Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Process Guide
Production Version 2.3
Production 2.1 SDM Development • CR #272077: synchronized role descriptions in SDM Guide and PM Guide
Team • CR#272084: Replace selected references of scope management with
change management.
• CR#271983: Correct MRS URL to www.ads.ford.com/mrs
• CR#271984: Add wording for assess and make recommendation to
Confirm/Refine Business Case.
• CR#333115: Corrected typos in process 1.1.1 Confirm Project Readiness to
Start.
• CR#271982: Add a step to process 5.3.3 Close and Archive Records to mark
the project complete in ITMS.
Production 2.2 August 14, EPMO – Program • Gate Review ICRP Control Concern – obtain signatures of decision-makers to
2003 Governance Team confirm accountability (Section 4.2.6)
• PQA Strategy update – direct PM to PQA web site (Section 1.1.1)
Prod 2.3 30Apr2004 Program • Portfolio Management – updated overview section with new Portfolio
Governance Office Management Process.
Table of Contents
PURPOSE ......................................................................................................................................................................................... 6
PORTFOLIO MANAGEMENT .............................................................................................................................................................. 6
PORTFOLI O MANAGEMENT PROCESS FLOW ................................................................................................................................... 6
DEFINITION OF PROJECT MANAGEMENT ......................................................................................................................................... 7
PROJECT MANAGEMENT CORE PROCESSES .................................................................................................................................. 8
PROJECT MANAGEMENT KNOWLEDGE AREAS ................................................................................................................................ 9
THE PROJECT LIFE CYCLE .............................................................................................................................................................. 9
PM ALIGNMENT TO TYPICAL PROJECT LIFE CYCLE ....................................................................................................................... 9
KEY PRINCIPLES OF PROJECT MANAGEMENT............................................................................................................................... 11
Project objectives must be SMART ................................................................................................................... 11
Understanding and managing requirements is crucial ............................................................................ 11
Planning is everything and ongoing ................................................................................................................... 11
Control is a necessity, not a luxury .................................................................................................................... 11
Customers must be part of the process .......................................................................................................... 11
Providing an honest assessment of project health is critical................................................................ 11
We know what works, just do it............................................................................................................................ 11
Metrics should be collected throughout the project life cycle............................................................... 11
PURCHASED PACKAGE SELECTION AND IMPLEMENTATION (PPSI) .............................................................................................. 14
IT MANAGEMENT TOOLS ............................................................................................................................................................... 14
GAO AUDIT GUIDELINES .............................................................................................................................................................. 17
PROJECT AUTHORIZATION REQUESTS AND PURCHASE ORDERS................................................................................................. 17
PROCESS PARTICIPANT ROLES ..................................................................................................................................................... 18
1.0 INITIATE PROJECT ......................................................................................................................................................... 25
1.1 PREPARE FOR THE PROJECT............................................................................................................................................ 26
1.1.1 Confirm Project Readiness to Start.................................................................................................................... 26
1.1.2 Identify and Engage Stakeholders..................................................................................................................... 29
1.1.3 Engage Project Start-up Team............................................................................................................................ 31
1.1.4 Develop Start-up Work Plan................................................................................................................................ 33
1.2 ESTABLISH PM INFRASTRUCTURE ................................................................................................................................... 34
1.2.1 Establish Project Control File .............................................................................................................................. 34
1.2.2 Establish Project Procedures.............................................................................................................................. 36
1.3 DEFINE THE PROJECT....................................................................................................................................................... 38
1.3.1 Develop Initial Charter/Enhancement Request................................................................................................ 38
1.3.2 Develop Project Approach................................................................................................................................... 41
1.3.3 Develop Quality Management Plan.................................................................................................................... 44
1.3.4 Develop Communications Plans......................................................................................................................... 46
1.4 DEVELOP HIGH -LEVEL WORK PLAN ................................................................................................................................. 48
1.4.1 Develop High-Level WBS .................................................................................................................................... 48
1.4.2 Develop Dependency Network ........................................................................................................................... 50
1.4.3 Estimate Effort ....................................................................................................................................................... 52
1.4.4 Develop High-Level Schedule............................................................................................................................. 54
1.5 COMPLETE INVESTMENT ANALYSIS .................................................................................................................................. 55
1.5.1 Complete Initial Risk Assessment...................................................................................................................... 55
1.5.2 Develop Initial SOW.............................................................................................................................................. 59
1.5.3 Confirm/Refine the Business Case.................................................................................................................... 61
1.6 CONFIRM READINESS TO PROCEED ................................................................................................................................. 64
1.6.1 Confirm Requirements/Business Owner View................................................................................................... 64
1.6.2 Obtain Initial Charter/Enhance. Req. Signoff.................................................................................................... 66
2.0 PLAN PROJECT............................................................................................................................................................... 69
2.1 DEVELOP PROJECT MANAGEMENT PLANS ........................................................................................................................ 70
2.1.1 Develop Organizational Chg Mgt (OCM) Plan ................................................................................................. 70
2.1.2 Develop Procurement Plan.................................................................................................................................. 71
2.1.3 Develop Transition Plans..................................................................................................................................... 74
2.1.4 Develop Resource Management Plans............................................................................................................. 76
2.2 REFINE WORK PLANS AND BUDGET ................................................................................................................................. 80
Purpose This Project Management Process Guide is intended for use on all types of IT
projects. Its purpose is to guide project managers in the execution of project
management processes and should be used in conjunction with the Solution
Delivery Methodology (SDM) Process Guides developed for specific project
types.
While this document presents processes for managing projects in a disciplined
and consistent manner, it is not a “cookbook”, nor is it a definitive discourse on
project management. It is assumed that you have had at least basic project
management training and that you are familiar with the Solution Delivery
Methodology Guides.
As shown in figure 1.1 below, projects can be viewed in three dimensions. The
Project Life Cycle axis describes the work to be done to deliver the product. The
Project Management Core Processes axis delineates the five processes that must
be performed to plan, manage and conclude projects. The Project Management
Knowledge Areas axis lists ten areas of responsibility that must be addressed by
the project manager while managing the project. Each of the three dimensions is
discussed in more detail below.
Typical Project
Life Cycle
Project Management
Support Knowledge Areas
Resources
Implement
Procurement
Cost
Integration Quality
Analysis
Risk
ID & Assess
Initiate Plan Execute Control Close
Project Management
Core Processes
Figure 1.1 – The Three Dimensions of Project Management
Control Execute
Project Project
Close
Project
Project The ten project management knowledge areas, shown in figure 1.1
Management and described below, represent what the project manager manages
while executing the project management processes.
Knowledge Areas
The Project IT projects are divided into stages that make up the project life cycle. Each
Life Cycle stage has specific processes and deliverables. For example, the processes
and deliverables for Classic Systems Development Life Cycle (shown here) are
described in the Classic Systems Development Solution Delivery Methodology
Guide. Similar guides are planned for different types of projects, including
Object Oriented Development and others.
PM Alignment to As shown in figure 1.3 below, project management activities overlap with and
enhance the processes defined in a typical solution delivery life cycle.
Typical Project
Life Cycle
Project Life
Cycle
Initiate
Plan
Core
Project
Execute
Mgmt
Processes
Control
Close
As this diagram shows, elements of Execute and Control occur at each stage of the
project. It is, therefore, recommended that the reader refer to the Execute and Control
sections throughout the project life cycle and take action, as needed, to acquire
resources, monitor and control project performance, and review and approve project
deliverables.
The following diagram illustrates the metrics collected during a typical project's life cycle:
NCI per Review (Non-compliance issues identified in a Process Quality Assurance Review)
See the appropriate SDM Process Guide for more details on that roles and
responsibilities that are relevant to a specific project type.
Purchased Process changes and special considerations have been incorporated to address the
Package selection and implementation of purchased products, including:
Selection and • Procurement-related processes include considerations for working with 3 rd party
vendors.
Implementation
(PPSI) • A special concern with any implementation performed by 3rd party vendors is that
the project team must pay special attention to ensuring that requirements are fully
understood and incorporated into the solution. Classic SDM addresses this by
explicitly including the Vendor/Supplier in Review Processes (ARB, PQA,
Gate/Tollgate, Validate Requirements, Validate Design).
• Ford's policy is to eliminate the practice of pre-committing orders because they can
lead to misunderstandings and delays in payments. A pre-commitment occurs
each time your firm is engaged to deliver a good or service without the appropriate
authority to proceed being given by your Ford Motor Company buyer. Pre-
commitments occur when anyone - regardless of level or location, engages a
supplier (in writing or orally) to provide a good or service, directly, without the Ford
Motor Company buyer's involvement, a valid release against a blanket purchase
order or purchase order that includes authorization from the appropriate finance
activity. Purchasing will also have emergency procedures developed to ensure true
emergencies can be handled that may require initial contact by those other than
your Ford Motor Company buyer. As a result, the Ford Purchasing Department
must be included in activities where outside vendors are being contacted for
information, proposals and quotes. See the web site
http://fcas268b.dearborn.ford.com:8050/ for further information.
IT Management The following picture depicts management tools currently in place for the tracking of
applications and IT projects within the ADS organization. A description for each of the tools
Tools follows.
§ ITMS: The IT Management System is a single common repository of all Initiative, Program,
Project, and Application Portfolio data enabling effective management of IT’s work across
the enterprise. Objectives of ITMS include:
o To Deploy a Global Common Project and Application Repository to support the One IT
Business Processes.
o Support FMC Corporate litigation by serving as the system of record for all applications
owned and supported by Ford Motor Company.
§ Prosight: Prosight is a Portfolio Management Tool, integrated with ITMS, which supports
choosing, executing, and evaluating IT project and applications. The concept of Portfolio
Management encourages organizations to evaluate the business value to the business
when making business decisions. The objective of Prosight is to enable effective portfolio
management by providing analytical capabilities to view project and application data based
on key business drivers; thereby supporting fact based business decisions. The Prosight
URL is http://www.itonline.ford.com/it_tools/Prosight.html. Refer to the ProSight tutorials
named ProSight Form Data Entry and Project Manager ProSight Data Entry on the same
web site for instructions in the use of Prosight.
§ IT Billing System: IT Billing will provide IT’s business partners with all their billing detail in
an online, web-based system. This system will receive detailed billing data from the various
IT departments, consolidate all charges, and create a single “IT Billing” Journal Entry for
each business partner. The system will automatically feed the Journal Entries into
PeopleSoft/MICS. The major objectives of the IT Billing System is to redistribute internal
costs and influence behavior by providing a consolidated, detailed IT bill to the Business
Partners.
§ RMS: ADS Resource Management System will ensure smooth operation of the Application
Development Services organization resource management model for both Ford and
agency personnel. The system will enable Ford to further develop and strengthen its core
Information Technology competencies. Objectives include:
o Ensure smooth operation of the ADS resource management model for both Ford and
agency personnel.
o Manage skills inventory of ADS project resources to meet business and IT strategy
demands. .
o Establish measures of success for the operational ADS Resource Management tool.
§ MRS: MRS is the Application Development Services (ADS) metrics repository that
provides the functionality for reporting and recording measurements and metrics related to
the Software Development Life Cycle. The planned enhancements encompass the
collection and reporting of application development, enhancement and maintenance project
data used to produce metrics related to productivity, cost, timing, sizing, quality, process
assurance and customer satisfaction metrics. Objectives include:
o Automate and centralize all ADS project, product and process metrics as input for use in
making timely data driven decisions to maximize customer satisfaction, minimize the overall
engineering effort and schedule, and to minimize the number of defects produced.
o Include as a minimum, size, effort, estimation, productivity and schedule metrics, technical
inspection, detailed defect and customer feedback metrics, and adherence to process
metrics.
GAO Audit The Ford General Auditor's Office (GAO) requires that all documentation (electronic and
paper) adhere to security guidelines and retention policies. Also note that electronic
Guidelines documents/data should not reside on desktops, but in an agreed repository (e.g.; electronic
project control book on a shared network drive, PVCS, eRoom, etc.).
Project As indicated in the Ford Financial Manual procedure #55-10-11, no commitments may be
made until the overall program (or a long-lead request for the program) of which the action is a
Authorization part has been approved. For most operations, funding for the specific action is authorized by
Requests and an approved "Project Appropriation Request / PAR", including a standard set of project detail
Purchase Orders sufficient for control.
Funds for the following items are to be requested through use of appropriations requests (or
lease requests):
• Substantial items that are of a fixed asset nature, but for accounting purposes are
expensed.
• Leases that are of fixed asset nature (represents a greater than 1 year commitments
of payment), even though it may expensed for accounting purposes.
Actions Not Requiring Appropriation Request - Appropriation requests are not required for the
following types of items:
• Items are to be capitalized for the first time upon acquisition. Expenses (freight,
dismantling, installation, and similar costs) associated with intra/intercompany fixed
asset transfers may be documented with use of an Intercompany Buying Authority,
to be approved by the local Controller.
• In developing project detail, line items of less than $25,000 need not be separately
identified. For the appropriation request, such items may be grouped in major
categories such as building improvements, machinery equipment, office furniture,
etc.
Note that for a Purchase Order (PO) can be released by Ford Purchasing, the following
steps must occur:
• A Ford Property Manager will review the PO, confirm that the cost is covered
by an entry in PCPAS or COIN and approve/reject the PO. In either case, the
Purchasing Buyer will be notified.
• If approved, the Purchasing Buyer will release the PO. If rejected, the
Purchasing Buyer will notify the user that the PAR must be modified to address
any issues.
The use of appropriation requests is described in the Financial Manual procedure #55-
10-11 which is located at
http://www.dearborn.ford.com/fm/accntng/apfund55/apfprc55/5510/551011.html. The
Project Appropriation Request / PAR description is located in Procedure 55-10-10 of the
Ford Financial Manual which is at
http://www.dearborn.ford.com/fm/accntng/apfund55/apfprc55/5510/551010.html.
For each task, the main participants are listed. Note that the roles in SDM are generic and not associated with an
organization. For example, depending on the type and size of a project, the role of Business Analyst may be played
by someone from the PTG organization or from the Practice. The bolded participant is the key person responsible for
that task.
Competency / Competency/Role Responsibilities Job Family
Role Acronym
6-Sigma 6-Sigma Blackbelt This is a person trained in 6-Sigma DMAIC and DFSS General IT
processes. The 6-Sigma Blackbelt will work with the project Management
team in the design of business processes and ensure that
those processes will achieve Customer CTQ's. It is expected
that all Business Analysts will eventually have Greenbelt or
Blackbelt certification. Until a critical mass of 6-Sigma
certified Business Analysts has been achieved, the Classic
SDM Guide will treat the 6-Sigma role as an additional
consultant on the project team.
ADSBusiness ADS Business Coordinates service rates, approval of project costs against General IT
Manager account codes prior to project execution and billing of incurred Management
project costs to account codes.
ADSMgt ADS Management ADS Manager with profit and loss responsibility for a project General IT
Management
AMCoord Architecture Review architecture selection for compliance with Ford Architecture
Management architecture principles and standards.
Coordinator.
Ensure that the
project team
adheres to Ford
corporate
architecture
principles.
APM/LOB Application Portfolio Coordinate application and support activities for a portfolio of General IT
Manager/ LOB applications, typically for one line of business. Management
Manager
AppDataAdmin Application Data This is the person who has oversight responsibility for N/A
Administrator application data, including data integrity, adherence to the
retention period as defined by GIS1 standards.
