Detailed estimate
Name of work : IMPROVEMENTS TO WORK SHOP SHED AND
MECHANICAL SUB-DIVISION OFFICE SHED TO ESTABLISH
OF 21ST CENTURY GURUKULAM INSTITUTE IN TGP CAMP
COLONY AT K.R. DAM.
Sl. Measurements
Description of Items Nos Contents
No. L B D
1. Brick masonry in CM 1:5 using
country bricks including cost and
conveyance of all materials and
labour charges for.
Closing of Ventilators on top of shed 2x15 0.90 0.60 0.34 6.61
Closing of windows in side hall 2x3 0.90 0.23 1.20 1.49
For cross walls 1x2 9.15 0.23 3.00 6.31
For small shed 1x1 25.00 0.23 3.00 17.25
For closing of window in hall 2x4 0.90 0.23 1.20 1.99
For closing of doors in out side 1x4 0.90 0.23 2.00 1.66
35.31
or say
36 Cum
2. Plastering the exposed faces of
brick masonry in CM 1:4,12mm
thick including cost and conveyance
of all materials and labour charges
etc., complete for finished item of
work.
For ventilators on top of shed 1x2x1 0.90 0.60 -- 10.80
0
For closing of windows 2x3x2 0.90 1.20 -- 12.96
For cross walls 2x2 9.15 -- 3.00 109.80
For small shed 1x1 25.00 -- 3.00 75.00
For windows 2x2x4 0.90 -- 1.20 10.28
For doors 2x4 0.90 -- 2.00 14.40
239.24
or say
240.00
2
Sl. Measurements
Description of Items Nos Contents
No. L B D
1. Brick masonry in CM 1:5 using
country bricks including cost and
conveyance of all materials and
labour charges for.
Sqm
12.00
Nos
Sl. Measurements
Description of Items Nos Contents
No. L B D
1. Brick masonry in CM 1:5 using
country bricks including cost and
conveyance of all materials and
labour charges for.
24.00
Nos
513 sft
47.67
or say
48.00
sqm
Sl. Measurements
Description of Items Nos Contents
No. L B D
1. Brick masonry in CM 1:5 using
country bricks including cost and
conveyance of all materials and
labour charges for.
.. gravel room 1x2x2 9.00 545 + 0.00 98.10
2
For north and south side wall 2x2 9.00 4.57 164.52
Deductions
1856.81
or say
1860
Sqm.
As a part of development activity far rural areas, Andhra Pradesh Government have
decided to establish in Institute in Kandaleru Project area. In this connection S.V. university
Vice Chancellor, Chairman for Higher Edcuation Department, District Collector and
superintending Engineer, SSLC& SB Circle, Nellore along with Member of Legislative
Assembly of Rapur inspected the dam site on 08.02.2007 in the first instance. Subsequently
a tem of members from higher Education Department of Andhra Pradesh visited dam site
along with Hon’ble Minister for information Public relation and Tourism on 26.05.2007. they
have decided to make use of the existing buildings in K.R. Dam. As a part, workshop shed
proposed as class rooms and Mechanical Sub- Division office as Mess, after getting
necessary renovation work done, accommodation for 100 Nos. of students and 12 Nos. of
staff in the Quarters of T.G.P. Camp colony at K.R. Dam.
In this regard a meeting was conducted in Hon’ble Minister’s presence with Zilla
Parishad Chariman, Nellore, Nellore District Collector, 21 st Century Gurukulam Co-ordinators
and Executive Engineer, SSLC & SB Divison No.2, Nellore.
In above meeting it is decided to provide funds for class room shed Mess shed
renovation work from Collector’s fund. Road, Gate, Fencing work from Z.P. funds and repairs
to Quarters from T.G.P. funds.
In this contest, the fact is that the construction of quarters, store shed, Mechanical
workshop sheds etc., were constructed during the year 1985. the formation of Kandaleru
2
earth dam bund was completed during the year 1997. the work shop yard and store yard
area and sheds were utilized by the then Mechanical staff. After 1997 there is no
maintenance activity in workshop as well as store yards. Major Part of Machinery kept idle
were sold-out conducting auction. At present only Major party is left out.
1. Brick Masonry in CM 1:5 using country bricks including cost and conveyance of all
materials and labour charges.
2. Plastering the exposed faces of brick masonry in CM 1:4,12mm thick including cost
and conveyance of all materials and labour charges etc., complete for finished item
of work
3. Supplying and fixing of door of size 3’-6”x 6’-6” made up of country wood frame
(vepa) and plywood door with decolam on both faces including frame with necessary
accessories like hinges, aldrops, tower both, doors stoppers, hydraulic wood classes
etc., complete.
