REMAINING WORK ROTATING TEAM as per 17/07/2011 No 1 EQUIPMENT NAME TK 23 C & D REMAINING WORK Change bolt of flanges Inspection

level vertical pipe Tightening bolt defuser pipe support Install Vertical pipe Change bolt of flanges defuser pipe Setting & Inspection level vertical pipe Tightening bolt defuser pipe support Install Vertical pipe & Colecting pipe Inspection tightening bolt welding scrapper blade (GTAW SS) Setting elevation center whell & install inflow pipe Inspection tightening bolt welding scrapper blade (GTAW SS) Repair shaft of scrapper (change new one flange) Install wear plate Reinstall scrapper unit Setting elevation center whell & install inflow pipe welding scrapper blade (GTAW SS) Reinstall and modification handrill after erection install oil cooler and platform Install elbow and silincer Install elbow and silincer Install elbow and silincer Final Aligment Final Aligment Final Aligment Final Aligment Final Aligment Final Aligment Final Aligment Inspection tightening bolt & Final Aligment Inspection tightening bolt & Final Aligment Inspection tightening bolt & Final Aligment Inspection tightening bolt & Final Aligment Inspection tightening bolt & Final Aligment

TK 23 A & B

Tk 24 A

TK 24 B

TK 26

MIXING AGITATOR TK 11 A/B & TK 12 A/B 9 Oil cooler 10 C 41 A/B C 42 A/B/C/D C 43 A/B 11 PUMP P- 31 A/B/C P-32 A/B P- 1041 A/B P- 1062 A/B P- 11 A/B/C P- 12 A/B/C P- 33 A/B/C/D P- 22 A/B/C/D P- 23 A/B/C/D P- 27 A/B/C/D P- 24 A/B P- 1063 A/B P- 1052 A/B P- 1040 A/B P- 1051 A/B P- 13 A/B/C P- 14 A/B/C/D P- 1061 A/B P - 1050 A/B P - 1060 A/B

Grouting, Tightening bolt & Final Aligment

Install motor Change padding of foundation(follow soleplate)

Install pump & grouting

G WORK ROTATING TEAM as per 17/07/2011 STATUS on going start from 17/07/2011 REMARKS glue of pvc pipe borrow from CNJO bolt arrive at site 17/07/2011

waiting ICC

waiting ICC

Remaining work other subcont : touchup painting wear plate (DPS) Dismatle scaffolding (TTP)

waiting DPS painting wear plate

waiting new flange

after scafolding install can do to start install wear plate

on going wait remove scaffolding shelter B002 wait new material bolt from EBARA wait new material bolt from EBARA wait new material bolt from EBARA wait final conection piping & solo run wait final conection piping & solo run wait final conection piping & solo run wait final conection piping & solo run wait final conection piping & solo run wait final conection piping & solo run wait final conection piping & solo run wait final conection piping & solo run wait final conection piping & solo run wait final conection piping & solo run wait final conection piping & solo run wait final conection piping & solo run

info from EBARA : 20/07/2011 arrive

Continue on going

waiting motor wait remove scaffolding shelter B002