Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
-0-
1. Preamble
1.1 The impact of globalization has given rise to the concept of knowledge-
based economies with emphasis on research and development activities
coupled with production. In such economies there is a need for a trained
and educated work force well acquainted with the latest scientific and
technological advances, and capable of making broad-based, logically
analyzed decisions. Technical Universities are needed to produce
workforce, which must be capable of undertaking research, development,
invention and innovation as well as of working in close liaison with the fast-
growing industrial needs of the Nation.
1.3 To bridge the gap and to catch up with the fast development rate in the rest
of the world, the Government of Pakistan has decided to set up new
universities of Engineering, Science and Technology in partnership with
technical universities in Germany, Austria, Italy, and China in the first phase
and with several additional advanced countries in a second phase. The
new universities will follow the teaching standards of partner universities
who will help to establish and manage these new universities, supply
-1-
experienced faculty and award their degrees to the students graduating
from these new universities.
2. Objectives
2.4 Producing a trained and skilled work force having a focus on innovation,
value addition and entrepreneurship, capable of employing knowledge
inputs for the rapid and sustainable technological and industrial
development of Pakistan.
-2-
2.5 The graduates of the UESTP must reach the same standard as graduates
of the international collaborator or partner. Through this equivalence of
standards they will be capable of supplying manpower of the quality needed
by the collaborating country and other foreign companies operating in
Pakistan.
2.6 The University must be linked, formally and informally, with the Technology
Park and Business Incubation Centre which will be established adjacent to
the central teaching and research area (CTRA) of the University.
3. Appointment of Consultants
HEC intends to plan and engineer the construction of the universities through the
appointment of:
The university projects shall be planned, designed and executed in the following
sequential manner.
a) The MAC will be appointed by HEC.
d) The MACs and the IAC will be asked to work together on certain
specified matters, but the IAC must remain independent of the MAC
and must report directly to the client.
-3-
e) The APCs will work under a separate agreement and will be required
to coordinate their work with both the IAC and the MAC. HEC will be
the client.
f) The IAC will prepare all the Conceptual Master Plans and will approve
all the Final Master Plans prepared by the MACs (which will include
inter alia detailed and fully specified building designs). The IAC will
provide periodic top-level supervision on behalf of the client, HEC, on
all UESTP sites.
g) Each of the APCs will prepare the architectural plans, sections and
construction details for their National Signature Building (for instance,
the National Signature Building) at the sites approved by the HEC and
shown in the Final Master Plans and will provide outline specifications
of structure and finishes of this building to the MACs for detailed
designing and construction supervision.
h) The APCs will provide top-level supervision of the NSBs and will
approve the quality of construction on behalf of the client.
i) The MACs will prepare all Final Master Plans and do all detailed
design work of all buildings (HEC may consult IAC to ascertain that
the design work is of appropriate quality).
j) HEC will select building Contractors with the help of the MACs (and of
the IAC if appropriate).
l) The MACs will phase the works as required by HEC according to the
growth of the UESTPs and the Technology Parks, on all sites
m) The IAC and the APCs will inspect the works periodically and will
report to HEC and advise MACs on the quality of work. (Top-level
Supervision)
-4-
n) The IAC and the APCs will do a final inspection at UESTP sites if
requested by HEC.
3.2 The Conceptual Master Plans are required for the complete technical
universities on a number of green field sites along with Integrated
Technology Parks on the principle of identicality elaborated here in
after. The site plans and details of local environmental conditions pertinent
to each site shall be provided by MACs to IAC in the form of topographic
survey plans, GT Sheets from Geological Survey of Pakistan and reports
obtained from the metrological survey of Pakistan showing details of
rainfall, ambient temperatures, and relative humidities etc for the last ten
years or as required by IAC.
3.3 The initial approximate size of student body on each site will on full
development of the university be 5000 Undergraduates & Master’s students
and 500 PhD students. The plans should however provide for a growth of
students by +50%. Other components of academics matters are as follows:-
i. Degree Courses:-
A common 1st year followed by 3 years Bachelor’s Course in each
discipline and subsequent two years Specialized Master’s Course
with most students staying for full six years.
-5-
ii. PhD Course:-
The PhD course will be of 3 years duration.
-6-
c Research facilities designed as open plan laboratories with
flexible internal partitioning arrangements, offices,
workshops etc.
Final details of internal arrangements will be provided by the faculty
members, once they have been appointed.
II. Residential Buildings:
i. Residential accommodation for faculty (240 m2 to 90 m2
depending on their grade).
ii. Residential hostels for students (hostel rooms of about 18m2
covered area with en-suite facilities, occupied either by two
undergraduate or Master’s students or by a single PhD student).
Each hostel will incorporate a dining room (with its own staffed
kitchen) and recreation rooms and prayer room; it is suggested
that on the ground floor of hostels there will be public-access
areas such as shops and cafes.
3.6 Landscaping:
Landscaping of the site with roads, paths, gardens and other features.
-7-
ii. Shell structures of one, two or three floors which may be occupied by
small and medium sized high-technology enterprises (SMEs). The
internal design will be specified by the tenant.
iii. The third section of the Technology Park will consist of landscaped
and serviced plots of land on which large companies will construct
their own premises in due course.
3.8 The Sites: (For details refer to Para 4 and relevant Annexure)
Areas and locations of the sites approved and acquired so far for this
programme are as follows:
-8-
of a well-established modern university in a European country such
as Austria, Germany, France, Italy or Sweden.
b) The Central Teaching and Research Area (CTRA) of the university
must be restricted to pedestrians except for delivery and installation
including O&M of heavy equipment and provision of services.
c) The design of the CTRA must be inward looking into either a central
courtyard or courtyards which should enable students and faculty in
different departments to interact easily for educational matters
pertaining to teaching and research. Access from the outside into
the CTRA must be strictly controlled with just one or two access
points. Access to the individual buildings in the CTRA must also be
restricted for security reasons. Architects familiar with medieval
colleges in Oxford or Cambridge in the UK may find useful analogies
in their design.
d) The student hostels should be in blocks of 200–250 occupants.
e) Men’s and Women’s hostels should be separate but located close to
the main university buildings or CTRA.
f) Faculty housing should be well away from student hostels
g) Security around Faculty housing is important and the area will
require perimeter security and a gated entrance.
h) Cars with drivers will be available from a Car Pool.
i) The Technology Park although separated from the university must
be designed to merge into the university so that personnel may
transfer easily between the two parts.
j) The covered area for SMEs will increase as the demand increases
and provision must be made for this expansion.
k) A short-stay guest house should be included in the Technology
Park for clients paying short visits to companies.
-9-
and to give equal opportunity not only to its several foreign partners
but also to all students irrespective of their choice of institution.
