DATA

Name of Work: DRILLING AND GROUTING FOR THE FOUNDATION


TREATMENT ON U/S SIDE OF K.R. DAM FROM T.B.L. AT 6.00Mts., INTERVALS
FOR PRIMARY AND SECONDARY HOLES BETWEEN KM.0.560 TO KM.8.000.

SL QTY., DESCRIPTION OF ITEM RATE PER AMOUNT


NO
1. 1Rmt. Drilling in consolidated earth by manual
augur or mechanical augur 100 mm dia
from +89.000 level to Ground Level
including driving the casing pipe of
Suitable dia for protecting the whole from
collapsing and removing the same
including wear and tear charges for
inserting and cost and conveyance of pipe
and couplings and labour charges complete
900/- Per 900.00
etc.,
RMT.
( As per quotations)

2. 1Rmt. Drilling of holes of 75 mm dia (NX BIT) 1220.77 1 Rmt 1220.77


in all types of rocks with diamond drilling / Rmt
including hire charges of machinery etc Or say
complete to a depth including plain 1221/ Rmt
washing the hole with water.
Drilling of hole 75mm dia.
2

3. 1 Rmt Conducting permeability tests in rock


drilling portion in stages in descending
order only at 2 mt zone for the top 10mts
and the balance depth with 3 mts zone
including cost and conveyance of all
materials and labor charges..etc.,
Hire charges of grout pump for 2001-02 198.12 0.167 33.09
hr rmt
Labor charges (As per Sanctioned
.
Est.No.100/03-04)
352.00 0.028 9.86
Pump operator 1 no 206.00
day/rmt
Man Mazdoor 1 no 146.00
352.00
Cost of packers and GI pipes L.S. 50.00

220 lt Water required for 1Rmt is 220lts 0.04091 9.65


102.6
or 103/Rmt.

Grouting with cement slurry of specified


4. 1 MT
consistency with required pressure
including call grouting with 5% of value of
cement of 600 micron sieved sand with
required pressure whenever required as
cost and conveyance of all materials and
labor charges.
Hire charges of grout pump rate as per
198.12 0.235 46.56
item. hr 1 bag
Cost of pneumatic hose pipe 100mt. Rate
45000 0.235 13.22
as per sanctioned estimate (61/02-03)
800 hr 1 bag
3

Cost of packer sleaved 10.00 0.235 2.35


1 hr 1 bag
Water consumption per bag = 550lt
0.04385 1 lt 24.12
Labor charges
Fitter 1 no X 206 = 206.00
MM 1 no X 146 = 140.00
0.028
352.00
day/ bag 1 bag 9.85

222.20 1bag 222.20


Cost of cement
318.30
Cost per 1MT 318.30 X 20 bags
= 6366
6366/MT.

5. 1.00 Back filling the drilled holes with cement


Cum mortor 1:2 mix including cost and
conveyance of all material and labour
charges etc., complete
1.00 Sand 570.10 1 cum 570.10
m3

720 Cement 4444.00 MT 3199.68


Kgs
1 Cum. Mixing Charges (5300.185-B P.No.26 of 45.00 1Cum 45.00
SSR) 3814.78
or 3815.00

7. Ech Manufacturing and supplying of country


wood core boxes of size 1.80m X 0.45M
X0.10m with inside partition arrangement
as specified by the dept including cost and
conveyance of all materials and labor 1500 1No.
1500.00
charges and painting etc complete
As per quotation

Asst Exe. Engineer, Deputy Exe Engineer, Executive Engineer,


SSLC&SB Sub Divn.II, SSLC&SB Sub Divn.II SSLC&SB Divn.No.2,
K.R.Dam. K.R.Dam. Nellore.
4

(Old)…. DATA

Name of Work: DRILLING AND GROUTING FOR THE FOUNDATION


TREATMENT ON U/S SIDE OF K.R. DAM FROM T.B.L. AT 6.00Mts., INTERVALS
FOR PRIMARY AND SECONDARY HOLES BETWEEN KM.0.560 TO KM.8.000.

SL QTY., DESCRIPTION OF ITEM RATE PER AMOUNT


NO
1. 1Rmt. Drilling in consolidated earth by manual
augur or mechanical augur 100 mm dia
from +89.000 level to Ground Level
including driving the casing pipe of
Suitable dia for protecting the whole from
collapsing and removing the same
including wear and tear charges for
inserting and cost and conveyance of pipe
and couplings and labour charges complete
900/- Per
etc.,
RMT. 900.00
( As per quotations)

3. 1 RMT Drilling of holes of 75 mm dia (NX BIT)


in all types of rocks with diamond drilling
including hire charges of machinery etc
complete to a depth including plain
washing the hole with water.
Drilling of hole of 75mm dia. 1202.35 1 RMT 1202.35

Or say 1202/Rmt.
5

4. 1 Rmt Conducting permeability tests in rock


drilling portion in stages in descending
order only at 2 mt zone for the top 10mts
and the balance depth with 3 mts zone
including cost and conveyance of all
materials and labor charges..etc.,
Hire charges of grout pump for 2001-02
Labor charges (As per Sanctioned
198.12 0.167
Est.No.100/03-04) hr rmt 33.09
310.00 0.028
Pump operator 1 no 180.00
day/rmt 8.68
Man Mazdoor 1 no 130.00
310.00
Cost of packers and GI pipes L.S. 50.00
0.04374 9.62
Water required for 1Rmt is 220lts
220 lt 101.39
or 101/Rmt.

