DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 1 of 20

DJEBEL GROUZ PROJEC

SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A

24/10/2011 23/10/2008

01 00

Issued For Review Issued For Comments

S.G. A.S.

S.H. K.B.M.

M.E. M.E.

Date

Rev.

Description of Revision

Prepared by

Verified by Approved by

Company Approval

ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 2 of 20

TABLE OF CONTENTS

1. GENERAL................................................................................................................................................4 2. DEFINITIONS & ABBREVIATIONS........................................................................................................4 3. DESCRIPTION OF THE SUPPLY...........................................................................................................5 4. REFERENCED STANDARDS AND DOCUMENTS................................................................................5 4.1. DOCUMENTS..........................................................................................................................................5 4.2. ENI SPECIFICATIONS..............................................................................................................................6 4.3. INTERNATIONAL STANDARDS......................................................................................................................6 5. ORDER OF PRIORITY OF THE DOCUMENTS......................................................................................7 6. AMBIENT CONDITIONS.........................................................................................................................7 7. SCOPE OF SUPPLY...............................................................................................................................8 8. SCOPE OF SERVICES............................................................................................................................8 9. TECHNICAL REQUIREMENTS...............................................................................................................8 9.1. GENERAL..............................................................................................................................................8 9.2. MECHANICAL REQUIREMENTS.....................................................................................................................8 9.2.1. Fire Water Pump.......................................................................................................................8 9.2.2. Bearing and Bearing Housing....................................................................................................9 9.2.3. Mechanical Seal and Packing...................................................................................................9 9.2.4. Coupling .................................................................................................................................10 9.2.5. Driver Diesel Engine.............................................................................................................10 9.2.6. Diesel Fuel System.................................................................................................................11 9.2.7. Engine Lube Oil System..........................................................................................................11 9.2.8. Engine Cooling System ..........................................................................................................11 9.2.9. Engine Exhaust System..........................................................................................................11 9.2.10. Vibration and Critical Speeds................................................................................................12 9.2.11. Starting System ....................................................................................................................13 9.2.12. Instrumentation......................................................................................................................14 9.2.13. Control Scheme and Control Panels.....................................................................................14 9.2.14. Electrical................................................................................................................................17 9.2.15. Structural Skid.......................................................................................................................17 10. INSPECTION AND TESTING..............................................................................................................17 11. SURFACE PREPARATION AND PAINTING......................................................................................18 12. SPARE PARTS....................................................................................................................................18 13. PRESERVATION.................................................................................................................................19 14. PREPARATION FOR SHIPMENT, TRANSPORT AND STORAGE....................................................19 15. DELIVERY...........................................................................................................................................19
ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 3 of 20

16. GUARANTEE.......................................................................................................................................20 17. DOCUMENTS TO BE DELIVERED.....................................................................................................20

ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 4 of 20

1. GENERAL
This specification covers the minimum requirements for the design, manufacture, fabrication, testing, inspection, packaging and supply of a Diesel Engine Driven Fire Water Pumps, complete with components and accessories, to be installed in Djebel Grouz Field located at the South East of Tunisia. The Vendor and his sub-vendors shall comply with all requirements of this Specification, Data Sheets, and the latest editions of all specifications, codes, and standards referenced in this scope of work. The packages shall be designed and guaranteed for continuous service in the environmental conditions specified, and the specified process parameters.

2. DEFINITIONS & ABBREVIATIONS


For the purposes of clarification in the present specification, the following definitions apply: Vendor: The party which supplies Diesel Engine Driven Fire Water Pump to perform the duties specified by E.N.I. Company: E.N.I. Tunisia B.V. Site: Djebel Grouz Field at the South East of Tunisia. Manufacturer: The party which manufactures or supplies equipment and pipes to perform the duties specified by the Vendor. Shall: A term which indicates that a provision is a requirement. Should: A term which indicates that a provision is recommended as good practice but is not a requirement. May: A term which indicates that a provision is neither required nor prohibited.
ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 5 of 20

NEC: National Electrical Code. SAE: Society of American Engineers. ASME: American Society of Mechanical Engineers.

NFPA: National Fire Protection Association.


IEC: International Electrotechnical Commission. DPDT: Double Pole, Double Throw.