Although the subjects studied by students will vary and the
environment will be different and distinct at the different campuses
each student’s quality of ‘experience’ will be very similar. As an
example of ‘identicality’ in design and construction we consider a
typical house allocated to a full Professor. There may be 50 such
houses on any one campus and they should all be identical to each
other and also identical to full Professors’ houses on all other UESTP
campuses.
There only has to be one conceptual master plan although it will have
to be adjusted to take account of the different shapes and sizes of
the sites. There need only be one set of detailed architectural
drawings and designs of all individual buildings except the NSB. The
- 10 -
concept of a campus university with all facilities on-site and with an
adjoining technology park can be carried forward throughout all the
UESTPs.
(d) Disadvantages
- 11 -
(d) Different colour schemes, facings etc. may be used in different
campuses as long as they do not contradict the ‘identicality’ principle
and do not add significantly to the cost.
3.11 The Conceptual Master Plan and the Main (Local) Architects and
Consultants in Pakistan
The IAC will be required to coordinate with a Pakistani firm of architect &
consultant (MACS). This firm will advise the IAC on local matters and they
will also be required to prepare detailed working drawings for building
designs proposed by the IAC. These drawings will then be transferred to
HEC’s ownership so that they may be used in all of HEC’s planned projects.
The Pakistani firm and other Pakistani firms of architects and consultants
will be charged with the detailed and day-to-day supervision of the
construction work. The IAC will be required to visit Pakistan at periodic
intervals, of say three months, to check and approve the construction work
on behalf of HEC. The IAC may also be asked to give advice to the
Pakistani architects on technical matters relating to services and
environmental conditions in laboratory areas.
- 12 -
The IAC and the Pakistani architects will both be required to assist the HEC
in the appointment of the Construction Company or companies for the
UESTP Programme.
APCs will undertake the detailed architectural design of National Signature
Building as described here after.
4. Availability of Land
The UESTPs are to be constructed on land for which legal rights exist with HEC,
as described hereunder
4.1 Near Lahore (Muridke) (For PGUT & one other University) (≈ 324
hectares).
About 800 hundred acres (324 hectares) of land has been acquired on the
Muridke-Narowal Road, near Lahore. The Site Plan of this land is appended
at Annex-I. It is proposed to build two UESTPs and one joint Technology
Park on this land.
- 13 -
The Provincial Government of Sindh Province and others have made
available approximately 1345 acres of land near Port Qasim on the Karachi-
Hyderabad Highway about 40 kilometers from the Karachi town centre. The
site plan of this land is appended at Annex-III.
5. Requirements of Land
Both MACS and IAC shall ensure that they are able to accommodate all the space
requirements of these Universities and Technology Parks, Incubation Centers etc
in the land made available to them, yet leaving sufficient areas for future
expansion of these universities. As stated in Para 3.3 here in before, both MACS
and IAC in close co-ordination shall decide the zoning of various buildings forming
part these complexes keeping in view the following:
a. Approximately 33% to 50% of the gross area has to be earmarked for
the Technology Parks and Incubation Centers for various types of
entrepreneurs separately described under the caption “Technology
Parks” vide Para 3.7.
b. All the UESTPs are required to be planned on principle of identicality
as repetitive plans, and building designs to enable employment of
minimum inputs both in design and construction for taking advantage
of the economy of scales to maximum.
- 14 -
c. Only one building viz National Signature Building may be designed
depicting the architecture of the collaborating countries viz France,
Germany, China, Korea etc. This shall be done through the
employment of APCs.
d. Where it is fore seen that the available land is less to accommodate
estimated future expansion of the university, the design of various
buildings shall be planned and structured to accommodate further
vertical expansion with minimum disturbance to the users of existence
structures. However in such an event the foundations of the
structures should provide for the ultimate development at this
stage.
5.1 The provisions of § 5(a) – (d) have to be taken into account by the
International Architects and Consultants (IAC) while preparing the
Conceptual Master Plan.
Other issues
(a) The existing services in the area of the UESTP development should
not be disturbed unless there are cogent and unavoidable
requirements for adjusting them. The IAC should, in a preliminary
report, describe such circumstances for consideration by the client
before seeking approval from the client of the Conceptual Master
Plan.
- 15 -
(d) The Pakistani Consultants (MACs) shall, from preliminary
geotechnical surveys/soil investigations etc. determine the most
economical and desirable zoning of proposed buildings and supply
the results with location maps to the IAC.
- 16 -
of reference and performance objectives so as to carry out the
project/projects through to their/their final completion with best professional
inputs.
The Consultants (MACS & IAC) shall include in their financial proposals
separately, the fee adjustments for increase/reduction in the scope of
services resulting from such improvements additions/deletions proposed by
them in the terms of reference and nothing extra shall be paid to them nor
deducted from their adjusted financial proposals, if such proposals of
increase/deletion are accepted by the client except that:
- 17 -
7. Scope of Work
7.1 Programme of Requirements
The land available for the construction of the UESTPs (shown in Annex
IV,V, VI) must be properly and optimally utilized to accommodate the
programme of requirements as well as the future expansion of the UESTPs.
The land utilization must be planned by optimal and economical analysis.
The provision of spaces and adoption of proper zoning plans for the
buildings and recreational spaces forming these UESTP complexes must
be made with care in all details. This work shall be carried out by the IAC,
who is required to submit a preliminary study report to HEC. The IAC will
be able to consult the MACs, the HEC, the experts of the Collaborating
- 18 -
Universities and the Project Directors for the purposes of preparing this
report.
Deliverables
Three hard copies of the study report incorporating the parameters in § 7.3
above together with an electronic copy to HEC.
MACS shall carry out topographic surveys of the site, correctly indicating all
existing salient features. Working out accurate levels for further work is the
sole responsibility of the MACS. The Consultant shall carry out detailed
survey of the site at his cost incorporating all existing utility services passing
from the site for incorporation in the Conceptual Master Plan to be prepared
by IAC.
It must be clearly understood that topographic maps form the basis for
all future work in connection with planning, design, preparation of
construction documents and measurements. The accuracy of this
work cannot be over-emphasized. In case at any later stage it is found
that there are mistakes in the topographic surveys the Consultant
(MACS) shall have to refund not only the payments made to him for all
subsequent works but also pay liquidated damages to HEC for the
delays caused in the work. Survey plan should be sufficiently detailed to
enable preparation of designs of utility services like roads, bridges, storm
drainage, sewerage, water supply, electric, telecommunication services and
the like, within the site. The survey plans should also give the location of all
external utility services passing around the site that do not enter the
site so as to dovetail the internal utilities with such utilities if
possible/required and as authorized by the Project Director/Co-
ordinators. The extra work required in this connection shall be evaluated
and paid for at their quoted rates.
