Sei sulla pagina 1di 8

Energy Policy 30 (2002) 575–582

Experience and new challenges in the Chilean generation and


transmission sector
Oscar E. Moya*
Department of Electrical Engineering, University of Chile, Av. Tupper 2007, P.O. Box 412-3, Santiago 6513027, Chile

Abstract

The Chilean electrical sector was deregulated in 1982, where unbundling was applied, and generation competition and marginal
costing were introduced. Description of the main features of the generation market and system operation is presented, followed by a
synthesis of the main achievements and difficulties experienced in the practical application. The experience with the troubles faced in
the reformed power sector after 18 years is used to look at the possible advantages of the second stage of deregulation. The
challenges of a new legislation, where the system is expected to join the second generation of deregulation are discussed. Advantage
and risks of opening the energy market with a bidding system separate from ancillary service market are analysed. The experience
with the troubles faced in the reformed power sector after 18 years is used to look at the possible advantages of the second stage of
deregulation. r 2002 Elsevier Science Ltd. All rights reserved.

1. Introduction generation leaving transmission and distribution as


regulated areas. The National Energy Commission
The original vertically integrated electrical sector in (NEC), the regulator body reporting to the Ministry of
Chile was formed during the national interconnection Economy, was the entity assigned to co-ordinate the
and electrification plan of 1940, by connecting hydro- system development through an indicative plan. Actual
electric power stations in the South to the main planning was left in a decentralised way to generating
consumer centres located in Santiago and Valparaiso. companies. National Energy Commission has the
State-owned ENDESA was committed to project, install mission of defining regulated distribution electricity
and operate several reservoir hydro plants from 1940 to rates for small customers, below 2 MW of installed
1982. Another utility, CHILECTRA, initially private capacity, and setting the by-laws that complemented the
owned and then nationalised, in charge of distribution main electrical law. The Commission also calculates
in the main cities, installed some thermal plants in the periodically nodal prices of energy and power for the
central part of the country. high voltage nodes of the SIC. These are the regulated
The period featured a demand increase of about 7% values at which distribution companies buy electricity
per year, due to vegetative growth and industry for their regulated consumers.
development and by the incorporation of a large On the other hand, the first open market for
number of small locations to the electrical system. generation was started with large customers, over
Electricity reached over 97% of the population located 2 MW, who should negotiate their supply with any of
in the part of the country covered by the central system. the generators or a combination of them. Competition
International agencies credits helped financing the in power supply was encouraged.
electrical development funded by the state. The genera- With the unbundling process Endesa was sepa-
tion was mainly hydraulic, supplying between 60% and rated into two generator companies, giving origin to
80%, depending on the hydrological conditions, and !
Colbun company, and a transmission company
coal-based thermal plants. Transelec. Chilectra splitted into the generation entity
In 1982, the deregulation process started by passing now called Gener and kept only as a distribution
the Electrical Law, which opened the market to company of the metropolitan area. Thus, there were
three actors in the generation field, Endesa, Colbun !
*Fax: +56-2-695-3881. and Gener, though by far Endesa remained as the
E-mail address: osmoya@die.uchile.cl (O.E. Moya). largest one.

0301-4215/02/$ - see front matter r 2002 Elsevier Science Ltd. All rights reserved.
PII: S 0 3 0 1 - 4 2 1 5 ( 0 1 ) 0 0 1 2 7 - 6
576 O.E. Moya / Energy Policy 30 (2002) 575–582