AppOwn Application Owner Customer with ultimate responsibility for application and N/A
related business processes. This person is registered on the
ACR as the application owner.
AppSecAdmin Application Security This is the person who administers security for an application N/A
Administrator and defines the type of access allowed.
AppSupr Application Provide oversight for maintenance of one or more General IT
Supervisor applications. Management
AppTechArch Application Plan and design of application platform technology patterns, Architecture
Technology usage standards, and guidelines used to implement IT
Architect solutions. Extend existing architectures to satisfy changing
application needs.
BusA Business Analyst Work with Customer to identify and documenting Business
requirements, perform business process design, measure Analysis/
process capability, and perform Acceptance Test with Reengineering
Customer.
CDBA Corporate / Data Install and configure database products. Database
Center Database Administration
Administrator
CDM Capacity Demand Works as a liason between with project teams and the Data Operations
Management (CDM) Center to select and allocate hardware and software for all
Analyst technical environments (e.g.; development, QC, Education,
Production, Support) in a timely manner.
Cust Business Person(s) knowledgeable of all requirements and business N/A
Customer(s) processes in a subject area, and empowered to define and
accept solution. It is expected that the Customer will actively
participate throughout the project and will sign-off on
designated SDM deliverables.
See the section titled " Customer Involvement In Projects" for
further information.
DBA Data Base Provides expertise, and performs physical database design, Database
Administrator administration and related planning. Administration
DMT Data Model Team A peer review team made up of analysts and the lead Architecture
Information Architect from a Practice that reviews proposed
Espon Executive IT and Business Sponsors who fund the project and actively N/A
Sponsor(s) participate throughout the life cycle.
EUSupport End User Support Provide consulting services, implementation services, End User
Analyst production, operational and systems support for distributed Support
computing at all locations; serves as a liaison between clients
and vendors or other technical groups to resolve client
problems. Also provide feedback to corporate application
owners on user-base issues and establishing effective
support processes Across it support organizations to ensure
timely resolution to end user technology issues.
Facilities Facilities Analyst Coordinate overall planning, deployment and operations of Facilities
facilities within computer centers.
FGTI Intellectual Property Review application and/or business processes and provide N/A
attorney from Ford Customer with advice/guidance and support with respect to
Global applying for patent.
Technologies, Inc.
FinanceAnal Financial Analyst Allocate and release funding for projects (e.g.; hardware, General IT
software and services) on behalf of a business area. This Management
person may also assist with development of project cost
estimates.
GAO GAO Prevention Review ACR documents with the ICC and Application Owner General IT
Control Specialist to ensure that the application adheres to Ford security and Management
(GAO ACR maintenance standards.
reviewer)
ICC Internal Controls Provide support to project teams that are developing an ACR General IT
Coordinator and/or ICR. This person will provide ongoing ACR coaching, Management
review the ACR drafts, and present them to the GAO along
with the Project Manager and Application Owner.
IRR Independent Risk Evaluate project risk (prior to project start) based on a pre- Project/Program
Reviewer defined set of questions. Management
NetE Network Engineer Individual/group with responsibility for all aspects of the Network
networks for a geographical area and the impacts to the rest Engineering
of the global network. Assists with the design, evaluation,
selection, and integration of networking technologies to meet
the needs of the business.
NLM Next Level Manager The manager directly over the Project Manager from a General IT
reporting perspective. Management
OGC Office of General Provide legal counsel for legal transactions such as contracts, N/A
Counsel Attorney as well as advice and guidance with respect to legal issues,
Office of General Counsel (OGC) Document and record
Suspension Orders, etc.
Oper Data Center Perform daily data center operations support activities Operations
Operations (backup, restore).
PGM Program Manager Direct all program -related activities. Initiates, plans executes, Project/Program
controls, and closes program, ensures requirements are Management
understood across all project teams, prioritized and that what
is delivered meets the agreed requirements. Provide
oversight in the management and execution of multiple
projects or projects that are viewed as large and/or complex.
PM Project Manager Direct all project-related activities – initiates, plans executes, Project/Program
controls, and closes project, ensures requirements are Management
understood, prioritized and that what is delivered meets the
agreed requirements.
PQA Independent Process coach who will provide coaching with respect to Process and
Process Quality methodology selection, related processes and templates. Methodology
Assurance Coach They will also participate in project/program reviews to ensure
adherence to process quality assurance guidelines.
PracticeMgr Practice Manager Provide application management for a particular business General IT
function, spanning the entire software development life cycle. Management
PSDevl Production Support Support and maintain application – performs production Solutions
Developer/Analyst support, participates in incident/enhancement design, Development/QA
constructs, tests, and documents application code. Ensures
the completeness of changes as the version specialist;
Coordinates build and packaging for a project as the build
specialist; performs SCM audits and reports the results.
Purchasing Buyer from Ford Works with project teams to acquire vendor-provided N/A
Purchasing information, RFP/RFQ, and negotiate the acquisition of goods
or services.
QCLead Quality Control Test A senior tester, with an understanding of test processes, Solutions
templates and tools who may lead the development of the
RS Reuse Specialist Develops strategies and leads implementation of knowledge- Process and
capture, -retention and -reuse efforts on it projects. Methodology
SAE Specialized Specialized
Application Application
Engineering Engineering
SCC Security Control The security control champion is organization-specific and will General IT
Champion ensure that Ford's security needs are recognized and Management
addressed in the implementation of policies, business
processes and computer applications.
SCMTool SCM Tool Install, configure and support software configuration Solutions
Administrator management (SCM) tools, process, and procedures to ensure Development/QA
they are understood and followed .
SDevl Software Developer Participates in design activity and constructs, tests, and Solutions
documents application system code under the guidance of the Development/QA
lead developer.
SecE Security Engineer Provide consultation on enterprise security both within the Security
organization and external business units. Provides Engineering
assessment, vision, expertise, direction and guidance in the
implementation of secure solutions.
SIE Strategic Work with one or more project team members to test an Technology
Infrastructure application to determine whether it is well behaved (e.g.; Analysis
Engineering Analyst DLL's installed in correct location, DLL's are not over-written,
(was called Ford etc.) and that it is compatible with the Ford Standard desktop.
Systems Integration
Center / FSIC)
SiteCRM Site Client Manage the application and technical environments at a site End User
Relationship as well as act a liason between the Customer and application Support
Manager development/deployment and support teams.
SME Subject Matter Person with sufficient knowledge of a business process as to Business
Expert be considered an expert on the subject who will provide Analysis/
guidance on an as -needed basis. Reengineering
SolnArch Solution Architect Responsible for the assembly and integration of business Architecture
processes, data, and application and infrastructure
Steering Steering Committee A group of individuals (e.g.; managers and subject matter N/A
experts) who can provide oversight and guidance to a
project/program. From a reporting perspective, the Steering
Committee reports to the Executive Sponsor and has the
project team report to it on a periodic basis. These people will
review project status on a periodic basis; provide guidance on
an as -needed basis.
Supplier / Any 3 rd party or a Company outside of Ford that either directly or indirectly N/A
Vendor representative of a provides hardware, software, goods or services to or for Ford.
3rd party that is
either supplying
software or software
services
SysDesAn Systems Individual who oversees design of business processes, Systems
Designer/Analyst application architecture, user interface and system design. Design/Analysis
Solution
Delivery Control
Methodology
Close
Inputs to Initiate Project
Overview At the start of any project, there will be a variety of ideas and opinions about its
purpose and scope, what the final product will be, and how the project will be
carried out. Project Initiation is concerned with taking these ideas and
intentions and developing them into a formal, planned, resourced and funded
project.
The purpose of Project Initiation is to define the overall parameters of the
project, develop initial project plans, and define the appropriate project
management and quality environment required to complete the project. Upon
completion of Initiation, the sponsor(s), business analyst, and project manager
should have enough information to make a go/no-go decision.
Process Contents
Objective Process Steps PM Deliverable
1.1 Prepare for 1.1.1 Confirm Project Readiness to Start Readiness Confirmation
Note the Project 1.1.2 Identify and Engage Stakeholders Stakeholder Assessment
Refer to PM Processes 1.1.3 Engage Project Start-up Team Resource Request/Roster
"3.0 Execute Project" 1.1.4 Develop Start-up Work Plan Work Plan for Initiation
and "4.0 Control
1.2 Establish PM 1.2.1 Establish Project Control File Project Control File Setup
Project" for processes
Infrastructure 1.2.2 Establish Project Procedures Procedures/Logs Started
such as "Maintain
Project Records" or 1.3 Define the Develop Initial Charter/Enhancement
1.3.1 Commitment Level Charter
"Conduct Status Project Request
Reviews" for process 1.3.2 Develop Project Approach Methodology/Approach
steps that must be
carried out across all 1.3.3 Develop Quality Mgmt Plan Quality Mgmt Plan
five PM Processes 1.3.4 Develop Communications Plans Communications Plan
(Initiate, Plan, Control, 1.4 Develop High 1.4.1 Develop High-Level WBS Initial Work Breakdown
Execute, Close). Level Work 1.4.2 Develop Dependency Network Dependency Network
Plan
1.4.3 Estimate Effort High Level Estimates
1.4.4 Develop High-Level Schedule High Level Schedule
1.5 Complete 1.5.1 Complete Initial Risk Assessment Risk Assessment/Plan
Investment 1.5.2 Develop Initial SOW SOW
Analysis
1.5.3 Confirm/Refine the Business Case Financial Scope
1.6 Confirm 1.6.1 Confirm Requirements/BOV Bus. Owner View Signoff
Readiness to
Proceed Obtain Initial Charter/Enhance. Req.
1.6.2 Charter Approval Signoff
Sign-off
Purpose The purpose of this process step is to ensure that the project is ready to start by
confirming that a record exists for the project in ITMS, RMS and MRS, an initial SOW
has been prepared and forwarded to the ADS Business Office, funding has been
provided and that required inputs are available. Required inputs include the
following:
• The original proposal or application change request(s) that precipitated the
project.
• The high-level business case that was used to justify initial funding for the
project (not applicable if the project is the result of change requests being
bundled into a project that will lead to a new application release.
• A Project Scalability Questionnaire that provides a relative sizing for the
project.
• Where appropriate, a Program Charter (i.e., where the project is part of a
larger initiative or program).
Trigger The project has been selected and a project manager has been assigned.
Process Tasks
1 Confirm creation Confirm that the Project Appropriation Request / PAR has been PM,
of Project created and approved. PracticeMgr,
Appropriation FinanceAnal
The primary purpose of the appropriation system is to control the
Request Company's expenditures for fixed assets including capitalized
facilities and tooling as well as items of fixed asset nature (such as
leases with greater than one year payment commitments) even
though they may be expensed for accounting purposes. Company
management exercises control of the appropriation system by means
of the Corporate Cash Flow, the quarterly forecast of facility and
tooling spending, and the review of individual funding requests. The
principal document in the review of individual funding requests is the
appropriation request, and is intended to provide management with a
10 Schedule Initial The Project Manager schedules a meeting with the assigned PQA. PM
Meeting with
PQA Consultant
11 Prepare PQA If the PM and NLM feel that the project should be exempt from PQA PM,
Waiver form reviews and involvement, a PQA Wavier form must be completed. NLM,
PQA
Tools/Techniques Summary
Methods and Applications/Tools
ITMS: http://www.itms.ford.com/ Refer to the ITMS tutorials on the same web site for instructions in the use of ITMS
Project Appropriation Request / PAR description located in Procedure 55-10-10 of the Ford Financial Manual which is at
http://www.dearborn.ford.com/fm/accntng/apfund55/apfprc55/5510/551010.html
MRS User and Quick Reference Guides are located at http://www.ads.ford.com/mrs/documentation.htm.
An IT Systems Quick Reference For Project Managers and Application Managers is located at
http://www.itonline.ford.com/sdm/docs/Templates/245_IT_Systems_Quick_Reference_For_Project_Managers_and_Application_
Managers.doc
Purpose To ensure project success, the project manager needs to identify stakeholders early
in the project life cycle, determine their needs and expectations, and manage and
influence those expectations over the course of the project.
Project Stakeholders are individuals , groups, or organizations that are actively
involved in the project, or whose interests may be positively or negatively impacted
as a result of the project. Stakeholders include, but are not be limited to:
• The Project Sponsor or Sponsors, who provide funding and direction
• The Customer, who approves requirements, plans and deliverables
• Functional Managers of organizations that are impacted by the project
• End Users, who will use the product or service when it is delivered
• Suppliers, who will be impacted by/use the product or service
• Any organization involved in project review, approval or administrative
processes, including Process Quality Assurance
• Full-time and part-time project team members who define and produce project
deliverables
• Representatives of the support functions that implement, train end users, and
maintain the project deliverable
The outputs of stakeholder analysis are used to develop project schedules and
communications plans.
Trigger The project has been selected and a project manager has been assigned.
Process Tasks
1 Identify Work with the Business Analyst to identify and classify key PM,
Stakeholders stakeholders . Use the project proposal and concept documents as BusA
input to the process.
2 Record Use the Stakeholder Assessment Matrix template to record the PM,
Information following: BusA
About Key
Stakeholders Organization: Identify the organization represented by
the stakeholder
Name: Provide the name of the stakeholder
CDSID Provide the CDSID of the stakeholder
Phone: Provide the phone number of the
stakeholder
Reports To: Identify to whom the stakeholder reports
Availability Record the stakeholder’s availability as a
percent of time available or as specific
dates, if known.
Role on Project: Describe the stakeholder’s role on the
project.
Importance to the Assess the stakeholders importance to the
Project: project as H- High, M- Medium, or L- Low
Engagement Briefly describe the strategy for engaging
Strategy: and communicating with the stakeholder.
3 Use Use the stakeholder information to assess risk, develop the charter, PM
Stakeholder plan meetings, and develop communications plans.
Information to
Plan Project
Tools/Techniques Summary
Methods and Applications/Tools
Interview with Sponsor/Business Analyst
Microsoft Word
Inputs to Process Outputs Recipients
241_Project_Proposal.doc 201_stakeholder_assessment_template.doc ESpon,
231_Scalability_Classification_Questionnaire BusA
Org Charts (if available)
Purpose The extent to which the project team has been defined at the beginning of the project
may vary. At a minimum the manager for the project and individuals who can provide
support in preparing for the project should be identified. This might include
representatives of activities responsible for implementing and supporting project
deliverables and other subject matter experts who represent both business and
technical concerns.
During project initiation, the project concept documents are reviewed to determine
the roles required to staff the project. With the help of appropriate stakeholders (i.e.,
the sponsor(s), program manager, and business analyst), the project manager
should identify the roles that are needed to define the project and the names of
individuals who will fill those roles.
As the project progresses and more is known about project deliverables and timing, it
may be necessary to identify and take on additional roles and resources. It is up to
the project manager to ensure that these needs are recognized and addressed.
Trigger The project has been selected and a project manager has been assigned.
Key Considerations The key considerations when identifying team members are
• What knowledge/skills are needed to define the project?
• What knowledge/skills are needed to define requirements?
• What knowledge/skills are needed to define the solution?
• What knowledge/skills are needed to produce deliverables?
• What knowledge/skills are needed to validate deliverables?
• What knowledge/skills are needed to enforce standards?