- 19 -
The contours at an interval of 2 ft shall be drawn on the survey plans which
shall be drawn to scales of 1:5000, 1:1000 and 1:500 respectively for
preparation of Conceptual Master Plans and detailed Master Plans
including preparing of working details of services. If required by local
municipal authorities/ Bye laws the survey plans shall also show the khasra
numbers of the acquired land as mutated and handed over to HEC duly
certified by the revenue officials.
Deliverables:
Survey plans containing details as stated above shall be supplied to the
client by the Consultants (MACS) in 03 copies including Compact Disc.
After the completion of survey work, it should be possible to produce
further copies by the Consultants as may be required. All survey data
fed in the computer shall be backed-up on Compact Discs so that the same
could be readily reinstalled in case of any damages caused to the data in
the computer through mistakes or otherwise.
The Consultant (MACS) will be responsible for carrying out in detail Geo-
technical/soil investigations as required for proper planning, designing and
execution of work. The Geo-technical investigations shall be carried out, but not
limited to, as detailed here under:-
- 20 -
of roads and services including preparation of outline specifications
for various buildings and services to be incorporated in the conceptual
master plans.
- 21 -
9. Preparation of Master Plans:
- 22 -
types of equipment loads for which the foundations of buildings etc
are required to be designed must be considered. The specifications
of such equipment etc. will be provided to the Project Directors
working closely with the MAC.
(e) The Conceptual Master Plans shall also include outline descriptions
of all external utilities like water supply, sanitary sewer systems,
storm drainage systems, etc electrification, roads, parking areas,
pedestrian routes gas and telecommunication lines etc. The
Conceptual Master Plan shall also show source development
facilities required for water supply and electricity generation if not
provided through municipal facilities. In addition, it should include
locations of tube wells overhead reservoirs, sanitary engineering
structures like sewerage treatment facilities. Details of requirements
will be developed in consultation with the MAC and the Project
Directors. The provision of parks, running tracks, playing fields and
other green areas separating the campuses from highways etc also
needs to be properly planned . The Conceptual Master Plans shall
also indicate the spaces required for expansion of the UESTP. All
highways, roads, streets and pedestrian paths shall be located and
planned keeping in view sound traffic engineering principles and in
accordance with the guidelines included in § 3 of these ToR.
- 23 -
(f) The Conceptual Master Plans prepared by the IAC with inputs from
MACs and the Project Directors shall be considered jointly by the
HEC, the foreign partners in each UESTP and HEC’s advisers. Any
changes required to be incorporated will be communicated to the IAC
and incorporated in the Conceptual Master Plans when agreed
mutually by all parties.
Deliverables
Three hard copies of the agreed Conceptual Master Plans along with three
hard copies of reports containing outline plans and outline specifications
and design development drawings and data for research laboratories and
workshops etc. Electronic versions of these documents also must be made
available.
While preparing the final master plans, the MACs shall incorporate the
recommendations of a study report prepared by properly qualified
hydrologists indicating the extent to which the university site is susceptible
to flooding and the hydrologist’s proposals for flood mitigation measures to
- 24 -
be adopted including an effective storm drainage system to be adopted on
the site. The Final Master Plans must be discussed with the Project
Directors and reviewed by the IAC before it is submitted to the HEC for
formal approval by the clients.
The Final Master Plans shall also incorporate the present and future land
use analysis. The PMAC shall in his technical report outline in detail the
proposed sequence of evolution of the Final Master Plans from the
approved conceptual Master Plans.
Phase-1 Works:
10.1 The entire work required to be carried out as specified shall be done in two
phases. Phase-I shall include:-
- 25 -
g) Prepare out line specifications for construction of various buildings
and utilities planned in the universities, except National Signature
Building (Action by IAC)
10.3 Deliverables:
The Consultant shall submit to the client:-
- 26 -
a) Topographic Surveys as detailed in 7.4. (3 copies),(Action by
MACs)
b) 3 copies of the Preliminary Geo-technical Soil/Investigation
and Hydrological Reports of the site. ( Para 8.1,8.2 & 8.3),
(Action by MACs)
c) A study report in respect of land requirements ( Para 7.3)
(03 Copies), (Action by IAC)
d) 03 copies of Conceptual Master Plans with compact disks
including line plans, outline specifications and reports etc.
(Para 8.4) (Action by IAC)
e) 03 copies of the final Master Plan with compact discs for
preparing further copies as and when required. (Para 9.2)
(Action by MACs)
f) 03 Copies of Preliminary Architectural Plans and outline
specifications of National Signature Buildingbuilding with
compact disks (Action by APCs)
g) 03 Copies of rough cost estimates of buildings as purposed to
be designed and constructed. (Para 9.2), (Action by IAC &
MACs and APCs)
Phase-2 Works
10.4 The works included in Phase 2 will be taken in hand only as and when and
to the extent authorized by the client (HEC). These include but not limited to
the works included and forming parts of approved mini PC-I for the
respective UESTP’s. The abstracts of civil works approved in the mini PC-Is
are shown at annexure IV, V, VI.
10.5 In addition of above works, the client in consultation with MACs & APCs
may authorize the detailed architectural and engineering designs as well as
other related services like Q.S services, preparation of construction
documents, pretender services and construction supervision etc of all such
works included the programme of requirements for which either the Mega
- 27 -
PC-Is have been approved by the ECNEC or anticipatory approval have
been obtained by it from the ECNEC Secretariat. Delays in authorization
of undertaking full scope of works shall not entitle the IAC, MACs and
APCs to any additional claims but will entitle the consultants to
extension of the time for completion of works. Part 2 works shall be
planned and designed in the following sequences.
- 28 -
d) For structures founded on clay/silty soils or combinations
there off all parameters required for settlement analyses shall
be required to be tested for working of differential settlements
as and where applicable.
g) The Consultant (MACs) shall satisfy itself with the work of sub
soil investigations by providing sufficient qualified &
competent supervision as the investigation work
proceeds. He shall be required to issue instructions regarding
further investigations if so required based on his experience of
the type of strata encountered.
10.7 Deliverables:
At the end of the detailed Geo-technical investigations including laboratory
testing, the Consultant (MACs) will submit three copies of the Geo-technical
Report to the HEC, certifying that he and his Structural Engineer are
fully satisfied with the work done by the Geo-technical Engineering
Contractor and he takes full responsibility for the correctness of the
data and the results derived in the reports.
- 29 -
11. Preparation of Design Development Proposal:
- 30 -
scrutiny fees/other charges payable to the local authority shall be
merged by the Consultants in their design fees. The design
development drawings shall also be submitted to HEC for approval.
c) Design development drawings shall be prepared to a scale of 1:100
and shall include architectural, structural, water supply
sanitary/plumbing, electrical, mechanical, HVAC, lifts where required,
Gas and fire safety proposals. These shall include security systems
as well as crises management system, garbage disposal system
etc.
d) The design development proposals for infrastructural development
works shall be prepared to a scale of 1:1000 and shall include
section/cross section of roads indicating the location of all internal
utility services like street lights, sanitary sewer system, storm drainage
system, sub soil drainage system if and where required, water supply
distribution system, recirculation system for treated affluent for use in
landscaping and horticulture including all works relating to source
development of electric power, water supply and sewerage treatment
etc as well as those relating to landscaping and environmental control
works as foreseen and approved in conceptual drawings/report.
