Sei sulla pagina 1di 3

Objective:

Presenting methods for evaluating and comparing projects


Lecture 9 Topics Covered:
- Relations Among Projects
- Minimum Acceptable Rate of Return (MARR)
- Present Worth (PW) and Annual Worth (AW) Comparisons
Comparison Methods Part - Present Worth for Independent Projects
- Present Worth for Mutually Exclusive Projects
1, cont’d. - Annual Worth Comparisons

Topics to be Covered:
- Present Worth (PW) and Annual Worth (AW) Comparisons
- Comparison of Alternatives with Unequal Lives
- Payback Period
1 2

Engineering Economy 85-313-(01 & 02) Engineering Economy 85-313-(01 & 02)

Comparison of Alternatives with Unequal Example 4.6 (p. 98):


Lives A mechanical engineer has decided to introduce automated
material-handling equipment for a production line. She
- PW comparisons can not be used with projects of different lives must choose between two alternatives, building the
equipment or buying the equipment off the shelf. Each
- Methods of transforming projects to equal lives: alternative has a different service life and a different set of costs.
- Repeated lives: Alternative 1: Build custom automated material-handling equipment
- Repeat the service life of each alternative to arrive at a common
with an expected service life of 10 years.
time period to all alternatives (least common multiple). First cost Labour Power Maintenance Taxes & Insurance
$15,000 $3,300/yr $400/yr $2,400/yr $300/yr
- Assume that each alternative can be repeated with the same costs
and benefits in the future. Alternative 2: Buy off-the-shelf standard automated material-handling
- Study period: equipment with an expected service life of 15 years.
First cost Labour Power Maintenance Taxes & Insurance
- Adopt a specific time period that is given for the analysis.
$25,000 $1,450/yr $600/yr $3,075/yr $500/yr
-Assume a specific salvage value whenever the life of one of the
alternatives exceeds that of a the given study period. 3
If the MARR is 9%, which alternative is better? 4

Engineering Economy 85-313-(01 & 02) Engineering Economy 85-313-(01 & 02)

1
Repeated indefinitely Payback Period
assumption (AW method) - It is a rough estimate of the time it takes for an investment
to pay for itself when the interest rate is assumed to be zero
z There is a more convenient approach for an annual - It should be used as a preliminary filter rather than a sole criterion
worth comparison of projects of unequal lives if it for evaluating projects.
can be assumed that the alternatives are repeated
Payback period = (first cost)/(annual savings)
indefinitely.
z Since the project would repeat indefinitely, its Example 4.8 (p. 103):
annual costs would remain the same no matter A project with initial cost $5,000 and annual savings of $2,000.
how many times it is repeated, it is not necessary to
- Assuming that the savings occur over the whole year:
determine the LCM of the service lives.
Payback period = $5,000/$2,000 = 2.5 years
z The AW can be assessed for whatever time period
is most convenient for each alternative. - Assuming that the savings occur at the end of the year:
Payback period = 3 years
5 6

Engineering Economy 85-313-(01 & 02) Engineering Economy 85-313-(01 & 02)

Payback Period, cont’d. Payback Period, cont’d.


- If the annual savings are not constant every year,
savings are deducted from the first cost until the first cost is
recovered. - The project with shorter payback period is the preferred
Example 4.9 (p. 103): investment.
A project of initial cost $8,000 and annual savings of $3,000, $2,000 - The maximum payback period is defined by the company
and $1,500 for the next 3 years and $1,000 for the following 2 years. depending on the type of project and the company’s financial
What is its payback period? situation.
- Paid amount after 3 years = $3,000+$2,000+$1,500=$6,500
- Payback periods are usually between 2 and 4 years.
- Paid amount after 5 years = $6,500+$1,000+$1,000=$8,500
- Payback period = 4.5 years assuming savings occur continuously
throughout the year
- Payback period = 5 years assuming savings occur at the end of
each year 7 8

Engineering Economy 85-313-(01 & 02) Engineering Economy 85-313-(01 & 02)

2
Discounted Payback Period Recommended Problems
The present worth of each year’s savings is subtracted from
the first cost until the first cost is diminished to zero.
Problems: 4.1, 4.9, 4.13, 4.17, 4.25 & 4.42
Example (p. 104):
A project with initial cost $5000 and annual savings of $2000. If the
interest rate is 10%, the present worth of savings would be:
Year PW Cumulative
1 $2,000(P/F,10%,1)=$1,818 $1,818
2 $2,000(P/F,10%,2)=$1,653 $3,471
3 $2,000(P/F,10%,3)=$1,503 $4,974
4 $2,000(P/F,10%,4)=$1,366 $6,340

The discounted payback period is over 3 years, compared with 2.5


years calculated for the standard payback period
9 10

Engineering Economy 85-313-(01 & 02) Engineering Economy 85-313-(01 & 02)

Potrebbero piacerti anche