Sei sulla pagina 1di 2

Constructing Durable Masonry

SCOPE
CONCRETE

data
This data sheet sets out practices to be followed when
IMPORTANT constructing masonry to ensure the durability of the
SAFETY INFORMATION resulting wall. For guidance on checking the plans and
When handling and using specification to see that all required information is
cement or fresh concrete, avoid
included and that appropriate materials have been STORAGE OF MATERIALS ON SITE
skin contact. Wear suitable
protective clothing.
specified see Concrete Data ‘Durable Masonry Generally, materials should be ordered and supplied
Specification Checklist’. so they are incorporated into the structure as soon as
possible after delivery. Long storage periods should be
INTRODUCTION
avoided. Materials should be stored on site so as to
Although the process of ensuring prevent deterioration or contamination. Particular
masonry elements are durable and don’t requirements for some materials include:
suffer deterioration during their life
Cement and Lime Store in bags off the ground in a
begins at the design and specification
dry environment, eg waterproof shed. Minimise air
Cement stages, it is the construction phase that is
circulation around bags. Keep different Types of
and Concrete crucial to achieving the objective. This
cement, eg Type GP (General purpose portland) and
Association of data sheet outlines the steps that should be followed
Type GB (General purpose blended) in separate
Australia during construction to produce durable masonry.
stacks so they are not used interchangeably. Use on a
The Association is a non-profit ORDERING MATERIALS ‘first-in/first-out’ basis.
organisation sponsored by the
Orders for materials should comply with the Masonry units Masonry units should be stored on
cement industry in Australia to
provide information on the many requirements as set out in the plans and specification. pallets in the wrapping as delivered from the
uses of cement and concrete. When placing orders, ensure that the supplier attaches manufacturer. When the units are taken from the pallet
This Guide is distributed by the
any required test certificates and documentation to they should be stacked off the ground on a clean, firm
Association for that purpose.
confirm that the specified material has been supplied. surface.
Since the information provided
is intended for general Reinforcement Reinforcement should be stored off the
guidance only and in no way
ground and supported at sufficient points along its
replaces the services of
professional consultants on
length to avoid bending or distorting the bars. It should
particular projects, no legal be protected from contamination by oil, paint or other
liability can be accepted by coatings that can reduce the bond.
the Association for its use.

JULY 1999 B2

Page 1 of 2
CONCRETE

data MIXING MORTAR


■ Batch by volume Ingredients should be measured
accurately by volume. Volume batching does not
LAYING UNITS
Units must be laid in the specified bonding pattern
with the appropriate bedding. Solid and cored units
mean by ‘shovelful’ as a shovelful of cement and a are laid on full bedding and hollow units on face-shell
shovelful of sand (usually damp) are not equal in bedding. Vertical joints in fully-bedded masonry should
volume. be completely filled with mortar. Check the specification
■ Use only specified materials Don’t add ‘fire clay’ or for face-shell bedded masonry.
‘brickies loam’ to the mix. These reduce the bond of Mortar joints should be tooled to give a dense,
the mortar. water-shedding surface. Joints should not be raked in
■ Do not use additives to replace lime Lime makes other than mild environments. Note that AS 3700 lists a
the mortar creamier and easier to use, improves number of restrictions when raking joints, for example
bond and minimises cracking. stipulating that joints in hollow-unit, ungrouted masonry
must not be raked.
■ Beware of overdosing with admixtures Chemical
admixtures have their place but must be used with WALL TIES AND OTHER COMPONENTS
care. It is not true in this case that more is better.
Wall ties and other components should be incorporated
Overdosing will lead to a dramatic loss of bond and
into the construction as specified and, if appropriate, in
resulting poor performance of the masonry.
accordance with the manufacturer’s instructions. Ensure
■ Mix in a mechanical mixer Mortar should be mixed that wall ties are properly bedded and fixed to
in a tilting drum or a ‘cement-mixer’. Hand mixing, supporting members.
eg in a wheelbarrow, should be used only in special
circumstances. PROTECTION OF NEWLY-LAID MASONRY
■ Adding materials to mixer A small amount of Newly-laid masonry should be protected from rain by
mixing water is placed in the mixer followed by the covering the top of the construction with plastic
sand, cement and lime. More water is then slowly sheeting. Mortar joints should be protected from
added to create a thick creamy mortar. premature drying out by wrapping the masonry in
■ Mix for a sufficient period of time Each batch plastic sheeting and shading the walls where possible.
should be mixed for two to three minutes to ensure a
uniform distribution of materials.
■ Use promptly Mortars should be used within half an
hour of mixing. Do not add water to mortar which Do not add water to mortar which has
has stiffened to restore workability as this will reduce stiffened to restore workability as this
the quality of the mortar and impair the masonry will reduce the quality of the mortar
Cement performance. and impair the masonry performance.
and Concrete
Association of
Australia

Page 2 of 2

helen rix d e s i g n

Potrebbero piacerti anche