12.1 Based on the approved design development drawings, the Consultant MAC
shall prepare and issue final designs incorporating all pertinent data
required or gathered in the previous stages of development and prepare
construction drawings for the buildings and infrastructural services.
Construction drawings relating to all internal utility services within various
buildings should be prepared separately based on the architectural
construction drawings. These shall include, but not be limited to:
(m) Details of all finishes, doors, windows, floors, roofs, wardrobes etc
should be provided.
- 32 -
(n) Drawings relating to fire safety, fire escapes and crisis management
systems
(q) Any other matters not specifically listed above but necessary for the
project.
They must include all details such as concrete outlines with dimensions and
details of steel reinforcement bars including bar-bending schedules etc.
These drawings should be prepared in sufficient detail to be followed by
Construction Foremen on the site.
i) Instruction to bidders.
ii) General Conditions of Contract.
iii) Conditions of particular Application.
iv) Formats of Agreement, Bid Security, Performance Security,
The tender, detailed Bill of Quantities and the like for review
and approval by the client while approving the final design
proposal.
- 33 -
v) Detailed specifications including copies of applicable
standards mentioned in detailed specifications.
vi) Time required executing the work.
- 34 -
13. Certification/Indemnification:
The Consultant’s (MAC’s) Structural Engineer shall certify that the drawings
prepared by him/vetted by him have been prepared in accordance with the
applicable building codes and incorporate provisions to resist seismicity of
appropriate intensity as specified by the Pakistan Building Code for various cities.
Where the Universities have been located in Zone-3 and Zone-4 from seismic
considerations, the Consultant shall get their structural design reviewed and
rechecked through an independent Structural Engineer to be designated by
the client (at no additional cost to the client). This shall however not apply to
turn key projects, where this work will be carried out by MACs.
The Consultant (MACs) and his Structural Engineer shall indemnify the
client against all risks of damages/claims by third parties in the event of
failure/collapse of structures during their life time, as determined by the
governing laws of Islamic Republic of Pakistan. A similar indemnification
shall also be obtained from the contractors in case of turn key bids.
Similarly in areas of low and moderate seismicity the structures shall also be
designed for all horizontal/vertical loads generated by seismic excitations and the
Consultant shall indemnify the employer as stated above. The need for vetting the
structural designs prepared by MACs through an independent Structural Engineer
may however, be relaxed by the client in its sole discretion.
- 35 -
c) 03 copies of the design calculation relating to structures and other utilities.
d) CD’s of the aforementioned submissions.
Alternatively
Where the contracts are placed on a turnkey basis, the deliverables shall be
similar submissions by the consultants of the Contractor and these must be duly
checked and verified by MACs for turnkey proposals.
a) Availability of sites.
b) Construction drawings, disputes etc.
c) Priority of documents as per clause 5.2 C (Part-1), FIDIC 4.
d) Powers of “The Engineer”, “Employer” and Engineers/Employers
representatives etc.
e) Type of BOQ format to be used etc shall ensure correctness of these
documents and will certify that no “loop holes” are left in these
documents which will enable the Contractor to prefer uncalled for
claims at a later stage.
A similar analysis and certification shall be required form the consultant MACs
in respect of contracts on turn key basis.
- 36 -
c) Where references have been made to standard specifications by
designation such as AASHTO, BSS, ASTM etc or others, a copy of
such standards shall be supplied to the client and the Contractor.
d) The provisions of all documents forming part of the Contract shall be co-
related to exclude any/all ambiguities/discrepancies, in the documents
forming parts of the Contracts.
- 37 -
should be entered in to. Subsequently Contracts, for the construction
of different buildings may be entered in to in the order of the priority
agreed to with the Project Directors. In case of turn key proposals, the
execution of works shall be carried out in the sequence in which
infrastructures and buildings are required to be used. This shall be
provided in the contract documents. The Consultant (MACs) should
supply sufficient tender documents to the client for issue to
prequalified Contractors. The prices of the documents should include
printing charges only and should be decided with the client which on
receipt of the same from the Contractors will be credited to the
accounts of the Consultants.
- 38 -
“Open negotiations are being held to reduce the tender price only.
The Contractors are not allowed to increase their bid price during
the process of negotiations. For those Contractors who do not
intend to reduce their prices, the original tendered cost shall
stand.”
The letter for open negotiations should be sent to all prequalified
Contractors who purchased the tender documents whether or not they
entered into the bid.
- 39 -
b) Where the design for the repetitive buildings / services exists with the
Client (HEC) as a result of work done by another MAC appointed by HEC
and is made available to another appointed MAC, it shall be mandatory for
the this MAC to satisfy himself for the designs already prepared before
adopting the same. HEC will pay the additional fee to the new MAC for
vetting the structural design already prepared at the finally negotiated /
contracted rates for 7.5% of the cost of civil works included in PC-I for the
lead model university. This shall apply to the cost of one building unit of
each type.
As an example if there are 45 buildings in a university and the consultant
has to vet the design of super structure of this university, the cost of civil
works as per approved PC-I is Rs. 2000 per square foot and contracted rate
of the consultant is 2% (assumed) of the cost provided in the PC-I, then for
2 7.5
vetting the design of super structure he will be paid * * 2000
100 100
i.e Rs. 3 x Area of one building.
Similar system will be adopted for other repetitive buildings.
- 40 -
numerations, advance payments, time schedules evaluation criteria for the
award of works etc.
- 41 -
works periodically and convey his findings to MACs and Project
Directors/HEC.
- 42 -
accordance with the computerized programmes of construction works,
approved by the client. The programmes shall be prepared on CPM/PERT
as applicable. Delays if any in the critical activities shall be immediately
brought to the notice of the client. Bi-weekly meeting will be held
between the contractor, the Engineer and the client’s representatives
to expedite the work in accordance with the schedule. The meetings will
high light the drawings required from Clients/ Consultant (MACs) and in
puts by Contractor. Progress report in the forms to be approved by the
Project Director shall be submitted by the Consultants to the Project
Director every month with copies to client and on achieving mile stones as
per computerized programmes.
- 43 -
activities during the process of execution of work so that it should be
possible to trace back the responsibility for the defects appearing in
the construction subsequently from the records of such quality
assurance programme. Similarly the employer’s representatives at
site shall also ensure that the contractor executing the work is
complying with the drawings and specifications.
