Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
2007
SOLUTIONS: Assignment 2
3.5
ii) 12 days. [See the paths and their durations in part vi).]
iii) There are two critical paths: cf and cd. The path with the larger variance is cd
with a variance of 2+4.25=6.25 and standard deviation of 2.5.
P(13 < X < 15) = P([13 – 12]/2.5 < z < [15-12]/2.5) = P(0.4 < z < 1.2) = 0.3849-
0.1554=0.2295
vi)
Current Length after crashing by one day the activities
Paths Length c d,f
ae 6 6 6
be 3 3 3
bf 10 10 9
cf 12 11 10
cd 12 11 10
Explanation: There are two critical paths: cf and cd. We must reduce the lengths of
both by one day. This can be done in two possible ways: 1) Crashing c by one day
which will cost 300. 2) Crashing d, f by one day each, which will cost 200 + 150 =
350. Choose the first way, which is cheaper.
But c can be crashed only by a maximum of one day. Hence to crash the project for
another day we are left with the only possible way of crashing d,f by one day each at
the cost of 350.
The optimal cost of crashing the project for two days is therefore 300 + 350 = 650.
If the cost slope for activity c is revised to $400, then the cheapest way will be to
crash d, f for both days at a cost of 350 + 350 = 700. This is possible because each of
the activities d, f can be crashed for two days?
3.6)
a)
Activity Duration ES EF LS LF S
a 5 0 5 0 5 0*
b 3 0 3 1 4 1
c 2 5 7 5 7 0*
d 3 3 6 4 7 1
e 7 7 14 7 14 0*
f 4 14 18 14 18 0*
g 3 14 17 18 21 4
h 5 18 23 18 23 0*
i 2 17 19 21 23 4
b)
Let X = project duration. Mean of X = 23 days, Variance of X = .64+.09+.16+1+.25 =
2.14
St Dev of X = 1.4629. P (X<18) is almost zero.
c)
X = 23 + 1.645(1.4629) = 25. 41 days
d) Crash Actiivity
Paths Durations f by 1 f by 1 a by 1 h by 1
The project time can be reduced by 3 days at a cost of 30000. An additional day of
reduction will cost
60000, which is over the budget limit. After three days of crashing, the critical paths are
a-c-e-f-h and
b-d-e-f-h.
3.7)
a)
Activity Duration ES EF LS LF
S
a 4 0 4 2 6 2
b 5 0 5 0 5 0*
c 3 0 3 4 7 4
d 2 4 6 6 8 2
e 3 5 8 5 8 0*
f 1 3 4 7 8 4
g 5 8 13 8 13 0*
h 4 8 12 14 18 6
i 7 13 20 13 20 0*
j 3 12 15 18 21 6
k 1 20 21 20 21 0*
1 2 21 23 21 23 0*
m 2 20 22 21 23 1
Activity Duration ES EF LS LF S
a 10.00 0.00 10.00 0.00 10.00 0.00*
b 7.17 0.00 7.17 11.83 19.00 11.83
c 3.00 7.17 10.17 19.00 22.00 11.83
d 15.00 10.00 25.00 10.00 25.00 0.00*
e 7.00 25.00 32.00 25.00 32.00 0.00*
f 10.00 10.17 20.17 22.00 32.00 11.83
g 7.17 25.00 32.17 39.83 47.00 14.83
h 15.00 32.00 47.00 32.00 47.00 0.00*
d) The critical path is a-d-e-h. The expected duration of the CP is 47 days and the
standard deviation is 1.856.
Std deviation of critical path = sq root of sum of variances of critical path
activities
Std dev = sq root of (.444+2.778+.111+.111) = 1.856.
3.9)
Activity Duration ES EF LS LF S
a 3 0 3 1 4 1
b 4 3 7 5 9 2
c 5 3 8 4 9 1
d 3 0 3 0 3 0*
e 6 3 9 3 9 0*
f 7 9 16 9 16 0*
Activity e on critical path with least crashing cost should be crashed first.
d)
Paths Durations
d) You cannot spend exactly $200 to reduce the project time. But within a budget of
$200 you can crash the project for one week. Crashing the project by two weeks will
cost $225.
a) The duration of the fully crashed project is 13 weeks. The total crashing cost is
$375.
Note: We did not have to be concerned with the fact that activity b can be crashed
only by ½ week, since it is never on any critical path. If it were on a critical path we
would have to consider the possibility of crashing it by ½ week.
4.12
4.13
b. Q* = 250,998
c. OP = 24500
d. 875000/250998= 3.47 times a year
e. 250998/3500 = 71.71 days
f. Production run time is 250998/6000=41.833 days. For 71.71-41.83=29.88
days the bags are not being printed.
4.14
4.15
a. Q* = SQRT(2*50*360*42/.24*7.2) = 935.41
b. DDLT is normally distributed with mean 4(50)=200 and standard
deviation = SQRT(4*25)=10
Service level = .95, Z=1.645
OP = 200 + 1.645(10) = 216.45
c. 16.45
4.16
X P (demand < X)
80 0.10
90 0.35
100 0.75
110 0.95
120 1.00