lal Umedram M/s Hema Dhanna Choudhary Applied Load 10 MW 25 MW Dt. of Dt of DN Appl. 14.09.10 14.09.10 Dt of Remarks SCO PPM to TCC PPM to TCC Under Sanction Job Work under progress Pannel box req

22 HP to 18.04.11 400KVA 59 to 150 11.03.11 HP 59HP 22-03-11 59 HP 15-12-10

16.06.11 16-062011 03-032011

G:pending new

Details of delay in new/load extension application of MIP & HT category Information as on 15.09.11 Jodhpur Zone, SE(O&M), Barmer S.No. Name of Consumer 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Sh. Satiyay Mata Mills, 4th Phase Balotra M/s Malleshawar Industries LTD BLT M/s. Alka Stone , Village- Deora M/s. Rishabbh Granite, Village - Deora M/s. Fateh Granit, Village - Deora Sh. Jagdish Prashad / Sultana Ram Sh. Vickaram ji / Daya ram / Village- Deora Sh. Kailash / Bhanwar Singh Village Deora M/s. Fateh Granit, Village - Deora Sh. Devendra / Bhagirath Village Mahadev minerals Tapriya Khanij Udhyog Tapriya Plaster Kawas Mahadev Stone Cuttin Valkoo Jaisalmer Road Raj west Pwt Shivkar Road

Applied Load
260 230 150 HP 150 HP 150 HP 150 HP 150 HP 150 HP 150 HP

Dt. of Dt of Dt Appl. DN SCO


01.06.11 30.06.11 01.02.11 29.04.11

of Remarks
constrction work not completed Under Estimate

Job Job
01.02.11 29.04.11

Job
01.02.11 29.04.11

Job
01.02.11 29.04.11

Job
01.02.11 29.04.11

Job
01.02.11 29.04.11

Job
01.02.11 29.04.11

Job
01.02.11 18.04.10 23.02.11 01.02.11 21.06.11 07.01.11 29.04.11 02.02.11 29.04.11 29.04.11 09.08.11 Transf. not provid JIR Pending JIR Pending DN Awaited Under objection

150 HP 40 to 85 80 80 59 59 to 149 ltd 4 MVA

16.11.10 08.08.11

G:pending new

Details of delay in new/load extension application of MIP & HT category Information as on 15.09.11 Bikaner Zone, SE(O&M), Bikaner
S.No . Name of Consumer Oaisis Indi. Beechwal Agarwal Packaging, KIA National Ind.KIA J.K. Industires KIA Maheswari ind. Napasar Prem Bhujiya Bhandar

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Applied Load 86-220 50-80 20-110 35-59 37-55 25-50 10-35 25-55 25-35 15-40 3-59 59-80 59-85 60-80 59-85 75-95 25-40 25-75 25.85 125-250 59-150 325 400 59 37.5 75 85

Dt. of App 25.1.11 3.5.11 16.5.11 26.5.11 30.4.11 7.1.11 10.1.11 15.2.11 24.2.11 30.6.11 23.6.11 26.10.10 21.10.10 11.2.11 24.5.11 20.8.10 31.5.11 6.6.11 15.7.11 27.7.11 22.7.11 15.3.11 12.7.10 4.5.11 19.5.11 31.5.11 14.6.11

Dt of DN 1.8.11 16.8.11 16.8.11 16.8.11 13.7.11 12.7.11 12.7.11 3.8.11 3.8.11

Dt of SCO

Remarks Own Trs. Not installed D.N. Amount not deposited Work under Progress Work under Progress Completed L form not received L form under Checking L Form under Checking D.N. Amount not deposited Under sanction Under sanction

S.K. Ind. KIA Karani Food Product KIA BKN Syam Sweet KIA BKN Sarad Repakers KIA BKN Keshav Ind KIA BKN Mahavir Chemical & Mineral, Sobhasar Godara Plaster Ind. Sobhasar Anant Plaster, Sobhasar Dewal Ind. Sobhasar Balaji Agro Cold Ind. Sobhasar Prince Packegers Nal Badi Super Plaster, Sobhasar Gaytri Plaster, Sobhasar Pawan Polytex Vishwakarma Ind. Nokha Welcome Oxizen Ind. Salasar Anpurna Ind. Gadwala Balaji Mines & Const. Roda Bhagirath/Moda Ram, Napasar M/s Jai Jawala Plaster, Jaimalsar M/s Siyag Plaster, Sobhasar

Under sanction Under sanction Under sanction Under sanction Notice issued for Transformer Under Sanction Under Sanction Under Sanction Own Trs. Not installed Under Objection 21.7.11 9.6.11 Work under progress DN Amount not deposited Under Objection Land conversion notice Work under progress Construction is not ready

15.12.10

12.8.11

30.8.11

G:pending new

Details of delay in new/load extension application of MIP & HT category Information as on 15.09.11 Bikaner Zone, SE(O&M), Sriganganagar S.No. Name of Applied Dt. of Dt of DN Dt of Remarks Consumer Load Application SCO 1 40 HP to Dhingra Flour & 150 HP 24.06.11 19.09.11 Oil Mill 125KVA 2 Sent to Rajesh Kr / 22 HP to 01.03.11 14.06.11 09.08.11 M&P for Harbans lal 55 HP Releasing 3 Gurmel 20 HP to 27.12.10 25.07.11 Singh/Jagir singh 80 HP 4 Prem Kr / Prabhu 59 HP 08.07.11 Dayal 5 25 HP to Pawan Industries 16.06.11 15.09.11 50 HP 6 Shivam Plaster 59 HP 05.07.11 Udyog Details of delay in new/load extension application of MIP & HT category Information as on 15.09.11 Bikaner Zone, SE(O&M), Churu S.No Name of Consumer . 1 M/sXEN(PHED), Ratangarh 2 M/s Ganesh Repairing, Ladnun 3 M/s Laxmi Crusher Udhyog, Sujangarh 4 M/s Ganga Crusher, Ladnun 5 M/s Pawan Crusher, Sarothia 6 M/s XEN(PHED), Sardarsahar Applied Load 2500 HP 44 to 132HP 120 to 250 HP 120 to 220 HP 140 to 200 HP 1900 to 4000KVA Dt. of Dt of DN Appl. 27.02.11 02.03.11 30.03.11 15.12.10 11.05.11 29.02.11 22.07.11 31.07.11 22.07.11 06.07.11 Dt of Remarks SCO Under sanction Job Under sanction Under Estimate Under Estimate