Process Tasks
1 Identify Skills Create a two dimensional matrix. List the skills/knowledge needed on PM,
Needed the project – particularly in early stages – down one side. BusA
2 Identify List the potential team members across the top of the matrix. PM,
Candidates BusA
3 Map Skills to Mark the intersection between skills/knowledge and each candidate. PM,
Candidates Identify and close gaps. BusA
4 Obtain Request and engage resources required. PM,
Required Sponsor
Resources
5 Create a Team Create a team roster identifying team members, their home PM
Tools/Techniques Summary
Methods and Applications/Tools
Skills needs assessment
Microsoft Word
Resource Request located at http://www.ads.ford.com/resman/
Purpose Most of the work that goes on during the first stage of a project is exploratory in nature.
The goal is to understand what needs to be done so that detailed plans can be
developed to specify how and when it will be done. Therefore, at the end of project
initiation, it is expected that the team will have a more detailed, but still high level work
plan for the remaining stages. In the meantime, a plan is needed to direct the activities
leading to this outcome.
Trigger The project has been selected and a project manager has been assigned.
Key Considerations The key considerations for developing the Initiation work plan are
Process Tasks
1 Identify Identify the activities in project initiation, including those outlined in this PM
Activities in process guide and any activities identified for the solution delivery
Initiation methodology (if known).
2 Identify Use the stakeholder Matrix and Team Roster to identify participants. PM
Participants
3 Estimate Determine the availability of participants and estimate the duration of PM
Duration activities.
4 Develop Develop and publish a schedule detailing the timing of activities and PM
Schedule assignments.
Tools/Techniques Summary
Methods and Applications/Tools
MS Project
Purpose Maintaining information about the project in an organized fashion facilitates new
team member transition and creates a central point of reference for those
developing project deliverables. Most importantly, it provides an audit trail
documenting the history and evolution of the project -- documents produced,
decisions made, issues raised and resolved, and correspondence exchanged.
Trigger The project has been selected and a project manager has been assigned.
Process Tasks
1 Establish Project Decide how project records will be kept and where. The types of PM
Control File records to be maintained include, but are not limited to the following:
Tools/Techniques Summary
Purpose The purpose of this step is to ensure that project management procedures are
established and communicated to the project team and stakeholders. This includes
control logs, procedures for collecting status reports from team members and
incorporating that information into status reports to be provided to team members and
stakeholders.
Trigger The project has been selected and a project manager has been assigned.
Process Tasks
1 Establish Using eTracker or MS Office files set up control logs for Issues, Risk PM
Project Logs and Change Management.
2 Identify SCM On software projects, identify and document any pre-existing PM,
Constraints constraints (e.g.; global requirements) with respect to software SCM
configuration management (SCM) products and procedures.
Note: For pre-existing applications, the current SCM plan is an input to
this activity. For new applications, the SCM plan will be developed as
part of the solution development process.
3 Communicate Communicate procedures for submitting change requests and PM,
Change identifying new issues and risks to project team members and BusA,
Procedures stakeholders Espon,
Cust
4 Communicate Communicate how status reports will be collected from project team PM,
Status members and the frequency of meetings conducted to review that Team
Reporting status. Ensure that team members understand what information they
Procedures must provide and when
5 Establish Team Establish team meetings to review issues, risks, change requests, and PM,
Meetings progress. Weekly meetings are recommended. Establish a regular Team
time and place, agenda and procedure for capturing meeting minutes
6 Establish Establish regular meetings with the Project Sponsor to review issues, PM,
Sponsor risks, change requests that require Sponsor signoff and project BusA,
Meetings progress. Monthly meetings are recommended. Establish a regular Espon,
time and place, agenda and procedures for capturing meeting minutes Cust
7 Communicate Communicate procedures for submitting normal and emergency logical PM,
Database data model, physical data model and database change requests. Team,
Change DBA,
Request DArch
Procedure
8 Establish If performing Package Product Selection and Implementation / PPSI, PM,
approach for the team will have to establish approach for logging defects and Team
logging defects
Tools/Techniques Summary
Methods and Applications/Tools
eTracker can be used to created the required logs, see http://www.etracker.ford.com or logs can be created in Word. See outputs
below for the Work templates available.
Inputs to Process Outputs Recipients
Project Control File http://www.etracker.ford.com Control File
09_SCM_Plan.doc (for existing applications) 212_risk_management_log.doc
213_issue_log.doc
211_change_request_log.doc
210_change_request_template.doc
220_meeting_minutes_template.doc
221_weekly_status_report_template.doc
Database Change Request
http://www.its.ford.com/as/dmts/lob/cgi-
bin/dbchgreq.cgi
Purpose The project charter or enhancement request is a critical tool for managing the
expectations of the project sponsor(s) and other stakeholders. Its purpose is to
help the project manager:
Trigger The project has been selected and a project manager has been assigned.
Process Tasks
1 Review Review the project proposal, business case, and concept profile PM,
Existing delivered with the project assignment and any existing documentation BusA,
Information to understand the project’s purpose. Team
2 Identify Project Identify the goals and objectives of the project. Project goals and PM,
Goal & objectives should align with the goals and objectives of the Sponsor,
Objectives organization and that of the program to which the project belongs (if BusA,
applicable). By definition, a project should have only one goal and Team,
4 Identify Describe the key aspects of the project that are believed to be true, but PM,
Assumptions should be expressly stated to ensure validity and concurrence, BusA,
including items that should already in place. Team
5 Define Risks Identify the high probability/high impact risks factors that may PM,
jeopardize a successful project outcome and their mitigation strategies BusA,
and contingency plans (to be completed after the Investment Analysis Team
is completed below).
6 ID Related Identify other projects that will impact your project. Include projects PM,
Projects that are in progress and those that are planned. BusA
7 Describe The Describe the project organization, including key roles and PM
Project responsibilities and the identities of individuals assigned to those roles,
Organization if known.
8 Describe Describe, at a high-level, the solution delivery methodology chosen PM
Approach and the project management approach (to be completed after the
"Define Project Approach" process is completed (below).
Tools/Techniques Summary
Methods and Applications/Tools
Facilitated Sessions and Interviews
Microsoft Word
Inputs to Process Outputs Recipients
242_business_case.xls 200_project_charter_template.doc Control File,
231_Scalablity_Classification_Questionaire.doc 230_enhancement_and_small_project_request_template Project Sponsor,
243_program_charter.doc ∗ 231_Scalablity_Classification_Questionaire.doc BusA,
241_Project_Proposal.doc Team,
Stakeholders
Existing documentation, if any
∗
A program charter will be provided if the project is part of a larger initiative or program.
Trigger Key sections of an initial charter have been drafted, including the project goals
and objectives and scope.
Key • When selecting the methodology, processes and templates, the project team
Considerations should understand the differences between Classic SDM and Unified SDM.
See the If the team is not familiar with both methods, a PQA coach will be able
to present the related concepts for both methodologies and help with the
selection process.
• Developing and refining the Project Approach can occur throughout the project
lifecycle. The process titled "Develop Project Approach" develops the initial
Project Approach, and the process titled "Refine Project Approach" does
refinement.
• Accelerators are proven techniques for delivering value to the Customer
quickly. Examples of accerators include prototyping, co-locating the customer
with the project team, and time-boxing. At this stage in the project lifecycle,
you may not have all of the information you need to select some of the
accelerators that will be appropriate for the project. However, you should know
enough to begin looking at them and selecting the ones that will obviously
apply. The Accelerator Use Plan template can be used as a starting point for
selecting and documenting accelerators that will be used.
Diagram No diagram provided for this process.
Process Tasks
1 Review Review requirements, initial scope definition, and any technology PM,
Requirements decisions made to date. BusA,
Cust,
SysDesAn,
SolnArch,
PQA
2 Review method Review the methodologies available to the team. Note that the PM,
options and 246_Classic_SDM_and_Unified_SDM_Comparative_Overview.ppt BusA,
determine presentation provides a comparison between Classic SDM and Unified Cust,
methodology SDM methodologies. Additionally, the PQA coaches can aid in SysDesAn,
Tools/Techniques Summary
Methods and Applications/Tools
Facilitated Sessions
PQA presentation titled 246_Classic_SDM_and_Unified_SDM_Comparative_Overview.ppt
247_Project_Approach_Questionaire.xls (job aid)
Purpose The purpose of project quality management is to ensure that the project will
satisfy the needs for which it was undertaken. Accordingly, quality
management includes the following:
Quality Planning includes identifying which quality standards are relevant to
the project and how to satisfy them. Incorporating quality standards into project
design is a key part quality planning. For an IT project, quality planning might
include planning a reasonable response time for a system or ensuring that
consistent and accurate information is produced.
Quality Control involves monitoring specific project results to ensure that they
comply with the relevant quality standards while identifying ways to improve
overall quality.
Quality Assurance involves periodically evaluating project performance to
ensure the project will satisfy the relevant quality standards. The quality
assurance process generally involves independent review of project
deliverables and processes (see 4.2.3 Coordinate Quality Reviews below).
Process Tasks
1 Establish Review the deliverables outlined in the Scope section of the Project PM
Completeness Charter. Establish completeness and correctness criteria for
& Correctness determining when each deliverable meets specifications. Use these
Criteria criteria as standards when conducting deliverable reviews.
2 Ensure Quality Ensure the consistency of the work within each deliverable and across PM,
through
Tools/Techniques Summary
Methods and Applications/Tools
Review of initial project charter and the guide for the selected solution delivery methodology.
Microsoft Word
Inputs to Process Outputs Recipients
200_project_charter_template.doc 200_project_charter_template.doc Control File
Solution Delivery Methodology Process Guide 214_project_pqa_plan_template.doc
57_PQA_Review_Checklists.xls
Purpose Plan the way you will communicate to avoid chaos and confusion. Projects
involve the transfer, use and retention of information. The more clearly and
concisely you communicate and manage the information in your project, the
fewer problems you will have. As the following diagram shows, the lines of
communication on project can be very complicated. A well-thought out
communications plan is needed to manage all of these crossing lines of
hierarchy and functional relationships.
Corporate
Executives
IT Customer
Relationship
Managers
Sponsor/Customer
Solution
IT Project Architects Business
Managers Managers
Users
Developers Support
Groups
Process Tasks
4 Refine Plan as Refine the communication plan as project plans are finalized and PM
Needed changes occur.
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word
Purpose A Work Breakdown Structure is a hierarchical representation of the work that needs to be
completed to deliver the product(s) that will satisfy the project’s objectives. It is the single
most important tool for project planning, because it provides a framework from which:
•
The total scope of the project can be described as a summation of the decomposed
elements
• Work activities can be defined and estimated
• Dependencies and iterations can be identified
• Costs and budgets can be established or confirmed
• Time, cost and performance can be tracked
• Responsibility can be established
Trigger Development of an initial charter.
Diagram The diagram below depicts the high-level process flow for this activity.
Decompose &
Sequence
Solution
Delivery Work Activities
Methodology
Note:
The High-Level WBS Ensure
Project generally stops at Yes Completeness
the Activity Level.
Stage
Task
Process Tasks
2 Identify Work Using the project charter, work with team members to review the PM,
Activities project deliverables and identify the work activities required to Team
produce them.
3 Decompose & Decompose the work to the point where a high-level plan can be PM,
Sequence created. Team
Work Activities
During Project Initiation, it may not be possible to develop a task-level
WBS and, in fact, it is not necessary. A WBS that is decomposed
two or three levels will suffice for initial estimates and schedule
development.
4 Ensure Review the breakdown to ensure that all of the work on the project is PM,
Completeness accounted for including Project Management and support activities. Team
5 Record the Use a WBS Worksheet to record the breakdown. If preferred, the PM
WBS breakdown can be entered directly into MS Project.
Note: An MS Project Plan Template has been developed for the
Classic Systems Development Methodology. See Tools/Technique
Summary below.
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word
MS Project
Inputs to Process Outputs Recipients
200_project_charter_template.doc 205_wbs_worksheet_template.doc Control File
230_Enhancement_and_Small_Project_Request 229_Classic_SDM_Work_Plan.mpp * BusA
Team
Purpose In order for the project manager to accurately determine the cost and
duration of a project, a detailed schedule must be created. One of the first
steps in creating that schedule is determining how many activities in the
project are related to one another and the nature of their dependencies.
Process Tasks
Purpose Estimating is the art and science of using historical data, personal expertise,
institutional memory, and the project scope statement to predict the resource
expenditures, total cost, and duration of a project.
Process Tasks
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word
MS Project
Microsoft Excel
Inputs to Process Outputs Recipients
200_project_charter_template.doc 205_wbs_worksheet_template.doc Control File,
230_Enhancement_and_Small_Project_Request 228_Classic_SDM_Estimating_Model.xls BusA,
205_wbs_worksheet_template.doc 229_Classic_SDM_Work_Plan.mpp Team
229_Classic_SDM_Work_Plan.mpp *
Purpose The purpose of this process step is to produce an initial high-level project
schedule with milestones identified.
Process Tasks
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word
MS Project
MRS User and Quick Reference Guides are located at http://www.ads.ford.com/mrs/documentation.htm.
An IT Systems Quick Reference For Project Managers and Application Managers is located at
http://www.itonline.ford.com/sdm/docs/Templates/245_IT_Systems_Quick_Reference_For_Project_Managers_and_Application_Managers.doc
Inputs to Process Outputs Recipients
200_project_charter_template.doc 200_project_charter_template.doc Control File,
230_Enhancement_and_Small_Project_Request 229_Classic_SDM_Work_Plan.mpp BusA,
205_wbs_worksheet_template.doc 230_Enhancement_and_Small_Project_Request Team
229_Classic_SDM_Work_Plan.mpp 232_PQA_Metrics_Project_Sizing_Profile.doc
Project Record in RMS
http://www.rms.ford.com
Project Record in MRS http://www.ads.ford.com/mrs
ITMS Record at
http://www.itms.ford.com/
Purpose There are always risks associated with a project. The purpose of risk
management is to ensure levels of risk and uncertainty are properly managed
so that the project is successfully completed. It enables those involved to
identify possible threats, the manner in which they can be contained and the
likely cost of countermeasures.
Risk assessment is used during project initiation as one of the major criteria in
deciding whether to do a project or not. Here, risk is compared to expected
reward to see if it is worth taking.
Trigger Definition of scope in an Initial Charter and completion the High-Level Plan.
Process Tasks
Threat
• Threat due to changes in nature and/or strategy of
competitors
Capability of Developer or Organization
• Capability of developing organization to perform the task
at hand, including technical or management (project
and/or program management processes, tools and
techniques, and how they fit together).
• Incorporates experience, tools, skills, documented
processes and capacity, influence of external factors such
as strikes, etc.
• Communication planning and execution skills and
resource availability.
• Includes ability of organization to provide adequate
resources (SME’s, BA’s, systems analysts, testers, PM’s,
etc.).
Cost
• Sufficiency of funds allocated for the life cycle of the
system
• Includes errors in cost estimating
Engineering
• Ability of system configuration to achieve program’s
engineering objectives
• Includes test environment, tools, O/S and software
version levels, etc,
Logistics
• Ability of system configuration to achieve logistics
objectives based on system design, maintenance
concept, support system design, and availability of
support resources.
• Ability to provide 24x7 support if developers are
geographically distributed
Manufacturing
• Ability of system configuration to achieve manufacturing
objectives
• Includes manufacturing processes, availability of
manufacturing resources.
Schedule
• The adequacy of the time allocated for the defined tasks
• Includes effects of schedule decisions, errors in
estimating, and external influences such as launch
window (e.g., holiday, or 01-JAN-2000).