- 44 -
laboratory results. The Consultants (MACs) acting as “The Engineer” may
suspend the construction for limited periods under relevant contract clause
if the contractor fails to redress the defects pointed out by the Consultants
(MACs) in the quality of materials or method of execution of work, found not
in accordance with the provision of the contract specifications.
The Consultant (MACs) will be responsible for correct authorization of
interim payments including finalization of the account on the
completion of the project and cessation of defect liability period.
- 45 -
The bids provided by consultants in their financial proposal/as negotiated
shall be valid for a period of six months from the date of opening of financial
proposals.
- 46 -
STANDARD FORM OF CONTRACT
FOR
ENGINEERING CONSULTANCY SERVICES
(for Large Projects)
Lump sum Assignments
- 47 -
Where the consultants are authorized to do the works in packages, he shall
provide the performance security for the works authorized by the client/PD’s.
18. Increase in Consultancy Fees for Supervision due to time over runs:
The fees of the Consultants for construction supervision due to time over runs
shall be subject to adjustment as follows:
a) If the time over run for construction supervision is due to the fact that
ii) If the Contractor defaults to execute the work in the required time
and the Consultants (MACs) have taken due care to expedite the
works through issue of notices, the additional fees payable to the
Consultant (MACs) for time over run shall be borne by the
Contractors in addition to liquidated damages payable by
him. A provision to this effect shall be made by the
consultant (MACs) in the Contract documents issued to the
Contractors.
- 48 -
percentage of the value of work done by the Contractors. Only in cases where
client (i) increases the quantum of work after the award of works to the
Contractors; (ii) Fails on the issue of client’s supplied materials or due to
such other action which are beyond the control of the Consultant (MACs)
and the Contractors except for force majeure that increase in consultancy
fee shall be considered based on the actual expenditure incurred by the
Consultants giving effect to changes stated above. No adjustment in fees shall
be made on account of force majeure.
The fees payable to IAC/APCs for top supervision shall be based on per diem
basis per visit charges in addition to business class air travel charges,
boarding and lodging to be provided by the client.
- 49 -
g) Preliminary Architectural designs of buildings and out line specifications
except Library. (IAC)
h) Preliminary Architectural Designs of Library buildings. (APCs)
i) Preparation of hydrological studies (MACs)
- 50 -
j) Pre construction stage: Preparing documents comprising of engineers
cost estimates attending to pre bid meetings, issuance of addendum etc.
(MACs)
k) Evaluation of tenders and recommendations for award of works (MACs)
I/C assistance required during negotiations if required to be carried out.
l) Project Management, detailed construction supervision and quality
control services. (MACs)
m) Periodic/ Top Supervision of works. (IAC/APCs as applicable)
Note:- The services defined in 20(h) above are only payable if specifically stated
in the technical report and fees quantified in the financial reports submitted by the
Consultant. (IAC)
- 51 -
of this contract deliver (if no already delivered) all such documents and software to
the client together with detailed inventories thereof.
For repetitive works/buildings in a university the consultants will repaid fees for the
one unit building type only except as stated and elaborated in Para 15.5 of these
Terms of Reference
- 52 -
buildings separately. A detailed programme on CPM for the completion of
design/supervision services along with man month schedules shall be submitted
institution wise and included in the technical report. The Consultants shall propose
absolute minimum time required, so that the construction work of these institution
is taken in hand expeditiously. The proposed time schedule shall be strictly
followed, while time being deemed to be the essence of the Contract.
(i) Present work load and capacity to fulfil the requirements of this
programme.
(j) Financial Status. (Attached copies of audited balance sheets for last
three years)
(l) Results of any litigation entered into with clients during the last five
years.
The financial proposals of the first three ranking Consultants shall be opened in the
presence of the representatives of the Consultants who may care to attend. The fees
quoted by the Consultants shall be negotiated by the Committee for finalization in
the order of the ranking of the Consultants as per the provisions of PEC rules.
- 54 -
It should be understood that even if the fees quoted by the first or second
ranking Consultants are the lowest, the Committee will have the power to
negotiate the fees in a transparent manner amongst the Consultants to an
acceptable level.
The client reserves the right to increase or decrease the scope of the work, to
award the work to any of the Consultants it chooses, or to divide the work among
several different consultants without assigning any reason. The decision of the
client shall be final and binding and may not be challenged in any Forum or Court
of Law.
- 55 -
Annexure X
Format of Contract
,...
/ •.. -., -~-,~,- '.,.
FORM OF CONTRACT
INotes: J. Use this Form of Contract when the ConsuLtants pe/form Services as
SoLe ConsuLtants.
(hcrcinaftcr called the "Client" which expression shall include the successors. legal
rqJrcscntalives and permitted assigns) and. on the other hand.
(hereinafter called the "Consultants" which expression shall include the successors.
legal rC[ncsclllatives and permitted assigns).
WIIEREAS
(a) the CI ient has requested the Consultants to provide certain consulting
services as defined in the General Conditions of Contract attached to this
Contract (hereinafter caJled the "Services"); and
(11) the Consultants, having represented to the Client that they have the required
professional skills, and personnel and technical resources, have agreed to
provide the Services on the terms and conditions set forth in this Contrnct;
INote: If any of these Appendices are not used, the words "Not Used"
shouLd be inserted beLow/next to the titLe of the Appendix and on the
sheet attached hereto carrying the title of that Appendix. I
(a) the Consultants shall carry out the Services in accordance with tht:
rrovisions of the Contract~ and
(Ii) the Client shall make payments to the Consultants in accordance with
the provisions of the Contract.
IN WITNESS WHEREOF, the Parties hereto have caused this Contract to be signed
in their respective names in two identical counterparts. each of which shatl be
deemed as the original, as of the day and year first above written.
Witness (CLIENT)
Sigl1atures _ Signatures _
Name Name
Title _
Title _
Seal
Name
Name _
Title Title ----------
Seal
Annexure XI
General Conditions of
Contract
,
\ ( - -. -. ,,to- .I'
....\. ,
1. GENERAL PROVISIONS
1.1 Definitions
Unless the context otherwise requires, the following terms whenever used 111
(a) "Applicable Law" means the laws and any other instruments having
the force of law in the Islamic Republic of Pakistan, as those may be
issued and in force from time to time:
(b) "Contract" means the Contract signed by the Parties, to which these
General Conditions of Contract (GC) are attached, together with all
the documents listed in Clause I of such signed Contract:
(c) "Contract Price" means the price to be paid for the performance of
the Services, in accordance wi,th Clause 6;
(c1) "Effective Date" means the date on which this Contract comes Into
force and effect pursuant to Clause 2. I.