4 Supplying and fixing of door of size 3’-6”x 6’-6” with country wood frame (vepa)
and Shutter, including fixing of all necessary accessories like hinges, aldrops,
tower both, doors stoppers, etc., complete including cost and conveyance of all
materials and labour charges etc complete.
5 Supplying and fixing of windows of size 3’x4” with country wood frame Take wood
and Shutters with glazed including fixing of all accessories like hinges, tower bolts,
friction stay Hings, etc., complete.
6 Painting of doors and windows with best enamel paint in two coats over the finished
coat of wood primary coat including cost and conveyance of all materials and labour
charges etc complete.
7 White washing one coat with best shell lime of approved quality including cost and
conveyance of all materials, bushes, Ganjee power (or) Gum, watering the wall
before whole washing etc complete as directed by department.
8 Dismantling of brick masonry ever necessary for opening of windows and doors and convey
the debris to out side the work shop yard with a average lead of 1 KM including cost of
conveyance and labour charges etc complete
Rates:
Rates are calculated as per current SSR for the year 2007-08and local market rates.
2
Programme of work:
The work is to be taken up during 9/07 and will be completed in Septembert 2007, by
approving nomination by District Collector.
Funds:
ABSTRACT ESTIMATE
Name of work : IMPROVEMENTS TO WORK SHOP SHED AND
MECHANICAL SUB-DIVISION OFFICE SHED TO ESTABLISH
OF 21ST CENTURY GURUKULAM INSTITUTE IN TGP CAMP
COLONY AT K.R. DAM.
Sl.
Qty Description of Items Rate Per Amount
No.
Sl.
Qty Description of Items Rate Per Amount
No.
7. 1880 White washing one coat with best 5.20 1 Sqm 9776
Sqm shell lime of approved quality
including cost and conveyance of all
materials, bushes, Ganjee power (or)
Gum, watering the wall before whole
washing etc complete as directed by
department.
244873
TOTAL: 2,54,800
DETAILED ESTIMATE
Name of work : IMPROVEMENTS TO WORK SHOP SHED AND
MECHANICAL SUB-DIVISION OFFICE SHED TO ESTABLISH
OF 21ST CENTURY GURUKULAM INSTITUTE IN TGP CAMP
COLONY AT K.R. DAM.
Sl. Measurements
Description of Items Nos Contents
No. L B D
1. Brick masonry in CM 1:5 using
country bricks including cost and
conveyance of all materials and
labour charges for.
Closing of Ventilators on top of shed 2x15 0.90 0.60 0.34 6.61
Closing of windows in side hall 2x3 0.90 0.23 1.20 1.49
For cross walls of small sheds 1x2 9.15 0.23 3.00 6.31
For small shed 1x1 25.00 0.23 3.00 17.25
For closing of window in hall 2x4 0.90 0.23 1.20 1.99
For closing of doors in out side 1x4 0.90 0.23 2.00 1.66
35.31
or say
36 Cum
2. Plastering the exposed faces of
brick masonry in CM 1:4,12mm
thick including cost and conveyance
of all materials and labour charges
etc., complete for finished item of
work.
For ventilators on top of shed 1x2x1 0.90 0.60 -- 10.80
0
For closing of windows 2x3x2 0.90 1.20 -- 12.96
For cross walls 2x2 9.15 -- 3.00 109.80
For small shed 1x1 25.00 -- 3.00 75.00
For windows 2x2x4 0.90 -- 1.20 10.28
For doors 2x4 0.90 -- 2.00 14.40
239.24
or say
240.00
Sqm
2
Sl. Measurements
Description of Items Nos Contents
No. L B D
1. Brick masonry in CM 1:5 using
country bricks including cost and
conveyance of all materials and
labour charges for.
12.00
Nos
Sl. Measurements
Description of Items Nos Contents
No. L B D
1. Brick masonry in CM 1:5 using
country bricks including cost and
conveyance of all materials and
labour charges for.
24.00
Nos
513 sft
47.67
or say
48.00
sqm
Sl. Measurements
Description of Items Nos Contents
No. L B D
1. Brick masonry in CM 1:5 using
country bricks including cost and
conveyance of all materials and
labour charges for.
For north and south side wall 2x2 9.00 4.57 164.52
Deductions
1856.81
or say
1860
Sqm.
LEAD STATEMENT
Name of work: IMPROVEMENTS TO WORKSHOP SHED AND MECHANICAL SUB DIVISION OFFICE SHED TO
ESTABLISH 21ST CENTURY GURUKULAM INSTITUTE IN T.G.P. CAMP COLONY AT K.R.DAM.
Sl. Description of Source of Unit Lead Initial Conveyance Deduct Add Add Total net Remarks
No. item material cost charges stacking seigniorage blasing rate
CT MR Total charges charges charges