The co-ordination of operation was assigned to an ordinated manner, which has effects on economic
operating body, Economic Centre of Load Dispatch operation and security of service.
(CDEC), which was originally formed by staff of the Co-ordinated economic dispatch means that the
generation companies. It was established only for the system is operated under minimum cost criteria, by
central interconnected system (SIC), 1800 km long, which using the audited cost information provided by the
covers 80% of the country’s electrical consumption. generating companies to the authority and to the CDEC.
Privatisation was initiated in 1986 by putting stocks to The electrical legislation (DFL 1, 1982) states that the
sale to institutions, mainly social security funds, and the marginal costs have to be determined in a time horizon
public. suitable for operation planning (Bernstein, 1988).
In 1995, the second CDEC in the country was created, Though there are four interconnected power systems
the northern interconnected system (SING), after in the country, the marginal cost procedures are used
connection of the generation components of the north- only in the central system (SIC), with a peak demand of
ern utilities that supplied different cities and mining 4800 MW, and in the northern system (SING,
processing plants that are the main load centres in that 1200 MW). The two other systems located in the
area. This system is purely thermal based on coal and extreme south are very small and fully regulated. A
originally had two generators Electroandina and Edel- computational model for the central system is used to
nor. It is isolated from the central system due to the long determine the economic cost of water for each time
distances involved. There is a desert zone of nearly interval in a 4-year horizon, period that is necessary
400 km between SIC and SING systems with almost no because the main reservoir, Lake Laja, has an inter-
consumers in between. annual regulation capability. In the absence of hydro-
In 1998, both CDECs became independent in opera- electric reservoirs in the northern system, the
tion and personnel, though generation and transmission interannual simulation becomes unnecessary. Economic
companies’ representatives form its Board of Directors. operation therefore is solved on an annual basis, by a
Companies in the generation sector in SIC today merit order method, considering the usual constraints,
include mainly Endesa (55% of the market), Gener which include transmission capacity and availability.
(20%), Colbun ! (17%) and several other minor compa- In both systems, availability is simulated with a
nies (8%). probabilistic model considering historical outages rates
After an economic protocol for natural gas import of thermal units. Load variation in time is taken into
from Argentina was approved, combined cycle gen- account by means of load forecast both for the next year
erators (CCG) entered the central system (three plants and for the shorter terms.
with 350 MW each) and the northern system (five plants A decomposition of the load curve in blocks is
with a total of 1480 MW). This was partly due to their performed, where a solution for each block should be
low variable costs, which made them very attractive in a searched. Interdependence amongst these blocks ap-
competitive environment. A substitution process took pears as a consequence of the thermal generation, which
place in the northern system, which had the unexpected imposes that a unit must remain in service for time
consequence of over-investment in capacity of about periods that exceed the daily horizon. The demand curve
120%. is represented as a duration curve with six blocks of load
The first CCG plant located in Argentinean land, levels valid for each month of the year.
Salta, delivering energy to the Chilean northern system, Operating costs of thermal units have fixed and
via a 350 km, 345 kV line, came into service in 1999. In variable components. Fixed items are costs incurred by
the decade 1990–1999, three other entities were opened 1 h of operation irrespective of the power output level [$/
in the SING: Gener, with coal-based units, Salta and h]. Variable costs include fuel consumption and other
Nopel, with CCG stations. variable items that are dependent on the power output
The following sections provide a view of the economic [$/kW h]. Audited costs are used for economic dispatch.
dispatch procedures and the mechanism to assure timely The economic dispatch is then technically defined and
investments in the electrical sector and a degree of solved by CDECs, in a procedure completely indepen-
reliability of supply. dent from the energy trade referred below.

3. The energy trade


2. The economic dispatch
Consumers of different types, industrial, residential,
commercial, public lighting, etc., represent the electrical
The interconnection of power stations in a system
market.
involves several conditions, which include the member-
The market includes three sectors:
ship to the Economic Load Dispatch Centre (CDEC).
This means the acceptance of operation in a co- * contract rate customers (free agreed rates),
O.E. Moya / Energy Policy 30 (2002) 575–582 577