• Time to develop and/or approve contracts, Requirements
Specifications, technical specifications, work plans,
charters, and funding.
• Misunderstood schedule dependencies
Technical
• Degree to which proposed technology has been proven
• Reliability of product, product certification
• Reliability / coverage by test tools
• Internal
• Scope changes
External
• Vendor unable/unwilling to perform Year 2000
modifications to systems and/or applications
• Supplier unable to provide goods and/or services as a
result of internal, external or upstream Year 2000
problems
• Changing reporting requirements (e.g.; Government
Compliance and Reporting / Regulatory)
Other common risk factors can be found in the E&Y Risk
Management Strategies job aid (see Tools/Techniques
Summary below).
3 Classify Risk Classify the potential risks into risk categories (e.g., scope, PM,
Factors technology, etc., see Risk Management Log Template). BusA,
Team
4 Assess Impact Evaluate the potential impact of each risk on the project’s PM,
and Likelihood success (High, Medium or Low) and the likelihood that the risk BusA,
will occur (High, Medium, or Low). Team
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word
MS Project
207_risk_strategies_jobaid.pdf
Inputs to Process Outputs Recipients
200_project_charter_template.doc 206_risk_assessment_template.xls Control File,
230_Enhancement_and_Small_Project_Request 212_risk_management_log.doc BusA,
229_Classic_SDM_Work_Plan.mpp Team,
Sponsor
Purpose The SOW serves as the cost baseline for the monitoring and controlling of
the project activity. The budget contained in the SOW can be distributed
across milestones or across calendar periods. Additionally, costs may be
associated with specific deliverables to assess and validate each
deliverable’s value.
Budgeted costs include labor, travel and living expenses, training, facilities,
computing, and other costs that are to be consumed by the project.
During Project Initiation you will be developing a high-level SOW that focuses
mainly on labor costs calculated on the basis of the initial man-hour
estimates and estimated non-labor costs.
Trigger Development of a draft initial charter, high-level plan, and risk assessment.
Process Tasks
4 Enter Summary Record the budget summary data in the Financial Scope PM
Data into the section of the Initial Charter document and the Business
Initial Charter Case.
and Business
Case
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word
Microsoft Excel
Purpose An effective business case must convince management that the investment is
financially sound, realistic for the organization, aligned with other business
strategies, and has a clear course of action for implementing deliverables.
Organizations can avoid wasting time and money on unnecessary projects by
developing initial cost justification criteria in the Project Proposal as part of the
Portfolio Management process and confirm/refine it during the ID & Assess
stage. Not only will a strong business case make project selection and
prioritization more efficient, the business case also serves two additional
purposes: it can provide as a foundation for the project charter and as a
temperature check throughout the project life cycle. The key element of the
business case is the cost/benefit analysis, which must prove that estimated
costs are justified by the anticipated benefits.
Different from a feasibility study, which is often used as a precursor, a
business case emphasizes the opportunity described by long-term goals, and
is supported by specific business objectives, cost and risk analysis
measurements.
Trigger Completion of an Initial Charter, High-Level Plan, Risk Assessment and High-
Level Budget Plan.
Key • Participation in this process by a Financial Analyst who is familiar with the
Considerations business processes in the value chain is essential to creating a
reasonable and accurate business case.
• Organizational benefits and risks may be included in the discussion in
order to show productivity improvement expectations by implementing the
system, but be careful not to overestimate savings by reducing or
redistributing headcount. If associates have multiple responsibilities,
reductions often aren’t possible.
• During the business case development, the benefits should be identified
as being either "qualified" or "perceived" based on the degree of certainty
achieved during the analysis process.
• Six Sigma projects may additionally require the use of a Six Sigma
template for stating the summary business case and a detailed business
case. See the DFSS template titled "DCOV overview with forms.XLS" for
details.
• Numerous references and links on the Ford intranet provide insight on the
business case development process. Enter the string "Business Case" as
the search criteria.
• Reference the introductory section in this guide titled "Project
Authorization Requests and Purchase Orders" for further information on
Project Appropriation Requests / PARs and Purchase Orders POs.
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word and Excel
Note: in addition to the project management templates, the DFSS template titled "DCOV overview with forms.XLS" contains a
summary business case in the "Charter" tab, and a detailed business case on the "Budget Matrix" tab.
Inputs to Process Outputs Recipients
241_Project_Proposal.doc 242_business_case.xls Control File,
BusA,
242_business_case.xls 200_project_charter_template.doc
Team,
200_project_charter_template.doc 56_Process_Capability_Scorecard.xls ESpon,
Finance
230_Enhancement_and_Small_Project_Request SOW located at http://www.ads.ford.com Office,
Stakeholders
206_risk_assessment_template.xls 230_SDM_Enhancement_and_Small_Project_Request.doc
229_Classic_SDM_Work_Plan.mpp 241_Project_Proposal.doc
SOW located at http://www.ads.ford.com PAR at the MEARS website
http://www.finance.ford.com/mears/index2.html
56_Process_Capability_Scorecard
PAR at the MEARS website
http://www.finance.ford.com/mears/index2.html
Purpose The purpose of this process is to ensure that that the initial Requirements
Specification and the business owner view documents have been completed
and reviewed by the Customer.
Note: The initial Requirements Specification and Business Owner View are
work products that are described in the Classic Solution Delivery Methodology.
They are referenced here in the Project Management Guide because of their
importance in assuring project readiness and because they are among the key
deliverables that must be reviewed and approved by the Customer before the
project can proceed.
Trigger Completion of the Initial Charter, High-Level Plan, Investment Analysis, Initial
Business Requirements Specification, Signed Business Owner View
Process Tasks
Tools/Techniques Summary
Trigger Completion of the Initial Charter, High-Level Plan and Investment Analysis
Key The decision to sign the charter is generally made on the basis of the
Considerations following key questions:
• Do expected benefits justify the estimated costs and effort?
• Are there significant risks attached to the project and do they outweigh
potential benefits?
• How important is the project to the business?
• Is the project required to meet regulatory requirements?
• Will the resources and skills required to do the project be available when
needed?
• Can timing constraints be met?
• Does the charter accurately capture the goal and objectives defined by
the Sponsor and key stakeholders?
• Will the deliverables identified meet the Sponsor’s criteria for success?
• If the project is part of a program, is the charter completely aligned with
the program charter?
• Is the Sponsor prepared to commit the end-user resources and business
subject matter experts required to assist the IT project team in
developing the end-product?
Diagram No diagram provided for this process step.
Process Tasks
6 Update Project Update the project record in ITMS, RMS and MRS to reflect PM
Records the status and file documents in project Control File.
7 Notify Notify support activities, the project managers of PM
Stakeholders related/dependent projects, the Practice Manager, the
Portfolio Manager, and the Competency Center Manager of
the results of the charter review.
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word and Excel
MS Project
ITMS – http://www.itms.ford.com/ Refer to the ITMS tutorials on the same web site for instructions in the use of ITMS
MRS User and Quick Reference Guides are located at http://www.ads.ford.com/mrs/documentation.htm.
An IT Systems Quick Reference For Project Managers and Application Managers is located at
http://www.itonline.ford.com/sdm/docs/Templates/245_IT_Systems_Quick_Reference_For_Project_Managers_and_Application_Managers.doc
Inputs to Process Outputs Recipients
02_Requirements_Specification.doc 02_Requirements_Specification.doc Control File,
200_project_charter_template.doc 200_project_charter_template.doc Program Mgr,
204_accelerator_use_plan 230_Enhancement_and_Small_Project_Request ESpon,
206_risk_assessment_template.xls Go/No-Decision Cust,
228_Classic_SDM_Estimating_Model.xls Project Record in RMS Team
229_Classic_SDM_Work_Plan.mpp http://www.rms.ford.com
Support Activities
230_Enhancement_and_Small_Project_Request Project Record in MRS http://www.ads.ford.com/mrs
241_Project_Proposal.doc Updated ITMS Record at Competency
Center
242_business_case.xls http://www.itms.ford.com/
Metrics
56_Process_Capability_Scorecard
SOW located at http://www.ads.ford.com
Solution
Delivery Control
Methodology
Close
Inputs to Plan Project
Overview Project Planning is an iterative process that occurs throughout the project life cycle.
It begins in Initiate Project with the development of the charter and high level plans
and continues in subsequent stages with more detailed planning and adjustments
made to reflect changes and corrective actions.
The process described below picks up where the high level plan that was created in
Initiate Project leaves off. Here, however, the results of analysis and design
activities are used to identify additional planning requirements and create detailed
work plans.
Process Contents
Objective Process Steps PM Deliverable
2.1 Develop 2.1.1 Develop Org Change Mgmt Plan Org Change Mgmt Plans
Project
Management 2.1.2 Develop Procurement Plans Procurement Plans
Note
Plans
Refer to PM 2.1.3 Develop Transition Plans Support and Launch Plan
Processes "3.0
2.1.4 Develop Resource Mgmt Plans Resource Mgmt Plan
Execute Project" and
"4.0 Control Project" 2.2 Refine Work 2.2.1 Refine Project Approach Accelerator Use Plan
for processes such Plans and
as "Maintain Project Budget 2.2.2 Refine Work Plans Baseline Project Schedule
Records" or
"Conduct Status 2.2.3 Refine Risk Management Plans Risk Management Plans
Reviews" for process 2.2.4 Refine Resource Requirements Resource Requests
steps that must be
carried out across all 2.2.5 Refine The SOW Refined SOW
five PM Processes
(Initiate, Plan, 2.3 Confirm 2.3.1 Confirm Requirements Spec Signoff Requirements Signoff
Control, Execute, Readiness to
Proceed Final Charter Approval
Close). 2.3.2 Obtain Final Charter Approval
Signoff
2.3.3 Conduct Formal Kick-off Kick-off Metting
Purpose Organization Change Management (OCM) is a process for managing the human aspects
of implementing major, complex change resulting in value, delivered through the
implementation of stated human, process and technology objectives in support of
business objectives.
OCM activities are warranted when the change is MAJOR, When there is a high COST
of implementation failure, or When there is a high risk that certain human factors could
result in implementation failure.
Trigger The need for engaging in change management has been identified.
Key Considerations • See the process "Develop Organizational Change Management (OCM) Plan" in the
Classic SDM Process Guide.
• The "HR Business Partner" for each organization is responsible for identifying OCM
resources. An OCM overview and the name of the IT HR Business Partner can be
accessed at the IT HR home page at http://www.itonline.ford.com/home/it-prof/it-hr/.
Process Tasks
1 Coordinate Ensure that OCM activities occur. See the Classic SDM Guide for PM
OCM activities details.
Update the work estimates and workplans as appropriate.
Tools/Techniques Summary
Methods and Applications/Tools
MS Project
Organizational Change Management techniques – see http://www.change-management.com/ for articles and books
Inputs to Process Outputs Recipients
200_project_charter_template.doc 200_project_charter_template.doc Control File,
Program Mgr,
230_Enhancement_and_Small_Project_Request 230_Enhancement_and_Small_Project_Request BusA,
215_communication_plan_template.doc 215_communication_plan_template.doc Sponsor
229_Classic_SDM_Work_Plan.mpp 229_Classic_SDM_Work_Plan.mpp
Purpose The procurement plan addresses the methods for the selection and purchasing
of project goods and services. It must proactively identify possible needs for
products and services. It must also establish standards and procedures for:
• Make or buy decisions
Trigger A decision has been made to purchase goods or services on the project.
• Does the organization have the means (staff, money, contract, etc.) to
produce or acquire the product?
Process Tasks
6 Develop Work with Purchasing to put a procurement plan together that PM,
Sollicitation determines how bids in the form of Contract will be solicited from BusA,
Plan potential vendors. Agree on how the final decision will be made Purchasing
(i.e., agree on the criteria that will be used to make the buy
decision.)
7 Make Make the final decision to purchase the goods or services and PM,
Decision BusA,
notify stakeholders as appropriate. Purchasing
8 Establish Work with Purchasing and the Office of the General Council PM,
Contractual BusA,
(OGC) to finalize the contractual arrangements with the vendor. Purchasing,
Agreement OGC
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word and MS Project
Cost/Benefit Analysis – see http://www.mindtools.com/pages/article/newTED_08.htm for brief explanation or
http://www.csd.uwo.ca/courses/CS179/lect8/sld008.htm for online presentation of this topic
Inputs to Process Outputs Recipients
200_project_charter_template.doc Organization-specific procurement plan Control File,
230_Enhancement_and_Small_Project_Request BusA,
Purchasing,
OGC
Purpose The purpose of the transition plan is to outline the steps that will be taken to promote
smooth handover of project deliverables to support activities.
Process Tasks
1 Initiate the Identify the Practice Application Supervisor that will be responsible PM,
Transition for supporting the deliverables produced by the project. Notify that AppSupr,
Process supervisor of the project and schedule an initial meeting to review ImpA
project plans and anticipated transition events.
2 Identify the Identify the transition team members, including their names, roles, PM,
Transition Team cds ids, and phone numbers. AppSupr,
ImpA
3 Schedule Key Identify when key transition events will occur, who will be involved, PM,
Transition Events and what actions will be taken. Transition events include, but are not AppSupr,
limited to the following: ImpA
Tools/Techniques Summary
Key Team members have a stake in the success of the project. Consider the
Considerations following as some of the commitments and understandings needed from
team members:
8 Refine the Refine the Financial Scope and Project Organization sections PM
Project Charter of the Project Charter to reflect the resource management
decisions made.
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word and MS Project
Skills assessment
Resource Request located at http://www.ads.ford.com/resman/
Purpose The purpose of this process step is to refine the Project Approach, including the
project methodology, processes, accelerators, tools & techniques that will be
used to achieve the project objectives. (Typically, revising Project Methodology
from Unified to Classic or vise-versa is not likely to happen.)
The objective of this process is to ensure that the project approach remains
optimal throughout the project lifecycle. The methodology that is used, the
team’s experience, and management philosophy provide guidelines for
establishing the project framework. Some paths through a methodology mandate
a specific approach but, generally, some decisions must be made about the way
the project is to be conducted.
Trigger Signoff of the initial charter, development of project management plans, or the
recognition of a need to change the methodology, processes or templates at any
point in the project lifecycle.
Key • When selecting the methodology, processes and templates, the project team
Considerations should understand the differences between Classic SDM and Unified SDM. See
the If the team is not familiar with both methods, a PQA coach will be able to
present the related concepts for both methodologies and help with the selection
process.
• Developing and refining the Project Approach can occur throughout the project
lifecycle. The process titled "Develop Project Approach" develops the initial
Project Approach, and the process titled "Refine Project Approach" does
refinement.
• Accelerators are proven techniques for delivering value to the Customer quickly.
Examples of accerators include prototyping, co-locating the customer with the
project team, and time-boxing. At this stage in the project lifecycle, you may not
have all of the information you need to select some of the accelerators that will
be appropriate for the project. However, you should know enough to begin
looking at them and selecting the ones that will obviously apply. The
Accelerator Use Plan template can be used as a starting point for selecting and
documenting accelerators that will be used.
Process Tasks
1 Review Review the current Accelerator Use Plan (AUP) and determine if PM,
Accelerator elements need to be updated or added based on information gathered BusA
Use Plan since the initial plan was created.