3. DESCRIPTION OF THE SUPPLY


This specification defines the requirements for the supply of Diesel Engine Driven Fire Water Pump. The Vendor shall therefore be responsible for the design, manufacture and correct operation of the complete unit. Design and supply of the Unit shall be complete (Mechanical, Electrical, Instrument, etc.) in order to ensure proper Operation, Maintenance, Safety and Control within the Unit Battery Limits.

4. REFERENCED STANDARDS AND DOCUMENTS


The following documents, codes and standards are referenced in this specification:

4.1.Documents
55117-ENI-SF-DS-DA-004: Diesel Engine Technical Data Sheet. 55117-ENI-SF-DS-PA-001: Diesel Firewater Pump PA 1100 A Technical Data Sheet.

ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 6 of 20

55117-ENI-SF-DS-PA-101: Diesel Firewater Pump PA 1100 A Inspection Data Sheet (IDS). 55117-ENI-SF-DS-PA-201: Diesel Firewater Pump PA 1100 A Required Documents Data Sheet (RDDS).

4.2.ENI Specifications
20000. VAR. PAI. FUN Rev.2 : Protective coating and hot dip galvanising functional specification 15801. PIP. MEC. SDS Rev.1: Company specifications manual valves. 07423. PKG. GEN. SPC Rev.0: Inspection and tests for package supplies. 03023. MAC. MEC.SPC Rev.2: General Specification Diesel Engines

4.3.International Standards
NFPA 20: Standard for the installation of stationary pumps for fire protection, 2003 Edition. IEC 62091: Low Voltage Switchgear-Controllers for drivers of stationary fire pump. IEC 60364: Electrical Installation of buildings. IEC 60529: Degree of Protection provided by enclosures. IEC 60947: Low voltage Switchgear and control gear. IEC 60439: Low Voltage Switchgear.

ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 7 of 20

5. ORDER OF PRIORITY OF THE DOCUMENTS


In the event of a conflict between this Specification, data sheets and the applicable codes and standards, the Vendor shall bring the matter to the Companys attention for positive clarification, resolution and review in writing before any work is started. In the absence of any guidance or agreement to the contrary, the most stringent requirements shall apply. Should any conflict occur as a result of applying data sheets and specifications, the order of precedence shall be as follows:

Purchase Order. This Specification including data sheet. E.N.I. General Specifications. Codes and Standards. Other International Codes and Standards.

6. AMBIENT CONDITIONS
The Supplier shall consider the following design site ambient conditions for the package design:

Air Temperature: Humidity: Elevation: Wind velocity Speed: Rainfall (average):

Min: -5 C Min: 40 %,

Max: 50C Max: 90 %

274 m above the sea level. 180 km/h. 25 mm/year.

ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 8 of 20

7. SCOPE OF SUPPLY
The Vendor shall be responsible for the provision of Diesel Engine Driven Fire Water Pump completely assembled which shall be painted and tested at shop. The Vendor shall provide all technical documentation relative to the Diesel Engine Driven Fire Water Pump.

8. SCOPE OF SERVICES
Services shall include but not limited to:

Inspection and testing. Surface preparation and painting. Preservation for storage. Preparation for shipment. Delivery Ex-works.

9. TECHNICAL REQUIREMENTS 9.1. GENERAL

The Vendor shall ensure that the Diesel Engine Driven Fire Water Pump is designed for maximum reliability, minimum maintenance and it shall be designed and constructed for a minimum service life of 20 years.

9.2.

MECHANICAL REQUIREMENTS

9.2.1. Fire Water Pump


The Firewater Pump shall be a Centrifugal Pump compliant to NFPA 20.
ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 9 of 20

Pump shall have the possibility for local / manual operation as well as remote / Automatic operation. Pumps design data is shown on the attached Data Sheet 55117-ENI-SF-DS-PA-004. In the event of conflict between this specification and Data Sheet, the Data Sheet shall govern. Firewater pumps speed shall not exceed 1800 RPM. Firewater pumps shall be horizontal centrifugal pumps with radial displacement as per NFPA 20. The pumps shall have suction strainers in accordance with NFPA-20. Bearings housing shall be arranged so that bearings can be replaced without disturbing pump drivers or mounting. Mounting skid shall be separate and located sufficiently below from the main body flange in order to facilitate bolting on the body flange.

9.2.2. Bearing and Bearing Housing


Bearings shall be lubricated by constant-level oilers.

9.2.3. Mechanical Seal and Packing


Detail of mechanical seals offered by the Vendor shall require Company approval prior to installation. The Vendor shall recommend and describe number, size, and material of packing rings, lantern rings, etc. Stationary mechanical seal faces shall be O ring mounted with a radial pin to prevent face rotation.

ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 10 of 20

9.2.4. Coupling
The coupling between the engine and the gear shall be short coupled universal shaft with flanges for driver and driven shaft. It shall be sized to handle full engine power with a minimum service factor of 1.75. Coupling shall be designed to prevent engine vibration, caused by misalignment. Coupling shall allow the engine or the pump to be removed without disturbing the other. Coupling shall be dynamically balanced and rated for a minimum bearing life of 5000 hours. A removable non-sparking guard shall be provided around the coupling. All bolting for shaft guard shall be type 316 stainless steel with a minimum spacing of 150 mm and a minimum diameter of 10 mm.

9.2.5. Driver Diesel Engine


The diesel engine driver shall conform to NFPA-20 requirements and shall be approved for fire pump use. The intermittent engine shaft horsepower shall be at least 1.2 times the maximum horsepower required to drive the fire pump at 150% of its design capacity at the rated RPM, installed elevation and engine inlet air temperature. The required horsepower shall include the pump and all the engine auxiliaries. Engine power ratings shall comply with power test codes of S.A.E. and A.S.M.E. A hydro-mechanical governor with a positive locking control shall regulate engine speed within a range of 10% between shut-off and maximum load conditions of the pump. There shall be no manual throttle.

ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 11 of 20

9.2.6. Diesel Fuel System


The fuel system shall include a fuel filter with readily replaceable filter media. The fuel system shall be leak-free throughout all conditions of engine operation. The inlet to the fuel system shall be readily connectable to a fuel supply line employing connections designed in accordance with a recognized standard of the nation to which the engine is to be delivered.

9.2.7. Engine Lube Oil System


A full flow engine lubrication pressure system with pump, strainer, piping, heat exchanger and full flow oil filter equipped with a bypass valve and pressure gauge shall be provided. Filters shall be furnished with accessible and easily replaceable cellulose type filter elements. All piping downstream of lube oil filters shall be stainless steel. Flexible connections shall be wire braid reinforced type 316 stainless steel bellows type.

9.2.8. Engine Cooling System


The engine cooling system shall be included as part of the engine assembly and shall be a radiator type that includes a circulating pump driven by the engine, a radiator, an engine jacket temperature regulating device, and an engine-driven fan for providing positive movement of air through the radiator.

9.2.9. Engine Exhaust System


Exhaust system in accordance with NFPA 20, shall be complete with all piping, fittings, brackets and supports. A properly sized rain cap shall be provided. Exhaust ducting shall be carbon steel with expansion bellows of 316 stainless steel, seamless or welded corrugated design, mounted between engine outlet and exhaust pipe. Silencers shall be furnished with spark arresters and support straps with vibration isolators.
ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 12 of 20

Engine exhaust manifold, and turbo charger if furnished, shall be water cooled. All other surfaces of exhaust system, silencer, flanges and expansion bellows shall be insulated.

9.2.10. Vibration and Critical Speeds


The Vendor shall assume full responsibility for performance of necessary torsional studies and elimination of any lateral or torsional vibrations that may adversely affect operation of complete unit within specified operating range. Torsional natural frequencies of engine and driven equipment shall not be closer than 10% to any specified running speed. The Vendor shall submit proof that required torsional vibration studies have been satisfactorily performed. Requirement shall be per Vendor Document Requirements.

ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 13 of 20

9.2.11. Starting System


All systems shall be furnished in accordance with NFPA 20 except where modified herein. Starting system shall be furnished with logic that prevents operation of starting motor when engine is running. Pump shall be capable of starting by either:

Remotely initiated signal (electric) from Master Control Panel. Loss of signal shall start
pump.

Manually initiated signal (local).


Pump shall be stopped by local manual action only, except when it is in its "Test" mode. The primary starting system shall be suitable for operation with compressed air, in EEx d IIB T1 hazardous area. The secondary (backup) start system shall be nitrogen gas stored in high pressure cylinders. It shall provide sufficient volume for three (3) start attempts. The Vendor shall also provide the high pressure regulator in the nitrogen outlet manifold. The volume of the air/nitrogen tank shall be sized for 180 seconds of continuous cranking start attempts without recharging. Dry nitrogen will be fed to the volume bottle at 10.34 barg from high pressure nitrogen cylinders. The volume bottle shall be an ASME coded pressure vessel designed for 13.8 barg, and shall be protected by a relief valve, sized for fail-open capacity of the nitrogen regulator. The primary (air) and secondary (nitrogen) systems shall be with manifold such that either air or nitrogen will be available to the starter valve. A low pressure switch on the start air line shall initiate the flow of nitrogen to the starter. All valves in the air start and nitrogen start systems shall be carbon steel.

ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 14 of 20

9.2.12. Instrumentation
Vendor shall supply all controls and instrumentation, associated with pumps and drivers, to reach Company and NFPA-20 design philosophy. The low pressure switches monitoring the firewater header pressure shall be supplied and mounted on pump control panels by vendor. Level gauges on the nitrogen gas bottle shall be a reflex type. Vendor shall install all required pneumatic tubing on the skid. All tubing external to the panel shall be 3/8" O.D. 316 stainless steel, 0.035" wall minimum, supported in tubing trays. (Tubing strapped to pipe is not acceptable.) Tubing installations shall be neat, plumb, properly supported and exhibit professional workmanship. A Pressure Indicator shall be installed at pump discharge line.

9.2.13. Control Scheme and Control Panels


Panel and stand shall be mounted on skid. Pneumatic and wiring connection of the control panel shall be required to external piping and wiring circuits furnished by others. All necessary valves, regulators and gauges shall be supplied by Vendor. Pressure and temperature gauges shall be liquid filled, with stainless steel cases. Tubing shall be type 316 stainless steel. Panel enclosure shall be constructed of 316 stainless steel with a brushed finish, free of tool and clamp marks. All internal braces, enclosure hardware and instruments shall be 316 stainless steel. Panel shall have removable, full opening doors on rear side with heavy duty 316 stainless steel hinges and closures.
ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 15 of 20

Panel nameplates shall be stainless steel, engraved type. All bulkhead connectors shall have nameplates both inside and outside the panel enclosure. Instruments shall be provided with permanently attached nameplates. Nameplates on the panel shall be mounted with 316 stainless steel screws. Instrument air pressure to the panel shall be 7-10 bar. Regulators shall be provided to reduce the pressure to the required pressure needed by the logic circuits. While running, loss of instrument air to the panel shall not cause shutdown of the pump. Panel shall house pump stop/start controls and test/auto selector switch. While in auto mode, all shutdown devices shall be disarmed. All alarm and indication functions shall operate normally. Panel shall contain all procedures necessary to start pump if not already running. procedures shall control starting sequence in accordance with NFPA guidelines. Except when the pump is running in "Test" mode, low fuel level, low oil pressure, engine over speed and high jacket water temperature shall run an audible alarm and a red flashing alarm. In "Test" mode, these malfunctions shall shut down the pump. The pump status (run, fail) shall be transmitted to a remote control panel through an electrical signal. Pump running signal shall be generated from an oil pressure switch set at rated engine oil pressure to ensure running signal will not be displayed unless engine has started and achieved operational running speed. The following instruments shall be furnished as a minimum on control panel:

Tachometer (range 0-125% rated speed), with adjustable over speed trip setting, over
speed alarm, digital speed indicator and test function.

Engine oil pressure gauge. Engine cooling water temperature gauge.


ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 16 of 20

The following alarms and shutdowns shall be provided. Alarm signals shall be displayed on control panel by means of first-out indicators. All shutdowns shall be bypassed in auto mode.

Oil pressure - low Coolant temperature - high Over speed Engine fail to start Fuel level - low

Alarm X X X X X

Shutdown (Test mode) X X X X

Vendor shall furnish following independently mounted instruments and controls:

Coolant level indicator. Fuel tank level gauge. Crank case dipstick. Jacket water inlet and outlet temperature indicator. Coolant flow indicator. Coolant inlet and outlet pressure gauge.
Vendor shall submit the wiring and connection diagram of the control panel logic, bill of materials, panel front layout, and name tag list for Company approval prior to fabrication of the panel.

ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 17 of 20

9.2.14. Electrical
All skid mounted electrical control and instrumentation systems shall be installed in accordance with NFPA-70, NEC or IEC Vendor shall do the wiring from devices on the skid to the unit control panel. All controls and signals which go off-skid shall be wired to a separate junction box located on the edge of the skid. Provide six (6) spare terminals. Electric pressure switches and solenoid valves shall be explosion proof material. Pressure switches shall be DPDT Electrical form. All electric installations shall conform to NEC or IEC recommended practices for EEx d IIB T1 hazardous areas.