* distribution utilities (regulated rates and node prices It is possible, therefore, to conclude that the electric
for regulated users), trade is made up of all the particular agreements that
* pool of generators (marginal costs obtained every have been achieved between generator utilities and large
quarter of an hour). customers. The relationships so created are completely
independent of the technical facts originated in the
economic technical dispatch. Whereas in the energy
Chilean legislation considers different rules for two trade operate open market conditions, irrespective of
large classes of customers: contract rate clients and physical links, in the economic dispatch, there is a
regulated users. Large consumers (over 2 MW at central decision making process. This process is
present) belong to the contract rates group. Small supervised by the CDEC.
consumers (with installed capacity below 2 MW) have The only common magnitude in both environments is
regulated energy and power rates, which are fixed by the energy produced by each generator.
authority periodically (every 6 months). Generator
utilities deal directly only with large customers and
distribution companies. Small users are served by the 4. Marginal costs and node prices
distribution company corresponding to their location.
Node prices are the high voltage energy and power Marginal costs are obtained ex post on a quarter of an
prices used for energy sold to distribution companies in hour basis, considering the machines that were dis-
the proportion of regulated consumers load to total patched at each time interval. Usually, the marginal unit
demand. These values are calculated every 6 months by is the most expensive unit dispatched at any time. Hydro
the regulator (NEC). units are represented by a curve of equivalent cost,
The electrical energy open trade takes place mainly which is adjusted according to hydrological conditions.
with the contract rated customers. There is a direct Penalty factors for generators are used to correct each
agreement on electricity rates between the generator marginal cost according to the extra transmission losses
utilities and the customers. Contract rate customers caused by a unit increase in energy. Thus, the corrected
within the area of a distribution company can buy their higher marginal cost gives the system marginal cost.
energy either from this company or from a generating Node prices represent an estimation of future margin-
company, in which case they are subject to a wheeling al costs on the average. Economic dispatch is simulated
right to be paid to the distribution company. in order to obtain nodal prices. Each time interval
The second sector is represented by distribution corresponding to load blocks of the duration curve is
utilities that intermediate between generators and final solved separately. The 12 months of a year are
users. Node prices are used for that part of a simulated.
distribution utility energy and power that is delivered The electrical law requires an averaging of expected
to regulated customers. The price for the rest of the energy marginal costs over 4 years. This allows for the
demand is left to free negotiation between generator and consideration of new plant that may be expected to enter
distribution entity. into service in the next years. The average so obtained is
Each generator in the system can sign agreements called basic energy price. It is referred to a relevant node
with any large customer. The only constraint is that the in the system chosen as reference by the regulator in
generator can undertake energy not exceeding its firm node price calculations, which are performed every 6
energy. This is the value of energy that a generator can months.
deliver to the system with a reasonably high probability, The calculation involves long term exploratory
explicitly defined in regulations, or the amount that has analysis in the SIC, due to the presence of large
been agreed with other generator. Anyhow, a difference reservoirs, which causes interactions between different
between the contracted energy and the actual produced years. The probabilistic nature of hydrology requires
energy in every monthly period always exists. That special software, which includes uncertainty in the right
amount is sold or bought, depending on whether there is assessment of expected or future energy prices.
a surplus or a deficit of actual generation with respect to For each node in the main grid, the node price is
the contracted amount. This difference is traded in the obtained by multiplying the basic energy price by a load
third sector, which is the pool of all connected penalty factor, which considers marginal losses caused
generators and is based on node marginal costs or spot by the respective load.
prices.
Generators with surplus receive payment from those
with deficit, with energy valued at the instantaneous 5. The capacity market
system marginal costs prevailing at the time when the
surplus occurred. These costs have been obtained in the In the electricity markets, distinction is made between
economic dispatch process. energy and power products. Power markets are the same
578 O.E. Moya / Energy Policy 30 (2002) 575–582