2 Update User At this stage, you will know about the users and functionality required. PM,
Types Describe/update and prioritize all user types and enter this information BusA,
into the AUP template. Cust
3 Describe Work with the Customer to identify and describe the primary areas of PM,
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word and MS Project
Inputs to Process Outputs Recipients
204_accelerator_use_plan.doc 200_project_charter_template.doc Control File,
200_project_charter_template.doc 230_Enhancement_and_Small_Project_Request BusA,
230_Enhancement_and_Small_Project_Request 204_accelerator_use_plan.doc Cust,
229_Classic_SDM_Work_Plan.mpp 205_wbs_worksheet_template.doc Team
205_wbs_worksheet_template.doc 229_Classic_SDM_Work_Plan.mpp
Purpose The purpose of this process step is to refine and finalize the project work breakdown
structure, dependencies network, estimates, and project schedule. It is also at this time
that resources are assigned to tasks.
Trigger Signoff of the initial charter and development of project management plans.
Process Tasks
1 Refine the Refine the work breakdown structure to reflect information gathered since PM,
Work project initiation. Add or remove activities and take the breakdown to its Team
Breakdown lowest level.
2 Refine Refine the dependency network to reflect task level dependencies. PM,
Dependencies Team
3 Update Update the project schedule to reflect the task-level work breakdown and PM,
Project assign specific resources. Make a note of any tasks for which a specific Team
Schedule individual cannot be identified. You will need to use this information to
refine resource plans and request additional resources.
4 Refine Project Refine project estimates taking new work breakdown and resource PM,
Estimates assignments into consideration. Ensure that adequate contingency is BusA,
baked into task estimates where resources are less skilled or liable to be Cust
distracted by competing responsibilities.
Note: If using the SDM Estimating Model a task level plan will already be
defined. Follow the instructions in that model to adjust estimating factors,
as needed.
5 Generate Update the MS Project Plan to reflect all of the changes identified. If the PM,
Baseline end-date has moved out, use the accelerator use plan and other factors BusA,
Work Plan to determine if the date can be bought back in line by deferring low Cust
priority functionality, adding resources, or other means. Baseline the
schedule when timing and resource issues have been resolved.
6 Update Update the project record in ITMS, RMS and MRS to reflect the updated PM
Project schedule and file documents in project Control File.
Records
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word and MS Project
Inputs to Process Outputs Recipients
Trigger Signoff of the initial charter and development of project management plans.
Process Tasks
5 Confirm Risk Confirm the risk assessment score on the Risk Assessment PM
Rating Checklist and file the refined copy in the Project Control File.
6 Record HH Enter any additional high impact, high probability risks into the PM
Risks in Project Charter.
Charter
7 Address Work Ensure that mitigation strategies and contingency plans are PM
Plan Impacts accurately reflected in the work plan
Tools/Techniques Summary
Purpose The purpose of this process step is to refine resource requirements based on the
information gathered and planning completed since project initiation.
Trigger Signoff of the initial charter and development of project management plans.
Process Tasks
Purpose The purpose of this process step is to refine the budget plan based the refined risk
assessment, baseline schedule, functional requirements, accelerator use plan,
and resource requirements.
Trigger Signoff of the initial charter and development of project management plans.
Key • Only Ford employees are authorized to access the SOW. Non-Ford
Considerations employees should work with their Practice Manager to modify it.
Process Tasks
2 Refine Refine estimates and any non-labor costs. Consider additional PM,
Remaining facilities, equipment, training or travel identified since the initial BusA,
Budget SOW was created during project initiation. ImpA
Elements
4 Summarize Confirm or refine the SOW as appropriate. If changes are required, PM,
Costs submit a new SOW to the ADS Business Office via the SOW BusA,
Workflow process and tool documented at http://www.ads.ford.com. ImpA
The Business Office review the SOW for completeness and
accuracy, then circulate it for signature via the Work Flow Tool.
5 Update the Update the financial scope section of the charter or enhancement PM
Charter request, as appropriate.
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word and Excel
MS Project
Inputs to Process Outputs Recipients
Purpose The purpose of this process is to ensure that the Requirements Specification
has been reviewed and approved by the Customer and that the final charter
accurately reflects the information contained in that specification.
Process Tasks
2 Ensure Ensure that the scope section of the final project charter is PM,
Alignment of aligned to the Requirements Specification. BusA,
Charter Cust
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word
Purpose The purpose of this process step is to ensure that all sections of the project
charter have been adequately addressed and that the final charter accurately
reflects the agreed goal, objectives, scope, project management approach, risk
assessment, and project organization.
Purpose The kick-off meeting marks the formal start of the project. Generally, it is the
first opportunity for the Sponsor or representative to meet with the entire
project team to present a vision of the project, demonstrate support, and
advocate project success. Its importance lies in setting the tone for the project
and in establishing a common understanding of project goals and plans.
The purpose of the Kick-off meeting is to
• Introduce team members
• Communicate project goals and objectives
• Review work methods and tools
• Communicate the roles and responsibilities of team members
• Set direction for the work to be completed
• Address team member questions
• Commit to the success of the project
• Promote team rapport
Key • Key considerations when planning and conducting the meeting include
Considerations
o What decisions must be made before the meeting?
o What information will be distributed to attendees in advance?
o What will be presented in the meeting?
o Who should attend?
Diagram The following diagram shows inputs and outputs for this activity.
Process Tasks
2 Schedule Identify the date, time and place. Reserve the meeting room PM
Kickoff and any presentation equipment required.
5 Conduct the Conduct the meeting, taking notes on any issues raised and/or PM,
Meeting action points BusA,
ESpon
6 Distribute Distribute minutes of the kickoff to attendees and appropriate PM,
Minutes stakeholders who were not in attendance. Admin Support
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word and Excel
MS Project
Inputs to Process Outputs Recipients
200_project_charter_template.doc 218_kickoff_meeting_checklist.doc Control File,
230_Enhancement_and_Small_Project_Request 219_kickoff_meeting_agenda_template.doc BusA,
229_Classic_SDM_Work_Plan.mpp ESpon,
204_accelerator_use_plan.doc Team,
Stakeholders
206_risk_assessment_template.xls
SOW located at http://www.ads.ford.com
201_stakeholder_assessment.doc
203_team_directory_template.doc
215_communication_plan_template.doc
Solution Control
Delivery
Methodology
Close
Overview Project Execution results in the completion of the work identified in plans created
during Project Initiation and Planning. During execution of the project:
• Facilities and supplies are acquired.
Purpose The purpose of this process is to ensure that facilities (e.g., space for a co-
located team) and equipment (e.g., PCs, phones, security badges, etc.) are
acquired.
Process Tasks
1 Obtain Team Request team room(s) or cubicles as appropriate to the location and PM
Facilities resource requirements.
2 Obtain Determine what workstations, network access, shared drives, phones, PM
Workstations eRooms, and other facilities or equipment will be needed and submit
and Other the appropriate requests through the help desk.
Equipment
3 Request Determine if specific software licenses will be required (e.g., licenses PM
Software for MS Project) and submit the appropriate support requests through
the help desk (GIRS). The cost of software should be included in the
SOW.
4 Schedule Ensure that the setup of cubicles, team rooms, equipment and software PM
Facilities, are scheduled and completed on time.
Hardware, and
Software
5 Verify Supplies Verify that adequate office supplies are available and accessible to the PM
team.
6 Verify Verify that team hardware and software are functioning properly before PM,
Tools/Techniques Summary
Methods and Applications/Tools
US ADS Move Request use http://www.ads.ford.com/facilities/
All Other Locations Use Ford Land Move Request at http://www.dearborn3.ford.com/fmls/move/
Help Desk Request
Purpose The timely requisition and development of team members whose skills match the
project’s requirements is vital to project success. As a project progresses, the skills
needed may change. While a core set of team members may remain throughout the
project, other resources may come and go as needed. For example, more experienced
resources (subject matter experts) are particularly important in the early stages of the
project when objectives are being defined and decisions are made on how those
objectives will be met. Later, when plans are firmed, less experienced resources can be
taken on board and directed in the work needed to complete the tasks that have been
defined. It is up to the project manager to identify the resources and skills that will be
required throughout the project and take appropriate action to complete those plans.
Trigger The trigger for this process will depend on the project plan and what that plan says about
the requisition or release of resources in each stage of the project. At this stage, the
trigger will be signoff of the final charter.
• What skills/roles are needed to do the work planned for the current stage?
• What resources are to be released from the project at this point, if any?
• Ford's policy is to eliminate the practice of pre-committing orders because they can
lead to misunderstandings and delays in payments. A pre-commitment occurs
each time your firm is engaged to deliver a good or service without the appropriate
authority to proceed being given by your Ford Motor Company buyer. Pre-
commitments occur when anyone - regardless of level or location, engages a
supplier (in writing or orally) to provide a good or service, directly, without the Ford
Motor Company buyer's involvement, a valid release against a blanket purchase
order or purchase order that includes authorization from the appropriate finance
activity. Purchasing will also have emergency procedures developed to ensure true
emergencies can be handled that may require initial contact by those other than
your Ford Motor Company buyer. As a result, the Ford Purchasing Department
must be included in activities where outside vendors are being contacted for
information, proposals and quotes. See the web site
http://fcas268b.dearborn.ford.com:8050/ for further information.
1 Identify Skills Create a two dimensional matrix. List the skills/knowledge needed on PM,
Originator: One IT PPM Team Page 100 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Needed the project – particularly in early stages – down one side. BusA
2 Identify List the potential team members across the top of the matrix. PM,
Candidates BusA
3 Map Skills to Mark the intersection between skills/knowledge and each candidate. PM,
Candidates Identify and close gaps. BusA
4 Interview Interview candidates. PM
Candidates
5 Obtain Request and engage resources required. Engaging resources PM,
Required includes providing them with background on the project. It may also Sponsor
Resources entail follow through on training plans for resources.
6 Request Direct new employees to the web sites or local support functions that PM,
Badge, Phone they will need to contact to get phones installed and access to the Team
or Move building, printers, and shared drives.
7 Update the Create a team roster identifying team members, their home PM
Team Roster organization, their role, and the amount of time that they will be
available.
8 Orient Team Provide new team members with background on the project and PM,
Members access to any existing documentation. Team
10 Notify Agency Send an MS-Outlook note to the appropriate agency representative 2 AppSupr,
of Upcoming weeks prior to the release and notify him/her that the resource will be Agency
Release of released and the date of the release. Representative
Agency
Resource
11 Notify RMS of Send an MS-Outlook note to cdsid RMSHELP to inform them that the AppSupr
Resource resource will no longer be working on the application and should not
Release bill against it any longer.
12 Perform Exit Follow the instructions at the exit procedure link located at AppSupr
Procedure http://www.ads.ford.com/facilities/. This procedure covers the removal
of application access, building access and other tasks.
Tools/Techniques Summary
Methods and Applications/Tools
US ADS Only Use Following Link for Move Requests http://www.ads.ford.com/facilities/
All other locations use Ford Land Move Request at http://www.dearborn3.ford.com/fmls/move/
Help Desk Request
Resource Request located at http://www.ads.ford.com/resman/
Inputs to Process Outputs Recipients
Originator: One IT PPM Team Page 101 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
200_project_charter_template.doc Resource Request located at Control File,
230_Enhancement_and_Small_Project_Request http://www.ads.ford.com/resman/ Competency Center,
229_Classic_SDM_Work_Plan.mpp 203_team_directory_template.doc Resource Mgmt,
http://www.ads.ford.com/resman/ Move Requests (see Tools Above) Demand Management
203_team_directory_template.doc
SOW located at http://www.ads.ford.com
Originator: One IT PPM Team Page 102 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Process Tasks
1 Assign Tasks to Ensure that team mem bers are aware of assignments including PM,
Team Members those added after the plan is baselined to deal with issues, risks, and Team
change requests. Also ensure that team members have a say in the
amount of time they are given to complete tasks. Solicit team
member input when estimating the duration of added tasks (i.e.,
tasks added in response to issues, risks, and scope changes that are
identified after the plan is baselined.)
2 Ensure Provide stakeholders who are outside the core team with a copy of PM,
Stakeholders the plan so they understand what is expected of them over the life of Stakeholders
Understand their the project. Stakeholders include, but are not limited to the Sponsor,
Role lead Customer, Business Analyst, and other subject matter experts
whose input will be required at various points over the project life
cycle.
3 Execute Project Ensure that tasks that rightfully belong to the Project Manager are PM
Manager Tasks carried out per the project plan.
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word and Excel, MS Project
RMS-- http://www.rms.ford.com
Inputs to Process Outputs Recipients
229_Classic_SDM_Work_Plan.mpp 229_Classic_SDM_Work_Plan.mpp Control File,
201_stakeholder_assessment_matrix.doc ESpon,
203_team_directory_template.doc BusA,
Timesheets http://www.rms.ford.com Cust,
210_change_request_template.doc Team,
Other Stakeholders
211_change_request_log.doc
212_risk_management_log.doc
213_issue_log.doc
Originator: One IT PPM Team Page 103 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Process Tasks
Tools/Techniques Summary
Methods and Applications/Tools
Originator: One IT PPM Team Page 104 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Microsoft Word and Excel
MRS
ITMS – http://www.itms.ford.com/ Refer to the ITMS tutorials on the same web site for instructions in the use of ITMS
RMS – http://www.rms.ford.com
MRS User and Quick Reference Guides are located at http://www.ads.ford.com/mrs/documentation.htm.
An IT Systems Quick Reference For Project Managers and Application Managers is located at
http://www.itonline.ford.com/sdm/docs/Templates/245_IT_Systems_Quick_Reference_For_Project_Managers_and_Application_Managers.doc
Inputs to Process Outputs Recipients
Timesheets http://www.rms.ford.com Updated project records Control File,
221_weekly_status_report_template.doc 221_weekly_status_report_template.doc Stakeholders
210_change_request_template.doc 210_change_request_template.doc
211_change_request_log.doc 211_change_request_log.doc
212_risk_management_log.doc 212_risk_management_log.doc
213_issue_log.doc 213_issue_log.doc
212_risk_management_log.doc Project Hours http://www.rms.ford.com
Originator: One IT PPM Team Page 105 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Purpose A successful project is one that meets its objectives through appropriate
methods and means of collecting and distributing project information. Project
Communications Management provides the critical link among people, ideas,
and information. Everyone involved in a project must be ready to send and
receive communications and must understand how the communications affect
the project as a whole. The purpose of this process is to ensure that this
distribution of information occurs in a timely fashion and according to the project
communication plan.
Trigger Generation of the weekly status reports, the completion of a stage gate, at a
planned point in the communication plan, or at any other critical decision point
that occurs during the life of the project.
Diagram The following diagram shows where Information Distribution fits into the overall
communication management process.
Process Tasks
Originator: One IT PPM Team Page 106 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word
Email
Meetings
eRoom
Web Sites
Inputs to Process Outputs Recipients
201_stakeholder_assessment_template.doc 221_weekly_status_report_template.doc Control File,
203_team_directory_template.doc Results of reviews Stakeholders
215_communication_plan_template.doc Approval to Proceed
See also the SDM Process Guide
Originator: One IT PPM Team Page 107 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Originator: One IT PPM Team Page 108 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Close
Inputs to Control Project
Overview The Project Management Institute (PMI) defines Project Control as follows:
Monitoring and controlling the project also involves proactive management of scope,
risks, quality, and issues and project reviews to ensure that stakeholders are satisfied
that the project will succeed and should continue as planned.
