Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Ay e AKBALIK-RAPINE s
January 2011
Line Balancing
Select project (Pareto, Fish diagram, Gantt, PERT, Job/Worksite analysis guide) Get and present data (charts, computations) Analyze data (operation analysis) Develop ideal method (motion, work, equipment design) Present and install method (decision making tools) Develop job analysis Establish time standards (time study) Follow up
2 3 4 5 6 7 8
Line Balancing
See Beyond Lean page Everyone is doing the same amount of work Variation is smoothed No one overburdened No one waiting Everyone working together in a balanced fashion
Line Balancing
Line Balancing
Example 1 Operation 1 = 5 min Operation 2 = 15 min Operation 3 = 10 min Questions What is the cycle time of this system? If each operation was 15 min, what happens? If we consider Operation 2 = 10 min ?
Line Balancing
Line Balancing
Example 1 What is the system efciency? What is the idle time percentage?
Line Balancing
Line Balancing
Example 1 What is the system efciency? efciency % = ( total actual standard minutes )% total allowed standard minutes
Line Balancing
Line Balancing
Example 2 We want 960 pieces a day (with 8h a day) See the standard minutes for each operation below Operation Op 1 Op 2 Op 3 Standard minutes 1.2 min 2.4 min 1.9 min Number of operators ? ? ?
Line Balancing
Line Balancing
Operation Op 1 Op 2 Op 3
Number of operators 3 5 4
Line Balancing
Reassign some of the work of operation 2 to the other operations Improve the method at operation 2 to decrease the cycle time Utilize a part-time worker
Line Balancing
Operation Op 1 Op 2 Op 3 Op 4 Op 5 Op 6 Op 7 Op 8
Standard minutes 1.25 min 1.38 min 2.58 min 3.84 min 1.27 min 1.29 min 2.48 min 1.28 min
Number of operators
Line Balancing
Line Balancing
Example 3 nd the number of operators to assign to each operation for a production of 700 pieces per day minimization of the storage costs are of high importance! no stock level is required at the end of day which operation determines the output from the line? nd the total number of pieces produced at the end of the day
Line Balancing
Line Balancing
Line Balancing
Operation times are given as follows: 0.46, 0.35, 0.25, 0.22, 1.10, 0.87, 0.28, 0.72, 1.32, 0.49, 0.55.
Line Balancing
Rank operations according to their number of predecessors Assign rst operations with least number of predecessors In case of tie, choose operation with longest operation time Total time at each work station cannot exceed the total cycle time Precedence relationships must be satised
Line Balancing
Compute "Positional weight = Operation time + Total time of all operations that must follow it" Begin by assigning the operation with highest positional weight If there is a tie, break it by
higher operation time lower operation number
Total time at a station cannot exceed the total cycle time Precedence relationship must be satised
Line Balancing
Line Balancing
Line Balancing
Line Balancing