Bikaner Zone, SE(O&M), Hanumangarh Nil

G:pending new

Urgent by Fax JODHPUR VIDHYUT VITRAN NIGAM LIMITED OFFICE OF SUPERINTENDING ENGINEER (RA&C)
No. JdVVNL/MD/CE(HQ)/SE(RA&C)/Ju/S.AAE(C) /2k11-12/D. Dt.

The Superintending Engineer(CC/DC/O&M), Jodhpur Discom, . Sub.: Regarding detail of pending new & load extention applications for MIP & HT category. Ref: This office letter No.1014 dtd 15.06.11 On the subject captioned above and this office letter under reference, vide which you were requested to send the status of pending HT & MIP category new connection & load extention applications by 5 th (detail as on end of previous month) & 20th (detail as on 15th of each month) day of each month. The desired information as on 15.08.11 has not been received till date, as such you are again requested to kindly arrange to send the same today itself, by fax(0291-5106366), for appraisal. Kindly treat it as urgent. (A.D.VYAS) SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR Copy submitted to the Zonal Chief Engineer(O&M-JDZ/BKZ), Jodhpur Discom, Jodhpur/Bikaner for information and needful action. SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR

G:pending new

Urgent by Fax JODHPUR VIDHYUT VITRAN NIGAM LIMITED OFFICE OF SUPERINTENDING ENGINEER (RA&C)
No. JdVVNL/MD/CE(HQ)/SE(RA&C)/Ju/S.AAE(C) /2k11-12/D. Dt.

The Superintending Engineer(CC/DC/O&M/M&P), Jodhpur Discom, . Sub.: Regarding detail of pending new & load extention applications for MIP & HT category. Ref: This office letter No.1081 dtd.20-06-11, 1095 dtd.22-06-11, 1096 dtd.22-06-11, 1253 dtd 08.07.11. On the subject captioned above and letters under reference, vide which you were requested to ensure for release of connections within specified time period and to send the names of officers/officials on whom part the delay has occurred. While observing the information of pending MIP and HT categories, new and load extension applications, as on 15 th August, 2011, it has been noticed that in some cases demand note has not been issued even after lapse of more than 3-4months of deposition of files. Delay has also occurred in release of connections in so many cases. It has been gathered that sufficient number of LT CT & LT TVMs are available with M&P wing. As such, you are requested to kindly look into the matter personally and arrange to get released the connections at the earliest. Further, it is again, requested to kindly intimate the names of officers/officials on whom part the delay has occurred. Any requirement related to metering equipment be send to the Superintending Engineer(M&P), Jodhpur under intimation to Superintending Engineer(MM&C), Jodhpur. Kindly treat it as urgent. (A.D.VYAS) SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR Copy submitted to the Zonal Chief Engineer(O&M-JDZ/BKZ), Jodhpur Discom, Jodhpur/Bikaner, for information and needful action. SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR
G:pending new

Urgent by Fax JODHPUR VIDHYUT VITRAN NIGAM LIMITED OFFICE OF SUPERINTENDING ENGINEER (RA&C)
No. JdVVNL/MD/CE(HQ)/SE(RA&C)/Ju/S.AAE(C) /2k11-12/D. Dt.

The Superintending Engineer(M&P), Jodhpur Discom, Jodhpur Sub.: Regarding detail of release of new & load extention applications for MIP & HT category. On the subject captioned above, while observing the information of pending MIP and HT categories, new and load extension applications, as on 15 th July, 2011, it has been noticed that delay has occurred in release of connections in so many cases. As such, while enclosing the list of some such applications, where delay has occurred, you are, requested to kindly look into the matter personally and arrange to get released the connections at the earliest. Further, it is requested to kindly intimate the names of officers/officials on whom part the delay has occurred. Kindly treat it as urgent. Encl.:As above (MOHAMMED IQBAL) SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR

G:pending new

Urgent by Fax JODHPUR VIDHYUT VITRAN NIGAM LIMITED OFFICE OF SUPERINTENDING ENGINEER (RA&C)
No. JdVVNL/MD/CE(HQ)/SE(RA&C)/Ju/S.AAE(C) /2k11-12/D. Dt.

The Superintending Engineer(CC/DC/O&M), Jodhpur Discom, . Sub.: Regarding detail of pending new & load extention applications for MIP & HT category. Ref: This office letter No.1014 dtd 15.06.11 On the subject captioned above and this office letter under reference, vide which you were requested to send the status of pending HT & MIP category new connection & load extention applications by 5 th (detail as on end of previous month) & 20th (detail as on 15th of each month) day of each month. The desired information as on 31.08.11 has not been received till date, as such you are again requested to kindly arrange to send the same today itself, by fax(0291-5106366), for appraisal. Kindly treat it as urgent. (A.D.VYAS) SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR Copy submitted to the Zonal Chief Engineer(O&M-JDZ/BKZ), Jodhpur Discom, Jodhpur/Bikaner for information and needful action. SUPERINTENDING ENGINEER(RA&C) JODHPUR DISCOM, JODHPUR

G:pending new