Process Contents
Objectives Processes Key Deliverables
4.1 Monitor and 4.1.1 Monitor and Control Scope Change Requests/Log
Control the
4.1.2 Monitor and Control Schedule/Costs Updated Plans
Project
4.1.3 Monitor and Control Risks Risk Management Log
4.1.4 Monitor and Control Issues Issues Resolution/Log
4.1.5 Monitor and Control Quality Checklists and Metrics
4.2 Conduct 4.2.1 Conduct Status Reviews Status Reviews
Project 4.2.2 Coordinate Architecture Reviews Architecture Rev. Results
Reviews
4.2.3 Coordinate Metrics Workshops Function Point Counts
4.2.4 Coordinate Security Rev/Certification ACR/ICR/Cert. Results
4.2.5 Coordinate PQA Reviews Results of QA Reviews
4.2.6 Lead Gate Reviews Go/No-Go Decisions
4.2.7 Support Operations Reviews Input to Ops Reviews
Originator: One IT PPM Team Page 109 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Purpose The purpose of Scope Control is to protect the viability of the approved project
plans and deliverables. Scope changes can be caused by business changes,
technical changes, requirements that were missed or not known when the
project was funded, and errors or omissions in design.
Trigger Submission of a new project change request and the monitoring of change
requests during weekly status reviews.
Originator: One IT PPM Team Page 110 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Process Tasks
1 Log New Change Ensure that the change request has been submitted on the Stakeholders
Request appropriate form and that sufficient details have been provided to
allow for assessment.
Note: All changes are to be logged, even small ones.
2 Group Requests Review change log to determine if other similar or related requests PM,
are outstanding. Group requests, if appropriate. Team
3 Schedule Assign a resource to investigate the request and add that effort to PM
Investigation the project schedule, as appropriate.
4 Investigate the Investigate the change and its potential impact on project Team
Change Request objectives, resources, budget and schedule, and any related
projects. Estimate the effort to complete the change and determine
if additional funding and/or resources/skills will be required.
5 Recommend a Based on the investigation recommend a course of action. PM
Course of Action
• Reject or defer the request
6 Obtain Approvals Any request that requires a change in the approved deliverables, PM,
resources, budget or end-date, a new project, or the use of project ESpon,
reserves must be approved. Recommendations to defer or reject Program Mgr
changes that have been submitted by the intended recipients of BusA,
deliverables should also be reviewed and signed off by the Cust
Customer and Sponsor.
7 Update Project Update project records and work, resource, budget plans, and PM
Records and SOW as appropriate. This includes updating the project record in
Plans ITMS, RMS and MRS.
8 Request Submit a resource request if additional resources are required and PM
Resources approved to complete the change.
9 Close the Notify the stakeholder who submitted the request of the decision to PM
Request & complete or reject the change request. Notify other stakeholders as
Communicate appropriate (e.g., the Project Mangers of related projects)
Status
Originator: One IT PPM Team Page 111 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Tools/Techniques Summary
Methods and Applications/Tools
eTracker – see http://www.etracker.ford.com/
ITMS – http://www.itms.ford.com/ Refer to the ITMS tutorials on the same web site for instructions in the use of ITMS
Project Record in MRS http://www.ads.ford.com/mrs
Resource Request located at http://www.ads.ford.com/resman/
MRS User and Quick Reference Guides are located at http://www.ads.ford.com/mrs/documentation.htm.
An IT Systems Quick Reference For Project Managers and Application Managers is located at
http://www.itonline.ford.com/sdm/docs/Templates/245_IT_Systems_Quick_Reference_For_Project_Managers_and_Application_Managers.doc
Inputs to Process Outputs Recipients
229_Classic_SDM_Work_Plan.mpp 210_change_request_template.doc ESpon,
210_change_request_template.doc 211_change_request_log.doc Program Mgr,
211_change_request_log.doc Resource Request located at BusA,
02_Requirements_Specification.doc http://www.ads.ford.com/resman/ Stakeholders,
213_issue_log.doc Project Record in MRS http://www.ads.ford.com/mrs Competency Center,
229_Classic_SDM_Work_Plan.mpp Resource Mgmt,
212_risk_management_log.doc Demand Mgmt
SOW located at http://www.ads.ford.com 213_issue_log.doc
Logs listed or logs in eTracker
SOW located at http://www.ads.ford.com
Originator: One IT PPM Team Page 112 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Trigger This process is triggered by weekly status reporting, or whenever a problem is noted in
the timing or costs of the project.
Key The questions/issues that need to addressed during this process are:
Considerations • Is the project ahead of or behind schedule?
• Has spending exceeded the budget plan?
• What are the root causes of schedule or cost variances?
• Will the scope of the project be impacted by proposed corrective actions?
Diagram The diagram below depicts the high-level process flow for this activity.
Process Tasks
1 Assess Determine project status and spending in relation to the approved plans. PM,
Schedule & Assemble pertinent materials, including the most recent weekly Team
Cost timesheets, expense reports, the current approved Project Plan and
Performance Budget, and any other documents that provide quantifiable data.
Determine if the work is on track, ahead of plan, or behind plan, based on
the resources spent (the burn rate) and the progress made. Assess
resource utilization to determine if resources have worked to the level
agreed. Review expenses to see if they are in line with the budget plan.
2 Analyze Analyze variances to determine their root causes and assess their impact PM
Variances on baseline plans. Use Earned Value Analysis to calculate the project’s
SPI (Schedule Performance Index) and CPI (Cost Performance Index).
Determine if the variances warrant taking corrective action.
Originator: One IT PPM Team Page 113 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
6 Obtain Get signoff on actions that will alter the current approved schedule, budget PM,
Approvals or resource plan. If the schedule is changed, the Project Manager needs Sponsor
(as to notify the Competency Center. The resource's agency must approve the
Required) change. Update ITMS, SOW and record in RMS.
7 Update & Update project plans, as appropriate, and update and close the issue. PM
Close Issue
Tools/Techniques Summary
Methods and Applications/Tools
http://www.etracker.ford.com/
Earned Value Analysis see http://www.ads.ford.com/eva/
MS Project
Resource Request located at http://www.ads.ford.com/resman/
Originator: One IT PPM Team Page 114 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Purpose The goal of risk management is to ensure that risks are identified, analyzed, monitored
and controlled, proactively. Risks are factors that have the potential to interfere with
successful completion of a project. Risks are not issues – issues have already occurred,
whereas risks may or may not occur. By addressing risks as soon as they are identified,
the project team can assess their potential impact on the project and develop plans to
manage them.
Note: This process follows the initial risk assessment that is completed during Initiate
Project and the development of risk management strategies that is completed during Plan
Project. However, is assumed that additional risks may be identified during project
execution and control. For this reason, the entire risk lifecycle is described here, including
risk identification, analysis and planning.
Trigger This process is triggered by weekly status reporting, or whenever a new risk is identified.
Key Considerations Some questions to be addressed in identifying and controlling project risk are:
Diagram The diagram below depicts the high-level process flow for this activity.
Yes
No Risk
Resolved
?
Yes
Process Tasks
Originator: One IT PPM Team Page 115 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
1 Identify and Log Identify a new Risk and log it into the Risk Management Log. Stakeholders
Risk Note: Most project risks should have been identified during
Project Initiation as part of the Initial Risk Assessment. Those
risks along with any new ones identified over the course of the
project will be monitored and controlled here to ensure that
mitigation strategies and contingency plans are effective.
2 Analyze Risk Work with project team mem bers to transform risk data into PM,
decision-making information. Categorize the risk in terms of how Team
it impacts the project. Determine the level of impact of each risk
(High, Medium or Low), the probability that each risk will occur
(High, Medium or Low). Estimate the impact that the risk might
have on costs, effort, timing, and benefits.
3 Develop Plans to Identify mitigation strategies (strategies to help minimize or avoid PM,
Manage the risk) and develop contingency plans (plans to go into effect if Team
mitigation strategies should fail). Ensure that mitigation actions
are incorporated into the project plans, as appropriate
Note: The E&Y Risk Management Strategies Document provide
suggested mitigation strategies for many common risk factors.
4 Track & Control Risk Review actions against plan to determine if mitigation strategies PM,
are working. Institute contingency plans if necessary or develop Team
new strategies to manage the risk.
5 Raise Issue Where risk management strategies are not working, raise an issue PM,
for immediate action. Team
6 Close Risk & Close risks that are no longer a potential threat to the timing, cost PM
Update Plans or quality of project deliverables or risks that have been converted
to an issue.
Tools/Techniques Summary
Methods and Applications/Tools
MS Project
Inputs to Process Outputs Recipients
206_risk_assessment_template.xls 206_risk_assessment_template.xls Sponsor
212_risk_management_log.doc 212_risk_management_log.doc Program Mgr
207_risk_strategies_jobaid.pdf 213_issue_log.doc or eTracker located at BusA
http://www.etracker.ford.com/
229_Classic_SDM_Work_Plan.mpp Sponsor
Originator: One IT PPM Team Page 116 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Purpose An issue is an immediate problem that will be detrimental to the success of the
project if it is not resolved quickly. If there is no urgency to resolve the issue or
if the issue has been active for some time, then it may not really be an issue. It
may be a potential problem (risk), or it may be an action item that needs to be
resolved at some later point. Issues, by their nature, must be resolved with a
sense of urgency.
The resolution of an issue usually requires the assignment of one or more
action items. Each action item should have a responsible person and a due
date clearly identified. The Project Manager should have an activity in the work
plan every week to follow-up on issues to ensure they are diligently resolved.
Diagram The diagram below depicts the high-level process flow for this activity.
Issue Weekly
Identified Status
Review
Resolve or
Log Issue Assign To Updated
Escalate
Resource for Work Plan Issue
Resolution
Yes
Yes
Submit Change Request
Originator: One IT PPM Team Page 117 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Process Tasks
1 Identify & Log Identify the issue and supply the following information to assess it Stakeholders
Issue properly:
Description A description of the issue
Level of Issue An assessment of the issues overall
potential impact: High, Medium or Low
Impact of Issue The estimated impact of the issue on costs,
effort, timing, and gross benefits, if known.
Proposed A proposed resolution or plan of action if
Solution known.
Comments Any other comments that will help the
Project Manager assign or escalate the issue
Note: Anyone involved in or impacted by the project can submit an
issue, including team members, users, support functions, etc.
2 Assign for Assign the issue for further investigation and resolution. Identify a PM,
Resolution due date and enter the information into the Issue Log (eTracker, if Team
in use). Update the work plan to reflect the new assignment.
3 Develop Develop a resolution strategy and review it with the project team. PM,
Resolution Determine if the strategy will require a change in the project scope. Team,
Strategy If it does, close the issue, submit a Change Request and manage BusA,
accordingly. Cust
4 Monitor Issue Review the status of the issue in weekly project status review PM
Status meetings.
5 Resolve or Resolve the issue within the project team or escalate it to the PM,
Escalate the Sponsor, Program Manager, or Business Analyst. Team,
Issue BusA,
ESpon
6 Close Issue Close Issues that are resolved and update the log entries PM,
accordingly. Team
Tools/Techniques Summary
Methods and Applications/Tools
http://www.etracker.ford.com/
MS Project
Inputs to Process Outputs Recipients
229_Classic_SDM_Work_Plan.mpp Issues in 213_issue_log.doc or Control File,
213_issue_log.doc eTracker Program Mgr,
02_Requirements_Specification.doc 229_Classic_SDM_Work_Plan.mpp BusA,
35_Quality_Control_Plan_and_Test_Strategy.doc or 210_change_request_template.doc ESpon,
89_QC_Plan_and_Test_Strategy_for_Enhancement_and_Support 211_change_request_log.doc Team
Originator: One IT PPM Team Page 118 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Purpose The primary purpose of quality control is to keep errors out of the hands of the
Customer through prevention (keeping errors out of the process) and inspection
(finding and removing errors from deliverables). Quality control is performed to
ensure that the product and interim deliverables are acceptable. Quality Control
consists of technical inspections and tests. Quality control should be performed
incrementally throughout the project life cycle so that defects (errors and
omissions) can be identified and rectified as early as possible.
Trigger Project deliverable ready for inspection and weekly status reviews.
Key As shown on the diagram below, which depicts the relative cost of addressing
Considerations defects over the life of the project, the earlier in the life cycle a defect is found,
the less costly it is to correct.
120
100
80
60
40
20
0
Analysis Design Build
Implement
Source: International Institute of
Learning
Diagram The diagram below depicts the high-level process flow for this activity.
Methodology/ Yes
Quality
Standards
Monitor Record Results
Process & Results Acceptable
Deliverables ?
Project Plans
& Deliverables
No
No
Originator: One IT PPM Team Page 119 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Process Tasks
1 Monitor Process Inspect deliverables and monitor the performance of required PM,
& Deliverables processes. Team
Inspections include activities such as measuring, examining, and
testing undertaken to determine whether deliverables conform to
requirements.
Monitoring of the process involves the use of checklists and
reviews to confirm that the process is being followed. It also
involves the use of control mechanisms to monitor cost and
schedule variances (earned value reports), the volume and
frequency of changes (change logs), the timely resolution of issues
(issues management logs), and other management results that
help determine that the process is in control and, thereby, that
quality is control.
2 Record Results Capture results on acceptance documents, control charts, trend PM,
analyses, checklists, and defect or incident reports, as appropriate. Team
Maintain records for use in project reviews.
3 Identify Issues Where defects or unacceptable results have been identified, PM,
and Determine determine what course of action is required. Defects in Team
Course of Action deliverables must be corrected before moving on. Failure to
complete some process steps or adhere to standards may also
require rework or the improvement of some deliverables.
4 Complete Schedule and complete any rework or improvement required. PM,
Rework or Team
Improvement
Originator: One IT PPM Team Page 120 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Yes
No Will it be addressed in
the current release? No Convinced with Yes
this resolution?
Yes
New
Defect Current/New/ Defect Still Exists
A
Old found?
Defect Closed
The defect is Root Cause Change
deferred, Status=“Closed” Status=“Reopen” Done Follow the Change Management
Status=“Deferred” Process
1 Log Defect Enter the defect in TestDirector as 'New' and categorize the Person who found
defect (e.g.; Critical, Serious, Moderate, Cosmetic). the defect
Note: test status should be sent on a periodic basis to the Project
Manager, usually after the completion of a logical group of tests
or at suitable intervals
2 Analyze Defect Analyze the defects reported and change their status to either - PM,
'Open', 'Deferred' or 'Reject'. LDevl,
QCTest
If 'Reject' or 'Deferred', specify in the 'R&D Column' on why it is
being rejected or deferred. If defects are 'Opened', assign them
for correction/fixing
3 Correct Defect Correct the defect. Using the configuration management system SDevl
(e.g.; PVCS, ChangeMan, etc.), check the corrected deliverable
back into the source control area and change the status of the
defect in TestDirector from 'Open' to 'Fixed'. Also enter the 'Root
Cause' of the defect (e.g.; Requirements, Design, Coding, Data,
database, Environment, Configuration, Change).
Note: changes to documents as a result of the defect correction
should be logged either in the project issue log or as a change
request.