(j) "Party" means the Client or the Consultants, as the case may be, and
"Parties" means both of them:
(I) "se" means the Special Conditions of Contract by which the GC are
amended or supplemente?:
(m) "Services" means the work to be performed by the Consultants
pursuant to this Contract, as described in Appendix A;
(0) "Third Party" means any person or entity other than the Client. the
Consultants or a SubconsultanL
This Contract, its meaning and interpretation, alid the relation between the
Parties shall be govenled by the Applicable Law.
1.3 Language
This Contract has been executed in the English language which shall be the
binding and controlling language for all matters relating to the meaning or
interpretation of this Contract. All the reports and communications shall be
in the English language.
1.4 Notices
1.5 Location
In case the Con~ultants consist of a joint venture of more than one entity, the
Consultants shall be jointly and severally bound to the Client for fulfillment
of the terms of the Contract and designate the Member named in the SC to
act as leader of the Joint Venture, for the purpose of receiving instructions
froll) the CI ient.
This Contract shall come into force and effect on the date (the "Effective
Date") of the Client's notice to the Consultants instructing the Consultants to
begin carrying out the Services. This notice shall confirm that the
effectiveness conditions, if any, I istedin the SC have been met.
___~LLthis Contract has not Qecome effective within such time period after the
. date of the Contract signed by the Parties as shall be specified in the Sc.
either Party may, by not less than four (4) weeks' written notice to the other
Party, declare this Contract to be null and void, and in the event of such a
declaration by either Party, neither Party shall have any claim against the
other Party except for the work (if any) already done or costs already
incurred by a Party at the reques~ of the other Party.
The Consultants shall begin carrying out the Services at the end of such time
period after the Effective Date as shall be specified in the SC.
Unless terminated earlier pursuant to Clause 2.9, this Contract shall expire
when, pursuant to the provisions hereof, the Services have been completed
and the payments of remunerations including the direct costs if any, have
heen made. TLe Services shall be completed within a period as is specified
in the SC, or such extended time as may be allowed under Clause 2.6.
I
I
I The term "completion of services" is as specified in the Sc.
2.5 Modification
I'
(a) the Consultants shall inform the Client of the circumstances and
probahle (;;lects;
- (c) the Client shall extend the time for completion of the Services
accordingly.
2.7.1 Definition
(a) For the purposes of this Contract, "Force Majeure" means all event
which is beyond the reasonable control of a Party and which makes a
Party's performance of its obligations under the Contract impossible
or' so impractical as to be considered impossible under the
circumstances, and includes, but is not limited to, war, riots. civil
disorder, earthquake, fire, explosion, storm. tlood or other adverse
weather conditions, strikes, lockouts or other industrial actions
(except where such strikes, lockouts or other industrial actions are
within the power of the Party invoking Force Majeure to prevent).
confiscation or any other action by government agencies.
(b) Force Majeure shall not include (i) any event which is caused by the
negligence or intentional action of a Party or such Party's
Subconsultants or agents or employees, nor (ii) any event which a
diligent Party could reasonably have been expected to both (A) take
into account at the time of the conclusion of this Contract and ([3)
avoid or overcome in the carrying out of its obligations hereunder.
The failure of a Party to fulfill any of its obligations under the Contract shall
not be considered to be a breach of, or default under this Contract in~ofar as
such inability arises from an event of Force Majeure, provided that the Party
affected by such an event; (a) has taken all reasonable precautions. clue care
and reasonable alternative measures in order to carry out the terms and
conditions of this Contract; and (b) has informed the other Party in writing
not later than fifteen (15) days following the occurrence of such an event.
Any period within which a Party shall. pursuant to this Contract, complete
any action or task, shall be extended for a period equal to the time during
which such Party was unable to perform such action. as a result of Force
Majeure.
2.7.4 Payments
The Cl ient may, by written notice of suspension to the Consul tants, suspend
all payments to the Consultants hereunder if the Consultants fail to perform
__~!1)1 <?ftheir obligations uneler this Contract, including the carrying out of the
Services, provided that such notice of suspension (i) shall specify the nature
of the failure, and (ii) shall request the Consultants to remedy such failure
within a period not exceeding thirty (30) days after receipt by the
Consultants of such notice of suspension.
2.9 Termination
The Client may terminate this Contract, by not less than thirty (30) clays
written notice of termination to the Consultants, to be given after the
occurrence of any of the events specified in paragraphs (a) through (e) of
this Clause 2.9.1 and sixty (60) days' ill the case of the event referred to in
(f) :
(h)
if the Consultants become (or, if the Consultants consist of more I,
one entity, if any of their Members becomes) insolvent or hank.lal;
or enter into any agreements with their creditors for relief of debtUPor
take advantage of any law for the benefit of debtors or go into
liquidation or receivership whether compulsory or voluntary:
(e) if the Consultants fail to comply with any final decision reached.
result of arbitration proceedings pursuant'to Clause GC 7 hereof: !as a
(c)
perform
if, as thea result
materialof portion
Force Majeure,
of the Services
the Consultants
for a periodare ofunable
notlless10
than sixty (60) days; or
(f) if Ihe Client, in its sole discretion, decides to terminate this Conliracl.
days written notice to the Client, such notice to be given after the occur ence
The
of any
Consultants
of the events
may specified
terminate inthis
paragraphs
Contract, (a)bythrough
not less(d)than
of thislause
thirt~' (30)
2.9.2:
Consultants
forty-five that such
(45) days payment
after is overdue;
receiving or
writteil notite fron1 I the
or
(d) if the Client fails to comply with any final decision reache~j\ as a
result of arbitration pursuant to Clause GC 7 hereof.
2.9.3 Cessation of Services
3. I General
The Consultants shall perform the Services and carry out their obligations
with all due diligence, efficiency, ane! economy, in accordance with
generally accepted professional techniques and practices, and shall observe
-7:'''''.~":~j:
Tc'!1.
. ,,·1
"IJ
1J
[,
\,
f'
I,
I sound managcmcnt practices, and cmploy appropriate advanced tccI1noll1gy
I
I; and safe methods. The Consultants shall always act, in respect of any mailer
I' relating to this Contract or to the Services, as faithful advisers to the Cli~nl.
and shall at all times support and safeguard the Client's legitimate interests
I;
II in any dealings with Subconsultants or third parties.
Ii
I'
il 3.2 Consultants Not to Benefit from Commissions, Discounts, etc.
Ii
The remuneration of the Consultants pursuant to. Clause 6 shall constitute the
Consultants' sole remuneration in connection with this Contract or the
j
Services, and the Consultants shall not accept for their own benefit any trade
cOlTlmission. discount, or similar payment in connection with activities
pursuant to this Cantract or to the Services or in the discharge of their
obligations under the Cantract, and the Consultants shall use their best
efforts to ensure that the Personnel, any Subconsultants. and agents of either
of them similarly shedl nat receive any such additional remuneration.
his part ar on the part af his employees in so. far as the design af the Prt .icel
is concerned
The to the
Consultants areextent
liableand
for with
the the limitations ofaserrars
cansequence mentianed hereinbel w.
and omlsslon~on
The I iabil ity of the Consultants expires after one (I) year from the stipulhted
date of completion of construction or after three (3) years from the dat~ of
"
li~c,~",- .