as the energy ones: contracts, regulated and pool capacity a transmission wheeling, which must be equal
markets. to the annualised investment of equipment involved.
Energy rates are used to obtain energy component Transmission owner companies receive a basic transmis-
payments to producers. Capacity rates (Oren et al., sion income in this way, which essentially represent
1985) are used for payments of firm power delivered by investment recovery with a fixed discount rate of 10%.
each generator company. This variable takes into Part of the payments are based on the marginal cost
account installed and available power that each of transmission which consists of marginal losses and
generating company puts as an asset that can be called congestions produced by each generator. This cost is
at any time to replace other units that may go out of dependent on the transmission path going from the
service. generator to his customers. These marginal costs are
Firm power requires definition of both system firm obtained as differences between energy withdrawn at
power and generator unit firm power. nodes where customers are connected and injected
System firm power is the amount of power that can be energy at nodes where the units are connected. The
guaranteed with a certain probability. This probability is amount collected as marginal costs of transmission has,
taken from the system loss of load probability LOLP historically, represented only a fraction (10–15%) of the
(Billinton and Allan, 1984) calculated for the season or basic transmission income. These payments affect in
annual peak demand. System firm power is usually different ways to generators, according to their con-
higher than peak load since installed capacity exceeds tracts. The sum thus received by transmission owner
load. companies is deducted from the basic transmission
A generating unit firm power is the contribution that income before the calculation of generators’ contribu-
a unit makes to the system firm power and it is an tions.
important figure as a part of the economic return
depends on it. Units with lower failure rates tend to be
those that present higher firm powers as percentage of 7. Experience: benefits and problems
their rating.
Firm power of a generating company is the sum of 7.1. Benefits derived from deregulation
firm powers of all its units. A company has a contracted
power, which is the sum of peak demands of all of its Efficiency and designs economically optimised are
customers. When the company has a larger firm power among other consequences. Old units have been
than the contracted power, an export occurs and the replaced due to their higher operating cost.
company receives a payment according to the system The most important achievement is the ability that the
power marginal cost. Funds come from all generators system has shown to keep up with a high demand
that have deficits of firm power. growth, with annual percentages between 6% and 9%.
The unit power price is obtained from the annualised The period between 1990 and 1999 shows the largest
investment cost per MW of a combustion gas turbine. It growth of generated energy in Latinamerica of 193%.
is also fixed by NEC every 6 months. Final user rates have gradually reflected the market
energy and power prices. They are in the range of 24–38
US$/MW h for industrial customers (year 2000), which
6. The transmission sector are the third lowest in Latinamerica (considering data
from ten countries) and between 76 and 92 US$/MW h
Transmission is unbundled from generation, though for residential consumers, which is the seventh lowest
generator companies may own transmission assets. value.
Open access is guaranteed by law to any generator The open market for large customers has triggered an
that wishes to interconnect with the system through the important increase of projects linked to the mining
transmission system (Rudnick et al., 1995) This gen- sector, the main export activity of the country.
erator must concur to financing possible installation Open market prices went down by some 45% in 5
extensions. years in the northern system, due to strong competition
Generators must pay transmission rights depending and the introduction of natural gas as the main primary
on the part of the system that belongs to their influence energy fuel. It should be pointed out that open market
area. This is the set of lines, substations and other prices push the regulated rates in this system because of
facilities that are located between the generating station predominance of free-contract customers.
and the reference node, which is the point where the The central system has shown a 23% reduction in the
energy base price is fixed and is defined by the regulation last years, but not a net reduction with respect to the
authority. The contribution is completely independent period previous to deregulation. It must be recalled
of the generator power transfers agreed with its that as electrical rates are a socially sensitive field, before
customers. All generators pay in proportion to their the reforms they were usually directly or indirectly
O.E. Moya / Energy Policy 30 (2002) 575–582 579