4 Rebuild Rebuild the deliverable using the configuration management SCM
Originator: One IT PPM Team Page 121 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
application system and "roll it forward" to the QC environment, informing all
the version number of application with a list of defect-IDs fixed
5 Confirm Confirm that the application is functioning properly in the QC SDevl
Application environment prior to testing. Make sure that the correct
Readiness deliverable has been rolled to QC environment, and change the
status to 'Rolled'
6 Test Application Update Test Case(s) if necessary. QC Team,
BusA,
Re-run the tests as documented in the TestDirector. Sdevl,
Cust
If the defect is seen again – change the status to 'Re-Open'. (e.g.; who ever
raised the defect)
If the defect is addressed (not seen) – change the status to
'Closed'.
Originator: One IT PPM Team Page 122 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Tools/Techniques Summary
Methods and Applications/Tools
eTracker at http://www.etracker.ford.com/
MS Project
Originator: One IT PPM Team Page 123 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Purpose Status reviews are an important tool in ensuring that project team members,
Customers, sponsors, and other stakeholders are kept informed of progress,
issues, risks, and changes. It is also an opportunity for the team to review the
overall state of the project in relation to the original commitment to determine if
the project is still viable.
Trigger Approval of the initial project charter and high level plan (see Initiate Project).
• Is the project plan sill aligned with external dependencies (i.e., are external
events proceeded as expected)?
• What issues are outstanding and what issues have been resolved?
• What is the status of known risks and have any new risks been identified?
Diagram The following diagram shows the periodic reviews that must be supported,
including PQA and gate reviews at the end of each stage, weekly status reviews
(see items highlighted by red arrows) and various levels of operations reviews
that are conducted on a monthly and quarterly basis.
Originator: One IT PPM Team Page 124 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
IT DIRECTOR
Quarterly From IT Director Ops Reviews
To CBG/GEC
Manager
Exec
During
SDM Project
Stage Architecture Project Status Reviews Reviews
Process Reviews
•ARB Health •Project Cost, Benefit, Timing Health
•Occurs for ID & Assess, •PQA Health
•Occurs for all Stages
Analysis, & Design Stages •Occurs for all Stages
•Many Times per Stage
•Once per Stage •Once per Stage
Process Tasks
1 Schedule Schedule a standing weekly status review meeting with core project PM
Weekly Status participants (the Customer, Business Analys t, and Project Team). If
Reviews appropriate, include the Sponsor and Program Manager in one or more
of those meetings each month. Create a standing agenda.
2 Prepare Prepare the standard weekly status report. Ensure that both the Project PM,
Materials Manager assessment and the Customer assessment are completed. Cust
Gather supporting documents, including Earned Value Reports, and the
results of gate reviews, etc.
The GYR status is defined as follows:
Green: Target dates and/or deliverables are on track.
Yellow: Target dates and/or deliverables are at risk, but a
resourced recovery work plan is available and has been
approved by the appropriate stakeholders
Note: The status can only be returned to GREEN when
the recovery work pan is executed and he risk is
resolved. However, if the recovery work plan is not on
track by the next review and the risk remains, the status
should be changed to RED.
Red: Target dates and/or deliverables are at risk and an
approved recovery work plan is not yet available or the
work plan does not achieve targets. The status remains
RED until an approved work plan is available.
Note: The Weekly Status Report Template calculates the GYR status
based on the percent over schedule or over budget, the significance of
Originator: One IT PPM Team Page 125 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
NO NO NO NO
YES YES
Target dates & NO Recovery YES Recovery YES Recovery Plan YES Recovery on
deliverables are Plan is in Plan is Approved by Track Since
on track Place Resourced Stakeholders Last Review
3 Provide Access Be sure that participants have access to issue, change, and risk logs, PM
to Materials and the most current version of the project plan. Distribute relevant
materials at least 1 day before the meeting or make available to
participants in an electronic folder on shared drive or in an eRoom.
4 Review Status Review and agree on the project GYR status with the team. Analyze PM,
with Participants any Yellow or Red items to determine root causes and agree on an Cust,
action plan to address, accordingly. Team
5 Review Open Review the open items in the Issues, Risk and Change Request Logs. PM,
Issues, Risks Identify work completed and any items that can be closed. Agree on a Cust,
and Change course of action and team assignments for addressing for any new Team
Requests items.
6 Assess Results Review the results of inspections, testing, technical reviews (see PM,
of Quality section 4.2.4) and the most recent gate review to determine if the Cust,
Controls project is adhering to quality standards. Make assignments, as Team
necessary, to deal with any issues identified.
7 Review Team Allow each participant to provide a brief report out on work in progress. Team
Assignments Work with the team to determine if additional help is needed or other
corrective measures are warranted.
8 Assess Viability Look at the actual work completed in comparison to the project plan to PM,
of the Project determine if the business case is still valid. Determine if anything has ESpon,
changed since the project started that would invalidate the assumptions Program Mgr,
made in the goals and objectives. Review forecasts of project Cust,
completion and costs to determine if the project will deliver to promise. Team
Tools/Techniques Summary
Methods and Applications/Tools
eTracker at http://www.etracker.ford.com/
Earned Value Analysis template at http://www.ads.ford.com/eva/
MS Project
RMS -- http://www.rms.ford.com
Inputs to Process Outputs Recipients
Originator: One IT PPM Team Page 126 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
229_Classic_SDM_Work_Plan.mpp 221_weekly_status_report_template.doc Control File,
211_change_request_template.doc Earned Value Analysis Template at Program Mgr,
212_risk_management_log.doc http://www.its.ford.com/eva/ BusA,
213_issue_log.doc 211_change_request_template.doc ESpon,
221_weekly_status_report_template.doc 212_risk_management_log.doc Cust
Timesheets http://www.rms.ford.com Issues in 213_issue_log.doc or eTracker at
220_meeting_minutes_template.doc http://www.etracker.ford.com
32_Defect_Log.doc 220_meeting_minutes_template.doc
Originator: One IT PPM Team Page 127 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Diagram The following diagram shows the periodic reviews that must be supported, including Architecture,
PQA and gate reviews at the end of each stage, weekly status reviews (see items highlighted by
red arrows) and various levels of operations reviews that are conducted on a monthly and
quarterly basis.
IT DIRECTOR
Quarterly From IT Director Ops Reviews
To CBG/GEC
Manager
Exec
During
SDM Project
Stage Architecture Project Status Reviews Reviews
Process Reviews
•ARB Health •Project Cost, Benefit, Timing Health
•Occurs for ID & Assess, •PQA Health
•Occurs for all Stages
Analysis, & Design Stages •Occurs for all Stages
•Many Times per Stage
•Once per Stage •Once per Stage
Originator: One IT PPM Team Page 128 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Process Tasks
Tools/Techniques Summary
Methods and Applications/Tool s
Classic_SDM_Process_Guide
Architecture Management Guidebook located at http://www.fsic.ford.com/architecturemanagement/
OneIT Architecture Review Board Workbook located at http://www.fsic.ford.com/architecturemanagement/
Inputs to Process Outputs Recipients
ARB review meeting minutes in ARB review meeting minutes in See SDM Guide
220_meeting_minutes_template.doc 220_meeting_minutes_template.doc
73_ARB_Workbook.xls completed to appropriate Update 73_ARB_Workbook.xls
level in system development lifecycle.
Originator: One IT PPM Team Page 129 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Purpose The deliverables from the Metrics Workshops are valuable tools to help
project managers evaluate project scope, determine resources required,
estimate project effort and duration, prioritize deliverables, and evaluate
productivity. A key output of each session is a function point count for the
project.
Key Instructions for preparing for metrics workshops (Initial, Interim, and Final)
Considerations are provided by the Metrics Specialists. Details on the Metrics workshop
processes are documented in the Solution Delivery Methodology Process
Guide.
Process Tasks
Tools/Techniques Summary
Methods and Applications/Tools
Classic_SDM_Process_Guide
Inputs to Process Outputs Recipients
Metrics meeting minutes in Metrics meeting minutes in See SDM Guide
220_meeting_minutes_template.doc 220_meeting_minutes_template.doc
Originator: One IT PPM Team Page 130 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Purpose Most project types undertaken by IT will involve various technical reviews that
occur across the project life cycle. These include, but are not limited to, the
following:
• Application Control Reviews (ACR) which are required to ensure that
adequate security measures have been designed into an application that is
being developed – see the following link for more information
HTTP://WWW.DEARBORN.FORD.COM/SECURITY/INTERNALCONTROL/552/ACRPROC.HTM
The details of these reviews will be found in the appropriate solution delivery
methodology guide for the project type (e.g., the Classic, Object Oriented, and
Purchased Package methodology guides.)
It is The Project Manager’s job to ensure that these technical reviews occur as
required and that any issues, action items, or decisions that are made as a
result of these reviews are approved, as appropriate, and reflected in project
plans and documentation.
Process Tasks
1 Verify Verify that the appropriate submissions and registrations have been PM
Submissions/ completed.
Registrations
2 Coordinate Coordinate scheduling of review sessions. PM
Scheduling
3 Participate in Make self and team members available for participation in the review SCC,
Originator: One IT PPM Team Page 131 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Tools/Techniques Summary
Methods and Applications/Tools
Classic_SDM_Process_Guide
Inputs to Process Outputs Recipients
Security review meeting minutes in Security review meeting minutes in See SDM Guide
220_meeting_minutes_template.doc 220_meeting_minutes_template.doc
Originator: One IT PPM Team Page 132 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Purpose Process Quality Assurance (PQA) Reviews occur at the end of each stage in the
project. The purpose of the PQA Reviews is to ensure that project processes and
deliverables meet standards and will lead to a successful outcome.
Trigger The trigger for a PQA Review is the completion of work products and processes
for a given stage (e.g., Design, Build, or Implement).
Diagram The following diagram shows the periodic reviews that must be supported,
including PQA and gate reviews at the end of each stage (see items highlighted
by red arrows), weekly status reviews and various levels of operations reviews
that are conducted on a monthly and quarterly basis.
IT DIRECTOR
Quarterly From IT Director Ops Reviews
To CBG/GEC
Manager
Exec
During
SDM Project
Stage Architecture Project Status Reviews Reviews
Process Reviews
•ARB Health •Project Cost, Benefit, Timing Health
•Occurs for ID & Assess, •PQA Health
•Occurs for all Stages
Analysis, & Design Stages •Occurs for all Stages
•Many Times per Stage
•Once per Stage •Once per Stage
Originator: One IT PPM Team Page 133 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Process Tasks
1 Coordinate PQA Ensure that a required PQA Review occurs. Refer to the appropriate PM,
Review SDM Process Guide for details. Team,
PQA
2 Ensure Review Review results and ensure that any action items are reflected in project PM,
Results are plans and completed. Team
Documented
3 Update Project Ensure that review documentation is stored in the project Control File PM
Records as appropriate.
Tools/Techniques Summary
Methods and Applications/Tools
Classic_SDM_Process_Guide
Inputs to Process Outputs Recipients
PQA review meeting minutes 239_PQA_Review_Report.doc See SDM Guide
Originator: One IT PPM Team Page 134 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Purpose Gate reviews are event -driven major milestones during projects that ensure
informed decisions are made about the continued viability of a project and/or its
readiness to proceed to the next stage. Gate Reviews typically occur at the end
of project life cycle stages, before the next major stage is to begin or before a
major commitment is to be made.
Decision makers (principally, the Sponsor or Customer and Business Analyst
and/or IT Management) review the results of actual work effort vs. baseline work
effort and projections of the work effort required to complete the project. They
make an assessment of the overall project health (R/Y/G rating), a Go/No-Go
decision (Is it ready to proceed to the next stage?) and, if necessary, a
recommendation to terminate the project. Project cost, business benefit, timing,
SDM process adherence and architecture compliance are all factors in
determining the overall project health.
At the Gate Reviews, obtain the appropriate signatures on the Gate Review
Checklist forms to ensure accountability of the decisions rendered.
Six Sigma Tollgate Reviews are checkpoints within the Six Sigma DFSS
process that ensure that the project is aligned with business requirements /
customer expectations and that the criteria listed below for this point in the
DFSS lifecycle have been achieved. Verification that Tollgate 0 occurred is
confirmed by the PM process "Confirm Project Readiness to Start". Tollgates 1
and 5 are explicitly called out in the Classic SDM methodology. Tollgates 2, 3
and 4 are embedded within the Gate review.
Trigger The remaining gate reviews are triggered by completion of the work products
and processes for each stage (e.g., Design, Build, or Implement).
Key At this point in the process, there are two key decisions that must be made: 1)
Considerations should the project continue and 2) is it ready to proceed to the next stage.
Originator: One IT PPM Team Page 135 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Diagram The following diagram shows the periodic reviews that must be supported,
including PQA and gate reviews at the end of each stage (see items highlighted
by red arrows), weekly status reviews and various levels of operations reviews
that are conducted on a monthly and quarterly basis.
IT DIRECTOR
Quarterly From IT Director Ops Reviews
To CBG/GEC
Manager
Exec
During
SDM Project
Stage Architecture Project Status Reviews Reviews
Process Reviews
•ARB Health •Project Cost, Benefit, Timing Health
•Occurs for ID & Assess, •PQA Health
•Occurs for all Stages
Analysis, & Design Stages •Occurs for all Stages •Many Times per Stage
•Once per Stage •Once per Stage
Originator: One IT PPM Team Page 136 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Process Tasks
1 Schedule The end date of each stage should be clearly identified in the project plan. PM
Review Before that date, confirm the date that the project will reach the stage gate
and confirm or adjust the scheduled gate review. Notify participants (the
Sponsor, IT Project Owner, Business Analyst, Program Manager, and if
appropriate, the PQA Reviewer, AM Coordinator and Project Managers of
related projects, and other interested parties).
2 Collect Pull together all of the materials that may be required to explain the PM
Backup current state of the project, including the PQA R/Y/G rating, ARB R/Y/G
Materials for rating, the status of issues, risks, and change requests, and recent status
Meeting reports, current metrics, etc., to have ready if needed during gate review
discussions. Ensure that these materials are current and accurate.
Include the signed charter.
Just prior to the meeting collect data on progress against plan and actual
costs from project team members. Complete the weekly status report
form and earned value analysis to determine the project’s current GYR
(Green, Yellow, Red) status, earned value, and Schedule Performance
Index (SPI) and Cost Performance Index (CPI). Identify planned
milestones achieved or missed.
Review the current risk assessment and update as needed to arrive at a
current risk rating score.
3 Complete the Obtain the appropriate Gate Review Checklist and complete the Yes/No PM,
Review checkboxes. Cust
Checklists Note that 6-Sigma Tollgate questions have been included in the Gate
Review Checklist.
4 Assess Review the completed Gate Review checklist, current status, risk rating, PM,
Project change logs, issue log, risk management log, with the Customer and BusA Cust
Viability Business Analyst to jointly arrive at a recommendation as to the viability of Program Mgr
the project prior to the actual gate review. Typically this is performed at a
regular project status meeting.
5 Conduct During the gate review, present and review the completed Gate Review PM,
Review checklist and, if necessary, any backup/supporting materials needed to BusA,
explain the current state of the project. Cust
Review recommendations made by the Project Manager, Business As necessary:
Analyst and Customer on the continued viability of the project. ESpon,
AppOwn,
Make Overall Project R/Y/G Rating, Go/No-Go Decision, and if Program Mgr,
appropriate, a recommendation to terminate the project. These decisions PQA,
may take the following forms: AMCoord,
• Overall R/Y/G rating becomes the lowest of the ARB, PQA and PM for related
Project Status R/Y/G ratings projects,
APM/LOB,
• Continue as planned Practice Mgr,
• Continue in a watch state for a specified short-interval and review the 6-Sigma,
status again at the end of that period Stakeholders,
Vendor/Suppli
• Continue the project under the condition of specified changes in the er
current plan (create Change Requests, as appropriate)
• Terminate the project
Originator: One IT PPM Team Page 137 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
6 Obtain Obtain signatures on the Gate Review Checklist Forms from the PM
Signatures appropriate decision makers including the customer responsible.