"
,
The Consultants shall, at the request of the Client, indemnify the Cliet1l
against any or all risks arising out of the furnishing of pro(essional services
by the Consultants to the Client, not covered by the provisions contained in
the first para above and exceeding the limits set forth in second para above
provided the actual cost of procuring such indemnity as well as costs
exceeding the limits set forth in fourth para above shall be borne by the
Client.
The Consultants (a) shall take out and maintain, and shall cause any
Subconsultants to take out and maintain, at their (or the Subconsultants'. as '
the case may be) own cost but on terms and conditions approved by the
Client, insurance against the risks. and for the coverage, as,are specified in
the SC; and (b) at the Client's request. shall provide evidence to the Client
showing that such insurance has been taken out and maintained and that the
current premiullls have been paid.
The Consultants shall obtain the Client's prior approval in wr1l1l1g hefore
taking any of the following actions:
(b) entering into a subcontract for the performance of any part of the
Services, it being understood (i) that the selection of Subconsultants
and the terms and conditions of the subcontract shall have been
approved in writing by the CI ient prior to the execution of the
subcontract, and (ii) that the Consultants shall remain fully I iable for
the performance of the Services by the Subconsultants and its
Personnel pursuant to this Contract:
The Consultants shall submit to the CI ient the reports and documents
specified in Appendix B in the form, in the numbers, and within the periods
set forth in the said Appendix.
Restrictron(s) about the future use of these documents is specified in the Sc.
; The Consultants (i) shall keep accurate and systematic accounts and
Ii records in respect of the Services hereunder, In accordance with
t:
internationally accepted accounting principles and in sllch form al,1ddetail as
I:
!,
will clearly identify all relevant time charges, and cost, and the basis
I: thereof, and (ii) shall permit the Client or its designated representatives
1,1
I,
periodically, and up to one year from the expiration or termination or this
ii,
Contract, to inspect the same and make copies thereof as well as to have
them audited by auditors appointed by the Client.
4.CONSULTANTS'PERSONNEL
q
!I 4.1 Description of Personnel
[i
II
,I
Ii" The titles, agreed jub descriptions, mlI1lmUm qualifications, and estimated
periods of engagement in the carrying out of the Services of the Consultants 1
"·1
(a) Except as the Client may otherwise agree, no changes shall be made
in the Key Personnel. if, foI' allY reason beyond the rcasonnhle
control or the Consultants, it becomes necessary to replace any or the
t
Key Personnel. the Consultants shall provide as a replacement a
person of equivalent or better qual ificat ions.
(b) If the Client finds that any of the Personnel have: (i) committed
serious misconduct or have been charged with having committed a
criminal action; or (ii) have reasonable cause to be dissatisfied with
the performance of any of the Personnel. then the Consultants shall.
at the Client's written request specifying the grounds therefor.
provide as a replacement·a person with qualifications ane! experience
acceptable to the CI iell!.
(c) Except as the Client may otherwise agree. the Consultants shall: (i)
bear all the additional travel and other costs arising out uf or
. incidental to any removal and/or replacement: and (ii) bear any
additional remuneration. to be paid for any of the Pcrsol)nel provided
fIi· as a replacement to that or the Personnel being replaced.
The Client shall use its best efforts to ensure that the Client shall:
(b) assist to obtain the existing data pertaining or relevant to the carrying
out of the Services, with various Goverl1li1ent and other
organisations. Such items unless paid for by the Consultants without
reimbursement by the Client, shall be returned by the Consultants
upon completion of the Services under this Contact;
\
5. j.2 (:o-ordination
I:
11
The CI ient shall
I:
Ii (a) coordinate and get or expedite any necessary approval and clearances
It relating to the work from any Government or Semi-Government
It Agency, Department or Authority, and other concerned organisation
It
named ill the SC.
(b) coordinate with any other consultants employee! by him.
5.1.3 Approvals
The CI ient warrants that the Consultants sha11 have, free 0 f charge.
unimpeded access to all land of which access is required for the performance
of the Services.
If, after the date of this Contract, there is any change in the Applicable Law
which increases or decreases the cost of the Services rendered by the
Consultants, then the remunerations and direct costs otherwise payable to the
Consultants under this Contract shall be increased or decreased accordingly.
and corresponding adjustment shall be made to the amounts referred to in
Clause 6.2 (a) or (b), as the case may be.
The Client shall make available to the Consultants and the Personne!, for
the purpose of the Services and free of any charge, the services, facilities
and property described in Appendix F at the times and in the manner
specified in said Appendix F, provided that if such services, facilities and
property shall not be made available to the Consultants as and when so
specified, the Parties shall agree on; (i) any time extension that it may be
appropriate to grant to the Consultants for the performance of the Services:
(ii) the manner in which the Consultants shall procure any such services,
facilities and property from other sources; and (iii) the additional
payments, if any, to be made to the Consultants as a result thereof pursuant
to Clause 6 hereinafter.
5.5 Payment
The Consultants I total remuneration shall not exceed the Contract Price and ,
..i
shall be a fixed lump sum including all stan costs; incurred hy Ihe
Consultants in carrying out the Services described in Appendix A. Other
reimbursable direct costs expenditure, if any, arc specified in the fie.
!':xcqH as provided in Clause 5.3, the Contract Price may only hc increased
above the amounts stated in Clause 6.2 if the Parties have agreed to
additional payments in accordance with Clauses 2.5.2.6.5.4 or 6.6.
Payment will be made to the account of the Consultants and according to the
payment schedule stated in the Sc. Payments shall be made after the
conditions listed in the SC for such payments have been met, and the
Consultants have submitted an invoice to the Client specifying the amount
due.
(b) I\nyother amount due to the Consultants shall be paid by the Client
to the Consultants within twenty-eight (28) days after the
Consultants' invoice has been del ivered to the CI ient.
6.5 Delayed Payment.s
If the Client has delayed payments beyond the period stated in paragraph (b)
of Clause 6.4, financing charges shall be paid to the Consultants for each
day of delay at the rate specified in the SC.
If the Cl ient fails to make the payment of any of the Consultants' invoice
(excluding the advance payment), within twenty-eight (28) days after the
expiry of thc time stated in paragraph (b) of Clause 6.4, within which
rayment is to be made, the Consultants may aftcr giving not less than
fourteen (14) days' prior notice to the Client, suspend the Services or reduce
the rate of carrying out the Services, unless and until the Consultants have
received thc paymellt.
Tile Parties shall use their best efforts to settle amicably all disputes arlsln~
uut of or in connection with this Contract or its interpretatioll.