subsidised. As the SIC is mainly dependent on water energy for which he receives payment. This introduces
resources, the impact of natural gas has not been as high distortions such as subsidies among generators. This is
as in the SING. Regulated customers predominate in due to the differences that are common between spot
this system. Companies have experienced some bad prices, used for transfers among generators, and
years mainly due to some droughts but all the initial contract prices.
entities are very active in the market after 18 years of the
reformed scheme and have achieved good economic 7.2.2. Transmission problems
results. The fact that the transmission system in SIC belonged
External effects ought to be mentioned since an to the main generator company was a problem till last
important consequence has been a partial property year 2000. It is believed that the transmission has been a
distribution in the public and the private social security barrier for new entrants to the generator market,
institutions returns that have been obtained as being especially those of intermediate or small size.
important partners in electric companies. Transmission payments face the trouble of interpret-
Summary of benefits: ing properly the way to determine influence area of each
generator. It has not been uniformly understood,
1. investment rate in accordance with the demand though the concept refers to that region of the system
growth, that is seen as common land for transactions among
2. system reliability satisfactory, generators of different companies. There have been
3. rates increase less than the national gross geographi- difficulties in writing down this idea in objective terms.
cal product, The authority has defined in a by-law the influence area
4. partial distributed property, as the zone located between the generator and the
5. externalities on social security funds return, reference node used by the regulator in the regulated
6. a working market in generation. rates setting process. But this definition addresses
mainly to a radial system and thus some ambiguity
7.2. Practical problems in the power sector appears with parallel flows and counter-flows.
Companies commissioning new plant have sometimes
7.2.1. Problems of organisational nature preferred to build their own lines instead of being
Several problems have appeared since deregulation in dependent on the transmission system owned by other
1982. Difficulties are related to transmission rights, firm generator companies. It is the case of Colbun ! 220 kV
power, node prices, penalty factors, reliability consid- lines in the central system and Gener 220 kV lines in the
erations and interpretation of marginal costs; over- northern system.
installation exists in the northern system; the number of
actors in the generation market has remained small. 7.2.3. Security difficulties
Disagreements are dealt within the CDEC. If no Security issues have appeared when responsibilities
solution is found, an appeal to authority or divergence is for provision of associated equipment, such as capaci-
submitted. If then there is no agreement still there are tors, reactors and static compensators, are not very clear
legal actions. This has caused that some problems are in the procedures. After a disturbance that interrupts
delayed by years and sometimes damage to operation some supply occurs, responsibility is supposed to be
has occurred due to legal ambiguities. shared by all generators, which discourages improve-
Technical problems are usually difficult to solve due ments that may be developed by a generating company
to the system configuration: long transmission lines in particular. Joint financing of improvements is
threaten security and voltage regulation, a high hydro restrained since the companies are competitors.
component in generation creates trouble in dry periods, Drought in 1999 was well over the statistical record of
presence of some units with high ratings with respect to the central system and led to compulsory partial
system size and demand concentration in a zone of the rationing of 10% for the first time after deregulation.
system. It was not quite clear whether compensations should be
On the other hand, commercial difficulties arise due to paid to rationed customers or not, and thus a by-law
the low number of generator companies of sufficient size established an obligation to supply in future events
in competition. Moreover, distribution companies cover under any hydrological condition. Whether this rule
geographical regions of very different sizes, which may might have affected investor interest from 1999 onwards
lead to the risk of monopsonial behaviour. And last, but has still to be cleared up.
not least, the regulated rates fixed by authority may not The northern system faced problems with new
always be attractive enough for generators to sign long combined cycle units size and frequent failures during
term agreements. their first months of operation. Outage of the largest
Commercial contracting has the disadvantage that the unit produced system collapse due to low frequency
supplier of a customer does not necessarily generates the despite the presence of an existing load-shedding
580 O.E. Moya / Energy Policy 30 (2002) 575–582