Cust
Others, as
necessary
7 Communicate Communicate the overall project R/Y/G rating and the go/no-go decision PM
Decision (and if appropriate, the recommendation to terminate the project) to key
stakeholders, including related projects and support activities per the
project communications plan.
If the project is to be continued, advise those impacted by the decisions
(e.g., ITS, application support groups, etc.) to reaffirm or adjust the
direction of the project's progress and schedule.
8 Update Store minutes and other documentation of the review in the project PM
Project Control File. Update the project record in ITMS, RMS and MRS.
Records
Originator: One IT PPM Team Page 138 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Tools/Techniques Summary
Methods and Applications/Tools
eTracker at http://www.etracker.ford.com/
Earned Value Analysis template at http://www.ads.ford.com/eva/
Microsoft Word and Excel
ITMS – http://www.itms.ford.com/ Refer to the ITMS tutorials on the same web site for instructions in the use of ITMS
Project Record in MRS http://www.ads.ford.com/mrs
MS Project
MRS User and Quick Reference Guides are located at http://www.ads.ford.com/mrs/documentation.htm.
An IT Systems Quick Reference For Project Managers and Application Managers is located at
http://www.itonline.ford.com/sdm/docs/Templates/245_IT_Systems_Quick_Reference_For_Project_Managers_and_Application_Managers.doc
Originator: One IT PPM Team Page 139 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Purpose Operations reviews provide the means to assess programs and projects within the context of an
organization’s entire portfolio of work.
IT DIRECTOR
Quarterly From IT Director Ops Reviews
To CBG/GEC
Manager
Exec
During
SDM Project
Stage Architecture Project Status Reviews Reviews
Process Reviews
•ARB Health •Project Cost, Benefit, Timing Health
•Occurs for ID & Assess, •PQA Health
•Occurs for all Stages
Analysis, & Design Stages •Occurs for all Stages
•Many Times per Stage
•Once per Stage •Once per Stage
Originator: One IT PPM Team Page 140 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Process Tasks
1 Ensure Ensure that project records in ITMS, RMS and MRS are kept current and PM
Project accurately reflect the true status of the project.
Records are
Kept Current
2 Provide Be prepared to provide a current status report if requested. PM,
Current Cust
Status
Report
3 Prepare Ensure that project records (documentation) are ready for review if PM
Backup requested – particularly if the current status of the project is yellow or red.
Material as
Required
Tools/Techniques Summary
Methods and Applications/Tools
Earned Value Analysis template at http://www.ads.ford.com/eva/
Microsoft Word and Excel
MRS User and Quick Reference Guides are located at http://www.ads.ford.com/mrs/documentation.htm.
An IT Systems Quick Reference For Project Managers and Application Managers is located at
http://www.itonline.ford.com/sdm/docs/Templates/245_IT_Systems_Quick_Reference_For_Project_Managers_and_Application_Managers.doc
Inputs to Process Outputs Recipients
221_weekly_status_report_template.doc Project Record in MRS Control File,
Project Control File http://www.ads.ford.com/mrs Sponsor,
Results of Gate Reviews Project Record in RMS http://www.rms.ford.com IT Management,
Results of ARB Reviews Project Record in ITMS http://www.itms.ford.com/ Cust
Results of PQA Reviews
Originator: One IT PPM Team Page 141 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Originator: One IT PPM Team Page 142 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Procurement Initiate
Plan Communication
Plan
Budget Plan Plan
Work Plans
Project Charter
Execute
Work Products
Solution
Delivery Control
Methodology
Close
Inputs to Close Project
Process Contents
Objective Process Steps PM Deliverable
5.1 Finalize 5.1.1 Finalize Implementation Implementation as Planned
Note Delivery
Refer to PM Processes 5.1.2 Finalize Transition Handover to Support
"3.0 Execute Project" 5.2 Conduct Final
and "4.0 Control 5.2.1 Administer Major Release Survey Feedback on Project
Project
Project" for processes Review 5.2.2 Conduct Wrap-up Session Lessons Learned/Metrics
such as "Maintain
Project Records" or 5.2.3 Prepare Closure Report Completion Documents
"Conduct Status
Reviews" for process 5.3 Perform 5.3.1 Release Resources Released Resources
steps that must be Administrative
carried out across all and Financial 5.3.2 Complete Financial Closure Budget/Contract Closure
five PM Processes Closure
(Initiate, Plan, Control, 5.3.3 Close & Archive Records Closed/Archived Records
Execute, Close).
Originator: One IT PPM Team Page 143 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Process Tasks
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word and Excel
ITMS – http://www.itms.ford.com/ Refer to the ITMS tutorials on the same web site for instructions in the use of ITMS
Project Record in MRS http://www.ads.ford.com/mrs
MRS User and Quick Reference Guides are located at http://www.ads.ford.com/mrs/documentation.htm.
An IT Systems Quick Reference For Project Managers and Application Managers is located at
http://www.itonline.ford.com/sdm/docs/Templates/245_IT_Systems_Quick_Reference_For_Project_Managers_and_Application_Managers.doc
Inputs to Process Outputs Recipients
Implementation Plans Project Record in RMS http://www.rms.ford.com Control File,
Project Record in MRS http://www.ads.ford.com/mrs AppSupr
Originator: One IT PPM Team Page 144 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Purpose The purpose of this step is to ensure completion of transition plans made during
the planning stage. This includes execution of handover and follow-up tasks.
Process Tasks
1 Execute Ensure that final transition tasks are executed as planned. If the PM,
Transition project is closing because it has been terminated, finish any Cust,
Plans transition steps that are appropriate. Support Activities
2 Update Update project records to reflect that transition plans have been PM
Project executed as appropriate.
Records
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word
ITMS – http://www.itms.ford.com/ Refer to the ITMS tutorials on the same web site for instructions in the use of ITMS
Project Record in MRS http://www.ads.ford.com/mrs
MRS User and Quick Reference Guides are located at http://www.ads.ford.com/mrs/documentation.htm.
An IT Systems Quick Reference For Project Managers and Application Managers is located at
http://www.itonline.ford.com/sdm/docs/Templates/245_IT_Systems_Quick_Referenc e_For_Project_Managers_and_Application_Managers.doc
Inputs to Process Outputs Recipients
217_transition_support_plan.doc 217_transition_support_plan.doc Control File,
AppSupr
Originator: One IT PPM Team Page 145 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Purpose At the end of the Category 2 and 3 projects, it is important to solicit feedback
from Customers and sponsors on the way that the project has been planned,
managed, and concluded and on final deliverables. The feedback, obtained can
be an important source inspiration for process improvements and professional
growth. It is also an important tool in assessing overall professionalism and
effectiveness of the Ford IT organization.
Trigger Project Manager indicates that a Category 2 or 3 project has completed. MRS
sends the Major Release Survey to listed users 30 days after Project
Implementation.
Key The key considerations in soliciting and obtaining Customer feedback are:
Considerations • Which Customers will be asked to complete a Satisfaction Survey?
• How much time will Customers be given to complete the survey?
• If the project in question a pilot project?
Process Tasks
1 Solicit User Project Manager will add/update user list in MRS with names of PM Cust(s)
Feedback individuals who should receive a support survey from MRS,
being sure to include the Business Analyst, Program Manager,
Customer, and Sponsor.
2 Solicit QC Ask the Quality Control Test Specialist (QCTest) to provide the PM,
Feedback QC final reports for filing in the Project Control File. QCTest
3 Assess Review and summarize completed results. PM
Feedback
Results
4 Share results Share summarized results with participants. Add completed PM,
ESpon(s),
and thank surveys and summary report to Project Control File. Thank
Cust(s),
participants participants.
Team
Originator: One IT PPM Team Page 146 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word / Project Record in MRS http://www.ads.ford.com/mrs
MRS User and Quick Reference Guides are located at http://www.ads.ford.com/mrs/documentation.htm.
An IT Systems Quick Reference For Project Managers and Application Managers is located at
http://www.itonline.ford.com/sdm/docs/Templates/245_IT_Systems_Quick_Reference_For_Project_Managers_and_Application_Managers.doc
Originator: One IT PPM Team Page 147 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Purpose The project wrap-up session provides an opportunity for team members
(including any support resources that have participated on the project as
needed) to review what transpired on the project, and agree on what went well
and what could have been done better. Outputs of the review process will be a
set of lessons learned and recommendations for improvements in project
management processes and the solution delivery methodology.
Process Tasks
1 Schedule and Schedule a wrap-up session with members of the project team. PM,
Hold the Arrange for a facilitator if possible. Ask participants to review Team,
Meeting documents in the Project Control File ahead of time to refresh Metrics
their memory on the status of the meeting at closure, the project
goals and objectives, and outcomes. Provide or direct team
members to the results of team, Customer, and sponsor
feedback.
2 Compare Compare the final project schedule, resource utilization, budget, PM,
Actuals to and deliverables to the original plan: Team,
Project Plans Metrics
• What was really created versus what was planned?
• Did the deliverables comply with the Customers’ and
sponsors’ acceptance criteria?
• Were there deviations from the project plan?
• Why did the deviations occur?
Originator: One IT PPM Team Page 148 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
7 Document & Document all lessons learned and any recommendations made PM,
File Lessons by the group and add to Project Control File. Share lessons Team
Learned learned with local management as required.
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word
Brainstorming
Facilitated Session
Inputs to Process Outputs Recipients
Results of Customer and team satisfaction 211_change_request_log.doc Team,
surveys 212_risk_management_log.doc Metrics
211_change_request_log.doc 213_issue_log.doc
212_risk_management_log.doc 222_lessons_learned.doc
213_issue_log.doc 220_meeting_minutes_template.doc
221_weekly_status_report_template.doc
220_meeting_minutes_template.doc
Originator: One IT PPM Team Page 149 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Purpose The Closure Report performs two functions. First, it summarizes the reason for
the closure (i.e., successful completion of the project or termination), the
deliverables produced, and relevant productivity metrics (e.g., function point
productivity measures on application development projects, the number of
change requests submitted and resolved, the number of defects reported, etc).
It also highlights the lessons learned as agreed in the Team Wrap-up Session.
Process Tasks
Tools/Techniques Summary
Originator: One IT PPM Team Page 150 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Originator: One IT PPM Team Page 151 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Purpose Once the project is closed, resources (personnel, equipment, and facilities)
need to be released for use on other projects. If appropriate, the performance
and contributions of individual team members should be assessed and
documented and feedback given. Note that contractual agreements preclude
providing direct feedback to contract personnel.
• What arrangements, if any, have been made for providing feedback on the
performance/contributions of non-Ford IT team members and personnel
who belong to other IT or Business Activities?
Tools/Techniques Summary
Originator: One IT PPM Team Page 152 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Purpose Financial closure is the process of completing and terminating the financial and
budgetary aspects of the project being performed. Financial closure includes
both (external) contract closure and (internal) account closure.
Diagram The diagram below depicts the high-level process flow for this activity.
Project
Contracts Confirm Project Confirm Contract Yes
Completion Contract Fulfilled?
Budget Plan Date Fulfillment
Project Closure
Report
Resolve No Close Contract
Contract Issues
Process Tasks
1 Confirm the Once a project is closed, there should be no need to apply labor or PM
Closure or resources against the project because it will be delivered or turned
Completion Date over to operations. Any further work done on the product beyond this
Originator: One IT PPM Team Page 153 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
6 Close Contract Produce any written contract closure documentation required by the PM
vendor.
Originator: One IT PPM Team Page 154 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Tools/Techniques Summary
Methods and Applications/Tools
Microsoft Word
ITMS – http://www.itms.ford.com/ Refer to the ITMS tutorials on the same web site for instructions in the use of ITMS
WebTracs
Project Record in MRS http://www.ads.ford.com/mrs
MRS User and Quick Referenc e Guides are located at http://www.ads.ford.com/mrs/documentation.htm.
An IT Systems Quick Reference For Project Managers and Application Managers is located at
http://www.itonline.ford.com/sdm/docs/Templates/245_IT_Systems_Quick_Reference_For_Project_Managers_and_Application_Managers.doc
Inputs to Process Outputs Recipients
229_Classic_SDM_Work_Plan.mpp Charge Code Closure Control File,
223_closure_report_template.doc Closed Contracts Purchasing,
Project Record in RMS http://www.rms.ford.com OGC,
Project Record in MRS http://www.ads.ford.com/mrs Demand Management,
229_Classic_SDM_Work_Plan.mpp MRS Plans Database
Project Record in ITMS http://www.itms.ford.com/
Originator: One IT PPM Team Page 155 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Key The key considerations in closing and archiving project records are
Considerations
• What project deliverables need to be handed over to other project teams,
support activities and end-users?
• What project work products might prove useful on other projects?
• What project work products and records need to be maintained to support
Corporate Records Retention policies?
Process Tasks
1 Handover Project Prepare project deliverables and records for handover. Ensure that PM
Deliverables the correct versions are passed to other teams and that the recipients
know how to access and update them, as appropriate.
2 Close Project in Update the Project State in ITMS so that it shows a status of BusA
ITMS "Complete".
3 Close Project Close records that describe the project. Ensure that the project is PM
Logs and Records accurately reflected in ITMS, RMS, MRS and any local systems used
to track IT projects.
4 Review Work Review work products in the Project Control File to determine if it PM
Retention should be maintained for reuse or legal purposes.
5 Archive Work The first rule of archiving project products is -- if it was important to PM
Product or Discard create, it is probably important to keep. Schedule a CD burn of
archived materials. Up to 2 copies can be requested. Schedule the
burn by submitting a GIRS ticket.
Originator: One IT PPM Team Page 156 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T
One IT Project Management
Process Guide
Tools/Techniques Summary
Methods and Applications/Tools
ITMS – http://www.itms.ford.com/ Refer to the ITMS tutorials on the same web site for instructions in the use of ITMS
Project Record in MRS http://www.ads.ford.com/mrs
GIRS
MRS User and Quick Reference Guides are located at http://www.ads.ford.com/mrs/documentation.htm.
An IT Systems Quick Reference For Project Managers and Application Managers is located at
http://www.itonline.ford.com/sdm/docs/Templates/245_IT_Systems_Quick_Reference_For_Project_Managers_and_Application_Managers.doc
Inputs to Process Outputs Recipients
Records Retention Policies 225_archive_documents_checklist.doc Control File,
Project Deliverables Updated ITMS Record at Metrics
Project Control File http://www.itms.ford.com/
Records Retention Policies Archived Work Products
225_archive_documents_checklist.doc Project Record in RMS http://www.rms.ford.com
Project Record in MRS http://www.ads.ford.com/mrs
Originator: One IT PPM Team Page 157 of 157 Date Issued: 2002-Apr-12
PM_Process_Guide.doc v2.3 Date Revised: 30Apr2004
Ford/Proprietary/Official/02.02 – Ford Internal Use Only Retention Period: C+3,T