Grouting with cement slurry of specified


5. 1 MT
consistency with required pressure
including call grouting with 5% of value of
cement of 600 micron sieved sand with
required pressure whenever required as
cost and conveyance of all materials and
labor charges.
Hire charges of grout pump rate as per
198.12 0.235 46.56
item. hr 1 bag
Cost of pneumatic hose pipe 100mt. Rate
45000 0.235 13.22
as per sanctioned estimate (61/02-03)
800 hr 1 bag

Cost of packer sleaved 10.00 0.235 2.35


1 hr 1 bag
Water consumption per bag = 550lt
0.04374 1 lt 24.06
Labor charges
Fitter 1 no X 180 = 180.00
MM 1 no X 130 = 130.00
310.00
0.028 1 bag 8.68
day/ bag
Cost of cement
550 lt 221.19 1bag 221.19
Cost per 1MT 316.06 X 20 bags 316.06
= 6321.20 6321/MT.
or say 6321/-
6

6. 1.00 Back filling the drilled holes with cement


Cum mortor 1:2 mix including cost and
conveyance of all material and labour
charges etc., complete
1.00 Sand 427.60 1 cum 427.60
m3

720 Cement 4423.80 MT 3185.14


Kgs
1 Cum. Mixing Charges (5300.185-B P.No.16 of 39.50 1Cum 39.60
SSR) 3652.34
or 3652.00

7. Ech Manufacturing and supplying of country


wood core boxes of size 1.80m X 0.45M
X0.10m with inside partition arrangement
as specified by the dept including cost and
conveyance of all materials and labor 1500 1No.
1500.00
charges and painting etc complete
As per quotation

Asst Exe. Engineer, Deputy Exe Engineer, Executive Engineer,


SSLC&SB Sub Divn.II, SSLC&SB Sub Divn.II SSLC&SB Divn.No.2,
K.R.Dam. K.R.Dam. Nellore.
7

DATA

Name of Work: DRILLING AND GROUTING FOR THE FOUNDATION


TREATMENT ON U/S SIDE OF K.R. DAM FROM T.B.L. AT 6.00Mts., INTERVALS
FOR PRIMARY AND SECONDARY HOLES BETWEEN KM.0.560 TO KM.8.000.

SL QTY., DESCRIPTION OF ITEM RATE PER AMOUNT


NO
1. 1Rmt. Drilling in consolidated earth by manual
augur or mechanical augur 100 mm dia
from +89.000 level to Ground Level
including driving the casing pipe of
Suitable dia for protecting the whole from
collapsing and removing the same
including wear and tear charges for
inserting and cost and conveyance of pipe
and couplings and labour charges complete
900/- Per
etc.,
RMT. 900.00
( As per quotations)

2. 1Rmt. Drilling of holes of 75 mm dia (NX BIT)


in all types of rocks with diamond drilling
including redrilling of grouted zone 1203.03 1 Rmt 1203.03
including the hire charges of machinery etc
complete to a depth where the permeability
value is below 5 lugeons continuously to a
depth of 6 mts ( ie,. 2 zones) including
plain washing the hole with water.
Add for re-drilling charges =900/2= 450.00 1 Rmt 450.00

1653.03
or 1653.00/
Rmt

3. 1 RMT Drilling of holes of 75 mm dia (NX BIT)


in all types of rocks with diamond drilling
including hire charges of machinery etc
complete to a depth including plain
washing the hole with water.
Drilling of hole of 75mm dia. 1203.03 1 RMT 1203.03

Or say 1203/Rmt.
8

4. 1 Rmt Conducting permeability tests in rock


drilling portion in stages in descending
order only at 2 mt zone for the top 10mts
and the balance depth with 3 mts zone
including cost and conveyance of all
materials and labor charges..etc.,
Hire charges of grout pump for 2001-02
Labor charges (As per Sanctioned
198.12 0.167
Est.No.100/03-04) hr rmt 33.09
310.00 0.028
Pump operator 1 no 180.00
day/rmt 8.68
Man Mazdoor 1 no 130.00
310.00
Cost of packers and GI pipes L.S. 50.00
0.04486 9.87
Water required for 1Rmt is 220lts
220 lt 101.64
or 102/Rmt.

Grouting with cement slurry of specified


5. 1 MT
consistency with required pressure
including call grouting with 5% of value of
cement of 600 micron sieved sand with
required pressure whenever required as
cost and conveyance of all materials and
labor charges.
Hire charges of grout pump rate as per
198.12 0.235 46.56
item. hr 1 bag
Cost of pneumatic hose pipe 100mt. Rate
45000 0.235 13.22
as per sanctioned estimate (61/02-03)
800 hr 1 bag

Cost of packer sleaved 10.00 0.235 2.35


1 hr 1 bag
Water consumption per bag = 550lt
0.04486 1 lt 24.51
Labor charges
Fitter 1 no X 180 = 180.00
MM 1 no X 130 = 130.00
310.00
0.028 1 bag 8.68
day/ bag
Cost of cement
550 lt 215.00 1bag 215.00
Cost per 1MT 310.32 X 20 bags 310.32
= 6206.40 6206/MT.
or say 6206/-
9

6. 1.00 Back filling the drilled holes with cement


Cum mortor 1:2 mix including cost and
conveyance of all material and labour
charges etc., complete
1.00 Sand 427.60 1 cum 427.60
m3

720 Cement 4300.00 MT 3096.00


Kgs
1 Cum. Mixing Charges (5300.185-B P.No.16 of 39.50 1Cum 39.60
SSR) 3563.10
or 3563.00

7. Ech Manufacturing and supplying of country


wood core boxes of size 1.80m X 0.45M
X0.10m with inside partition arrangement
as specified by the dept including cost and
conveyance of all materials and labor 1500 1No.
1500.00
charges and painting etc complete
As per quotation

Asst Exe. Engineer, Deputy Exe Engineer, Executive Engineer,


SSLC&SB Sub Divn.II, SSLC&SB Sub Divn.II SSLC&SB Divn.No.2,
K.R.Dam. K.R.Dam. Nellore.