Services under the Contract shall, if reasonably possible. continue cluring the
!,I
arbitration proceedings and no payment clue to or by the Client shall be
i'l
withheld 011 account of such proccedings.
.,
j.
APPENDICES
Annexure XII
An nexu re-XII
No. of Amendments of and supplements to, Clauses in the General Conditions Clause
of Contract.
1.1. Definitions
(a) In sub-clause (I) after the word supplemented add "and in case
of ambiguities or discrepancies, provisions of S.C. shall have priority over
the provisions of G.C."
Advance Income Tax will be deducted at source from the bills on gross amount of
the Consultant bills as per rate fixed by the tax authorities and as amended from
time to time.
The date on which this contract shall come into effect is the date as
mentioned in the letter of award of the work by the Client.
For the purpose of this clause, the time period shall be· 7 days·. The notice
period will be 15 days.
"The· Consultant shall begin carrying out services w.e.f. the date of receipt of
letter of award of this work issued by the Client"
If the scope of services is increased by the Client other than those required or
provided in the TOR, scope of services, or those required to achieve
performance objectives concluded/described' in the contract, the consultant
shall:-
b. Negotiate with the Client the fees and time effects of such increase. The
fees shall be payable on the same parameters on which the
design/supervision is being done.
c. The Client shall extend the time for completion of services accordingly.
2.7 Payment
Any cost incurred by the Consultant during the period of their inability to perform
the services as a result of Force Majeure and in. re-activating the services shall be
deemed to be included in the lump sum prices given by the Consultant and made
part of the Agreement and nothing extra shall be payable for any additional cost
incurred by the Consultant during such period and reactivating the same after
such period of Force Majeure.
In the sixth line of clause 2.8 G.C, word & figure "thirty (30)" shall be substituted
by the word & figure "fifteen (15)".
2.9 Termination - By the Client
I. Replace the word & figure of thirty (30) days and sixty (60) days with
fifteen (15) days and "thirty (30) days" respectively Clause 2.9.1 G.C
II. In the 2nd line of sub clause (c) of 2.9.1 G.C, replace "arbitration
proceedings" with "decision of dispute adjudication Board".
In 2nd line of clause (d) of 2.9.2 G.C replace "arbitration with "decision of
Dispute Adjudication Board".
Delete the last sentence of Clause 2.9.3 G.C starting from "With _ by
clause 3.8 or 3.9" and add 'The Consultant shall within 7 days of such notice
handover to the Client all designs, drawings, record. and material etc.
including that furnished by the :Client or
. purchased' on behalf of the Client and prefer his claim based 'on quantum
merit basis failing which nothing shall be payable to the consultants for the
work claimed to have been performed prior to the cessation of the Services.
Add following to sub-c1ause(b) of 3.6 G.C. "Provided that the particulars of such
Sub-Consultants have been duly provided to the Client along with the technical
proposal".
The Consultant shall also clear with the Client, before making
commitment with Contractors of any action they' proposed to take under
the following:
Issuing variations Orders in respect:
For any new item of the Works not envisaged in the Contract Documents
and which is determined by the' Client to be necessary for the execution
of works, the deliverables shall be agreed to between the parties.
The Consultants shall not use these documents for purposes unrelated to this
Contract without prior written approval of the Client.
Add following to sub-clause (b) of 4.2 G.C "The approval accorded by the Client
shall not relieve the Consultants of their responsibilities under applicable laws".
5.1.1 Assistance
a. The Client shall make available on demand within one week from
commencement date. The documents relating to the project and available
with the Client.
5.1.2. Coordination
"'Provided that the delays' resulting from such coordination" shall not entitle the
Consultants to additional claim on any account.
5.1.3. Approvals
Fill in the blank space in first line of 5.1.3 G.C with "two" and add "'provided the
documents are complete and correct and such approvals shall not relieve the
consultants from any of his responsibilities under contract".
Add to the clause 5.2 G.C "provided that such access may be provided in parts
and in the event of any resistance by the occupants of land or for any other
reason, the issue shall be treated as Force Majeure under clause 2.7"
Add to 5.3 G.C "provided that no such adjustment in cost shall be made if the
consultancy period specified in the Contract does not. exceed one year or due to
any adjustment of cost of POL electric tariffs and transport tariffs within one year.
The contract price is as specified in the TOR and quoted by the consultant, break
up of this price is as follows:
a. In sub-clause 6.6 (b) G.C, the portion after the words & figure
"clause 2.6" shall be substituted by the words "as provided
therein".
"Any dispute between the parties as to matters arising pursuant to this contract
which cannot be settled amicably within (30) days after receipt by on party of the
other party's request for such amicable settlement shall be referred to dispute
adjudication board stated below. However the Consultants shall continue to
proceed with the services with all due diligence.
7.3 Dispute Adjudication Board
Appendix A
.il
'I
_''';'1'
Appendix B
Reporting Requirements
Pursuant to Clause GC-3. 7, the Consultants shall I ist format, frequency, and contents
of reports; persons to receive them; dates of submission and the number of copies of
each submittal; etc. If no reports are to be submitted, state here "Not applicable".
Appendix C
List here the elements of cost used to arrive at the breakdown of the Contract Price
foreign currency portion:
3.
Total, remuneration and reimbursable direct costs expenditure (I + 2)
Note:
'fliis appelldLr HiiL! exclusively be llsed for dl'ferlllil/il/g U'IIII/I/eralioli .for Addiliollo
,)'ervice,\' ill occordol/ce wilh CLause GC 6.6.
Appendix E
I ,ist her<.:the elements of cost used to arrive at the breakdown of the Contract Price-
local currency ponion:
(i) rentals;
(ii) furnishing and equipment:
(iii) operation and maintenance of office. office equipmenl and
furniture, office supplies.
(e) Transport including rUlinillg and 11l:1inlellalllT. and other assllciilll'd l'(lSls:
INote:
The Client shall make available the following Services and racilities:
The CI icnt shall make available to the Consultants and the Personnel, 1m
purposes of the Services and free of any charge, the services, facilities
[lillperl:y, at the times and in the manner specified hereunder:
(a)
(b)
(c) Rent will be charged by Ihc Clicnl only I'm the fcllllily s1
accommodation provided to the Personnel, ill the ('Iient's colonies
the following rates:
2. Lodge Accommodation
..
I
;;
I: " I f requested by the Consultants, the CI ient shall provide lodge accol1lll1odati
i'
II
Hi if available, to all Personnel of the Consultants when on visit to various part:
j!
)1 ~I the Project area or any other station where such facilities or the 10
Ji
l' accommodation of the Client exists (and provided that the Personnel of
H
ji' Consultants visit that place in connection with the Project) under the same te'
II,
Ii.
I'I and conditions as the Client's still'!" is cntitled.
1:
11
Ii
d
;1
n