Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Abstract-Cogeneration and Independent Power and steam turbines in early 1900s saw cogeneration and
Producers are playing an increasing role in deregulated IPP fall increasingly out of favour for residential use,
electricity supply markets. The scheduling of combined heat being replaced by boilers and utility-supplied power. By
and power outputs from multiple-generator cogeneration the 1940s IPP cogeneration was only suitable for the
plants is a complicated problem that needs powerful largest industrial power users and users of process heat.
methods to solve. Representative test systems are required to
test any new method in the development of new algorithms.
This paper presents a test system and a set of solutions for Interest in cogeneration was renewed in the early 1980s
demand cases. The proposed new test system could be used following the PURPA reform act in 1978. Initially the
as a standard test system for assessing cogeneration focus was on more efficient use of fossil fuels and the
economic dispatch algorithms. issues investigated were primarily economic feasibility
studies and case studies for conversion of existing plant to
Index Terms-Cogeneration, Combined Heat and Power, cogeneration. Throughout the 1980s technological
Economic Dispatch Evolution Computation, Independent advances in gas turbine components and an increased
Power Producers, Test System supply of natural gas lead to IPP gas turbine cogeneration
and combined cycle plants becoming economically viable
1. NOMENCLATURE alternatives to utility supplied electricity. The efficiency
of single cycle gas turbines is now comparable (or better)
Pi Active Power MWe, than coal-fired steam turbine plant, and combined cycled
hj Thermal Power (Steam) MWth gas turbines are approaching 60% thermal efficiency.
C,(pi) Generation Unit Cost Economic scheduling strategies for supplementing utility
Cj(hj) Thermal (Boiler) Unit Cost supplied power and independently meeting internal power
Ck(pk,hk)Cogeneration Unit Cost needs from on-site cogeneration [1]-[5] continued to be
Gena An Electricity Unit in a Cogeneration System investigated.
Cogp A Cogeneration Unit in a Cogeneration System
Boil, A Process Steam Unit in a Cogeneration System However, unlike the traditional, electricity-only
H-P Heat(MWthtPower(MWe) Cogeneration Demand economic dispatch (ED) problems, cogeneration ED
problems do not have a standard set of test problems for
11. INTRODUCTION assessing algorithms. The demonstration system and
demand case used by Guo, Henwood and van Ooijen [ 11,
Cogeneration, or combined heat and power (CHP), and has become a defacto standard test case because: a) it is a
Independent Power Producers (IPP) have had a role in cogeneration system, and; b) it is to-date the only test
industrial and residential power supply and heating since system published in the literature. This test system has a
the inception of commercial power supply in the 1880s. number of strong points, especially concerning the
The small capacity and short transmission distance modelling cogeneration unit Feasible Operating Regions,
achievable from DC power generation meant that however it has inherent weaknesses that make it
electricity users were forced to a certain extent to utilise unsuitable as a “standard” test system for algorithm
waste heat from the generators’ coal furnaces for heating development.
purposes. The increased transmission distances and
capacity increases made possible by AC power generation As part of the development of an Evolution
Computation (EC) algorithm for solving IPP cogeneration
C. Algie obtained his Master of Engineering Science from the School ED [ 5 ] , a new test system has been designed by the
of Electrical Electronic & Computer Engineering, The University of authors. The new system augments the old system model
Western Australia in 2003 and now works for CSR Sugar.
(calgie@graduate.uwa.edu.au)
from [ l ] with new generation unit models. In this paper,
the strengths and weaknesses of the old test system are
Professor K.P. Wong is Chair and Head of the Department Electrical discussed and the new test system is described. The
of Engineering, Hong Kong Polytechnic Univcrsity, as well as member solutions of three heat-power demand cases solved by the
of Staff of the School of Electrical Electronic & Computcr Engineering, authors’ EC algorithm are presented for the purposes of
The University of Wcstcm Australia.
demonstrating the different types of dispatch solutions
that the new test system can provide.
0-7803-8237-4/04/$17.0002004IEEE
96
2004 IEEE International Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DWT2004) April 2004 Hong Kong
97
2004 IEEE International Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004)April 2004 Hong Kong
showing passive variables, Units 1 and 4, and a minimum generators available to meet the remaining demand. In
cost that is insensitive to a small variation, 6, in the output practical terms, a test system for cogeneration ED
of Units 2 and 3. problems should consist of two or more generation units.
By including two different cogeneration unit models, a
boiler and a power generator, the effects of these two
auxiliary units can also be taken into account.
Unit 1 Unit 2 Unit3 Unit4 Cost The cogeneration units used are of significantly
Min A B Max $min.xxxy different maximum capacities; one is 247 MWe of
Min A+6 B-6 Max $min.xxxz electricity and 180 MWth of in steam, the other 125.8
MWe and 135.6 MWth. This corresponds to modelling a
Difficult cases are characterised by extreme variable new smaller gas-turbine unit (125.8 MWe unit) being
sensitivity and the involvement of all generators in the added to increase power and steam output capacity of an
solution process. Though outputs may be minimums or older coal-fired (247 MWe unit) plant.
