Date: 10-02-2012 1) Tunnel Progress up to 31-01-2012 5541.54 Meters (3440 Rings) 2011April-16.50, May-97.02, June-123.03, July-258.81, Aug-304.61, Sep-204.

.68, Oct-229.10 Nov.250.42, Dec.308.12, Jan-359.76 (2152.05 M) 2) BORING & LINING - As on 09-02-2012 Progress in Meters No. of Rings built During the Day Cumulativ Progress During the day Cumulative Cumulative from e for the from the for the the starting A B C A B C month starting month 0 11.09 13.02 0 7 8 160.66 5702.20 100 3540 24.11 15 3) P-Gravel: Pumping: Bin capacity 4.8 Cu.M; Consumption = 1.1, Bin/ring; 01 bag cement = 0.18 C.M No. of Segment/ No.of bags / Total Bags/ Average Progressive Stock of Segments/ Ring Nos bins bins per ring Average bags / bins Rings consumed consumed in this day /Month 3502-3505 1. I G 9 6.0 6.0 3510-3514 2. B G 13 3364-3476 18.61 18.54 6.0 3. P G 14 3422-3535 84 Cu.M 84 Cu.M 3 bins 6.0 Cu.M 4) Surveyor Report Details: Position at Start of Day Position at the end of Day F R Tendency F R Tendency Roll 1 H -51 -45 -2 Roll 1 H -1 -13 -3 P -1 V 52 59 -2 P -1 V 9 47 -2 5) Details: Details Maintenance
Probe hole drilling done in BH No.3 60 M in 1st shift. . Cutters inspection done & 1 No. cutter replaced.. Pea gravel pumps maintenance done. WR2 grease barrel filled in labyrinth seal pump.

6) Cutters: No.of cutters replaced during the day No. of cutters replaced during the month Cum. Total Single Double Single Double Single Double

Remarks

01 Nos. (No.31)

5 nos.

--

--

7) Material status as on: 09-02--2012 Name of the material 1.a) Water pipe line Extension b) M16x100mm anchor bolt c) M16x145Fischerbolt Hilti type 2. Conveyor belt extension a) Splicing kits b) Belt hangers c) Brackets Top Bottom d) M20x184 Fisher Bolts e) Conveyor Belt Materials (Set is 3.2 Mtrs)

Consumed in the day Nos/Mtrs) 4 (out) 5 Nos. & 6(in)- 5 Nos 50 0 24.11 Mtrs (61.22 Mtrs) 0 Nos 0 nos 0 nos 0 nos 30 nos
Channels Bottom Frames Top Frames 7 sets 7 sets -- 7 sets

Stock available (Nos/Mtrs) 4- 6 Nos, 6- 8 Nos 830 Nos 190 1000 M (5513 M) 2 nos. 300 nos 110 nos 30 nos 280 nos
Channels: - 9 sets 32 Mtrs Bottom Frames - 135 sets 432 Mtrs Top Frames - 197 sets 630 Mtrs

Bottom Rollers Top Rollers

7 sets 7 sets

Bottom rollers 50 sets 160 Mtrs Top rollers - - 133 sets 425 Mtrs

3. a) Rails extension 14 nos 149 nos 2438 Nos b) Fish plates 30 nos c) Rail clips 0 nos 6125 (4500 Returned to T2) nos d) Plate screws 500 nos 9000 nos 4. Ventilation Duct. 24.11 Mtrs (L- 53.8 Mtrs) 2000 Mtrs (5656 M) a) Ventilation over head rope 0 96 nos 5. Cement 6.a) Grease barrels-WR2 0 14 barrels b) Hyd. Oil SS-68 0 10 barrels c) Servo mesh SP-320 gear oil 0 01 barrel d) Servogem-3 0 2 barrels e) Shell Omla F-460 0 8 barrels g) 15W40 Engine oil 0 295 L h) Coolant 0 222 Ltrs i) Roto inject Oil 0 75 L g) Gear Oil HP 90 0 0 barrel h) SP Mesh 1000 0 0 barrel i) Servo grease MP3 0 3 barrels 7.a) 33 KV cable extension 24.11 Mtrs (128 Mtrs ) 770 Mtrs ( 5412 M) b) 33KV cable kits 0 nos 3 nos 8. a)Lighting Cable 10Sq.mm 24.11 Mtrs 443.96 Mtrs b) Lighting cable junction box 1 no. 98 nos 9. Telephone cable 24.11 Mtrs 500 Mtrs 10. Water pipe line brackets 20 Nos 17 nos 11. Cable bracket 25 nos 124 nos 12. Dowel inserts 120 nos 267 nos Segments : Received 56 Consumed 60 nos, Stock in yard 84 nos 8) Power Details: Approved Contract Demand 4000 KVA, 80% of contract demand = 3200 KVA Max. Demand Cumulative No. of Units Total consumed in the KVA P.F. Consumed-KVAH month KVAH 3500 0.9942 34,000 5,94,600 9) Muck Transport Details - Solid: 01 Mtr progress = 50 Cu.M, 01 Cu.M = 02 Tons No. of 20T Tippers No. of trips / Cu. Mtrs Total Solid Cu.M Total Solid Cu.M - Cumulative A B C A B C 1205.5 8033 ----0 0 0 10. Pumping & seepage water: All pumps in order. 50 HP pump working with 7 bar pressure inside tunnel. 11. Water flow: 1714 GPM 12. Urgent material required: 13. Material received: 1. Dowel inserts 160 nos from Mam Technology, Hyderabad; 2. 4 pipes 10 nos & 6 pipes 10 nos received fromT2. 14. Details of Tiffin/Meals Date Description I shift II shift III shift G Shift Total Prog. Remarks 09-02-12 Tiffin 66 65 58 -189 1523 Lunch/dinner UTS-2+ NSC-9 Meals ---10 10 78 15. Remarks : 1. Rail clips 4500 nos returned to T2. PROJECT INCHARGE DY GENERAL MANAGER