9.2.15. Structural Skid


Vendor shall be responsible for supplying the completed and assembled package on structural steel skids. Vendor shall be fully responsible for the detailed design. Each skid structure shall be designed for a single point lift. Lifting eyes shall be provided on skid. All equipment shall be mounted on structural members of the skid. Packaging shall be suitable for withstanding transportation loads during ocean and truck transportation. All load bearing members shall be connected by full penetration welds. All defected surfaces shall be continuously seal welded.

10.INSPECTION AND TESTING


Inspection and testing of the pumps and all associated auxiliary items shall be carried out in accordance with the relevant codes, standards, approved procedures and Inspection Plan. The Vendor shall provide an Inspection & Testing Plan for purchased review and comments.

ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 18 of 20

The equipment shall be subject to inspection and witnessing of tests by the Company, as and when required. The Vendor shall provide free access to his work for the authorized representative of the Company. All necessary certification of materials, shop test data, etc, shall be made available to verify that the requirements of the Company are being met. Acceptances of shop Tests shall not relieve the vendor to meet field tests under specified operating condition, nor does the inspection relieve the Vendor of his responsibility.

11. SURFACE PREPARATION AND PAINTING


The preparation and painting procedures must comply with the attached ENI specification: 20000. VAR. PAI. FUN. As option, the Vendor may include in the offer his standard painting procedure for approval. The Vendor shall paint the equipment and materials within his scope of supply, which shall be done at Vendors facilities to the maximum extent possible. Paint materials to be used shall be in accordance to the paint specification attached.

12.SPARE PARTS
The Vendor shall provide all spare parts required for construction, pre-commissioning, commissioning and Start-up. The vendor shall provide quotation for Spare Parts of the various components of the supply according to his experience as follow: Capital spare Two Years of Operation.

Each part shall be separately quoted.


ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 19 of 20

Spare parts definition shall include sectional drawings and/or exploded view to identify the listed parts on the relevant Spare Parts Form.

13.PRESERVATION
The extent of preservation to be applied shall be based on the assumption that a minimum of 06 months will pass before the equipment is ready for initial start-up. The Vendor shall specify his recommendation for the preservation for both indoor and outdoor storage. Provided manuals shall list all the conservation applied and all measures required for upkeeping the Diesel Engine Driven Fire Water Pump until installation time.

14.PREPARATION FOR SHIPMENT, TRANSPORT AND STORAGE


The Diesel Engine Driven Fire Water Pump, shall be crated, properly protected and marked for export and shipment. It shall be adequately preserved and sealed to withstand any adverse condition evolving from the mode of transportation (trucks in desert and bad condition road; dusty environment).

15.DELIVERY
The Diesel Engine Driven Fire Water Pump shall be delivered Ex-works. Its Vendors responsibility to provide all necessary paper work and documentation for transportation and customs clearing (if any).

ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.

Oil & Gas Engineering Services

DJEBEL GROUZ PROJECT SUPPLY SPECIFICATION FOR DIESEL ENGINE DRIVEN FIREWATER PUMP PA1100A
CONTRACTOR Document N: 55117-ENI-SF-SA-PA-301 COMPANY Document N: Rev: 01 Page : 20 of 20

16.GUARANTEE
The Diesel Engine Driven Fire Water Pump, component parts shall be guaranteed by the Vendor against defective materials, design and workmanship for a period of 12 months after start-up or 18 months after delivery. If any mal-performance or defect occurs during the guarantee period, the Vendor shall make all necessary alterations, repair and replacements free of charge.

17.DOCUMENTS TO BE DELIVERED
The following documents shall be provided prior to the shipment of the Diesel Engine Driven Fire Water Pump: Material certificate Certificate of Conformity Certificate of shop visual inspection by third party Inspector Certificate of shop Hydro test by third party Inspector Installation, operating and maintenance instructions.

ALPHA ENGINEERING Intl. Immeuble Jeaiem, A8, Avenue Yasser Arafat Sahloul 1, 4000 Sousse - Tunisie Code TVA : 950448R/A/M/000. R.C : B279902006 Tl : +216 73 821 245 / 246 / 247 Fax : +216 73 821 249
This document is the property of Alpha Engineering International who will safeguard its rights according to the civil and penal provisions of the Law.