maximums, they will not be passive. Difficult cases tend
to occur near the edge of the FDR and involve generation Not only are the cogeneration units modelled for this
units competing for minimum or maximum output, though system of different output capacities, but they also use
they can also occur in the central regions (see Section VI). different FOR models; an irregular quadrilateral like
Table 111 demonstrates a generic “maximised” difficult Figure 1 (247 MWe unit) and a two-segment model (125.8
solution where a slight change, 6, to Unit 2 output affects MWe unit). The irregular quadrilateral is the “standard”
the outputs of Units 3 and 4, in turn significantly FOR model and is suitable for modelling all types of
increasing (+ A) the minimum operating cost. cogeneration unit. Though better suited for modelling
possible outputs from gas turbine cogeneration units, the
TABLE I11 authors of this paper found [6] that in practical terms, the
DIFFICULT
SOLUTIONCHARACTERISTICS two-segment model has no advantages over a single
quadrilateral. However, the two-segment model provides
Unit 1 I Unit 2 I Unit 3 I Unit 4 I Cost challenge to CHP dispatch problem solution
max I A I B I max I Smin methodologies; the FOR model for the 125.8 MWe unit
I max I A+6 I B-%6 Imax-%i3I $min+A I will be shown in Section VI.
B. Weaknesses
V. AN EXISTING TEST SYSTEM
Though the cogeneration unit capacities and generator
Guo, Henwood and van Ooijen [l] developed a mix for this test system are sound in principle, the models
Lagrangian Relaxation method for solving cogeneration used for the auxiliary boilers and generators have
dispatch problems. To demonstrate the method, they compromised the validity of the system. Instead of using
chose a test system and heat-power demand case that quadratic models for heat characteristics, single variable,
would allow a complete solution process to be shown in linear coefficients have been used. Because of this, these
only seven steps. This demonstration system has become a auxiliary units are quickly discounted in the Lagrangian
starting point for comparison of other methods by other Relaxation solution process. The linear coefficients have
researchers. Though the test system contained all elements been selected to be larger than the heat-only and power-
necessary to describe cogeneration plant system, certain only partial derivatives of the cogeneration heat
parameters were chosen as to ensure the optimal result characteristic models. Also the minimum viable outputs
was found in minimal time, thus removing the element of for auxiliary units have been set at 0 MWth and 0 MWe
challenge that is required for a more general test. The respectively.
strengths and weaknesses of the existing test system are
discussed below. A linear model is an acceptable model for boiler heat
characteristics, however the lack of an offset term is
A. Strengths questionable. Using 0 MWth as minimum output is a
reasonable approximation. However the maximum
This test system can be tailored to cover the majority of capacity of the boiler model (approximately 2700 MWth)
IPP cogeneration configurations. The defining features of needlessly expands the FDR.
cogeneration system are that they contain at least one
cogeneration unit and that the total power and heat outputs The simplified generator model is definitely not
of the system cannot be separated. In most cogeneration acceptable. The heat characteristic at least should be
system’s FDR either the maximum heat or power output piecewise linear, or a continuous quadratic, with a
will significantly outweigh the other. In these cases, it is significant offset term. Also the minimum output should
more economical to be able to meet the smaller of the be at least 25% of the maximum, i.e. around 40 MWe
maximum demands with cogeneration only, and then have would be expected given the maximum output is 150
auxiliary heat-only units (coal-fired boilers, or auxiliary MWe.
firing of heat recovery steam generators) or power
98
2004 IEEE Intemational Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004) April 2004 Hong Kong
cogeneration units) and the approximately 2: 1 capacity Fig. 4. Cogencration Unit 3 2-Segment FOR
ratio between cogeneration units. Only the gas-turbine
cogeneration unit, and its 2-segment FOR model, was The cogeneration unit FOR regions and output ranges
reused. A smaller cogeneration unit replaces the 247 of equations (8) and (9) have been combined to form the
MWe unit from Section 4 and fresh boiler and generator new test system's FDR. This is shown in Fig. 5.
models have been sourced. Heat characteristic / cost
functions of the units are shown in (4) - (7).
30 -
(0 20 40 60
Hnt.2 (Mwthl
Fig. 3. Cogeneration Unit 2 FOR
99
2004 IEEE Intemational Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004)April 2004 Hong Kong
VII. THREE DEMAND CASES optimal settings (again causing knock-on effects on the
others) without affecting the total cost.
To demonstrate the difficult and simple solutions to
demand cases, studies were run for three cases using the C. Case 3: 240 MWth - 250 MWe (Diflcult)
authors’ Cogeneration Economic Dispatch - Evolution
Program solution algorithm, “CED-EP” [ 5 ] . All cases TABLE VI
SOLUTIONS FOR 240-250 DEMAND CASE
were run for ten trials each. For the two simple cases, “1”
and “2” in Figure 5, each trial was allowed a maximum of
500 iterations, and the difficult case, “3” in Figure 5, was
allowed a maximum of 2000 iterations. In each of the set
of results shown, Tables IV, V, and VI, the top row (in
italics) is the optimal solution, followed by three
representative cases from the 10 trials run. The columns
are the generation units’ outputs followed by the total cost. Of the 2000 iterations available, between 640 and 1993
iteration were used. None of the trial runs found the
A. Case 1: 125 MWth - 205 MWe (Simple) optimal solution. In terms of variable settings, all
TABLE IV
solutions were very close, but not in absolute dollar terms.
SOLUTIONS FOR 125-205 DEMANDCASE Apparent failures like this lead to the investigation of the
underlying factors in difficult cases.
IO0
2004 IEEE International Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004) April 2004 Hong Kong
XI. REFERENCES
101