scheme. Four blackouts and several partial interruptions not affect electrical marginal costs. All companies in the
affected the SING between 1998 and 2000. Reduction of northern system started nearly simultaneous projects,
unit outages and limiting the maximum unit power has which had the effect of increasing installed capacity too
recently permitted an important improvement. much over the peak demand (about 3000 MW of
capacity versus 1200 MW in 2000), with the consequent
7.2.4. Capacity contribution controversy inefficiency introduced into the sector.
Capacity contribution has a return by means of the Summary of problems:
recognised firm power of each generating unit. Dis-
agreements have appeared on the form to consider the 1. ambiguity in definition of transmission influence area
calculation of firm power. This might be considered to for cost allocation purposes;
be dependent on generator dynamics, the quality of 2. marginal cost distortions due to several non-energy
hydrology or the reduction of available power due to attributes;
transmission constraints. 3. ambiguity in the responsibility for energy shortages;
The argument has appeared that unit dynamics 4. lack of security and power quality equipment
should be included in firm power calculations, as this incentives;
affects the capacity to deliver power after short duration 5. reliability problems and several firm power inter-
failures. The dynamic features include time response and pretation problems;
start-up time. Another view considers that firm power 6. regulated rates sometimes differ from market prices
calculation is a form of capacity assessment and
therefore must consider reliability in its static meaning.
The same controversy has been present with respect to 8. Challenges for the new generation stage of
hydraulic units. Since they have faster time response, a deregulation
higher firm power with respect to thermal units should
be recognised. But this may lead to over-paid hydro- A good challenge for the electrical sector appears with
plants, which might discourage future thermal plant the possibility of making important changes to legisla-
investments. tion, which will introduce the system to those of the
second generation of deregulation.
7.2.5. Energy marginal costs discrepancies
There are actors in the sector that claim that any 8.1. The main challenges
increase in operation cost should affect the marginal cost
of energy. Since this value has a significant impact on The next step of deregulation considers rules for an
payments due to energy transfers among generators, open market with several options, including mainly long
there are other interpretations that separate energy and term contracts complemented with a short term power
what is known elsewhere as ancillary services. Thus, exchange (PE) (Hao, 2000). Additionally, an ancillary
voltage constraints may force to run an expensive unit service market, an independent system operator (ISO)
out of merit order and then energy marginal cost and intermediate energy traders are considered.
increases. The second point of view considers that How problems may be solved in this way?
energy marginal cost is not altered by this condition, Part of controversies is originated in the mixed role of
which is instead an increase in the cost of keeping system the CDEC. Technical decisions may conflict with
security. Since this aspect is responsibility of the whole commercial interests and this body is often subject to
pool, all generators should pay for it. the choice between secure service and minimum cost
The same difference appears when quick starting but operation. Separate bodies, with technical management
expensive running, small machines are brought into independent from energy trade, may alleviate the
service due to a sudden unit outage. The practical problems since decision making lies within a known
consequence has been that some generators have been sequence. It is convenient that CDEC becomes com-
indirectly benefited by outages, as they sell part of their pletely independent from generation or transmission
energy to the pool at marginal cost. Even if there are companies.
surplus of energy in the system, this sudden power The type of contracting will involve physical transfers
deficit might push up marginal costs. between supplier and user. This principle can avoid
distortions caused by only commercial transfers that
7.2.6. Over-installations have been used so far.
A consequence of using variable costs as the main The elimination of the firm power or capacity
economic signal for system dispatching had the effect payment based on a rate fixed by the authority may
that natural gas variable cost displaced coal-based units solve a number of controversies, since there have been
from competition. The pipeline investment is considered cases of over- and under-paying because the total
as fixed cost for the combined cycle units and thus does amount is fixed and independent of the actual system
O.E. Moya / Energy Policy 30 (2002) 575–582 581

reliability. The reserves market would take over as 8.2. The risks
ancillary services and the ISO will be responsible for
assigning the resources properly, i.e. assigning power for Risks are not absent of course in a market where few
generation and for reserves of different types. participants have significant presence. Market power
Calculation of node prices involves estimations made (Vieira Filho et al., 2000) may appear and introduce
by the regulator of the expected load growth rate and distortions, specially originated in large hydraulic
new generation stations to be installed in the near stations and reservoirs.
future. This information has been sometimes wrong or These risks could be reduced to some extent by
misinformation has tended to influence the diagnostics. encouraging competition as much as possible. Facilities
The increase of the number of deregulated customers for special generations, such as co-generation projects,
can encourage user participation in the market. In- distributed generation and new sources should be
formation based on historical behaviour of contract considered.
rates and PE clearing prices may improve the energy A possible decoupling between regulated prices to
cost estimations. It is expected that the PE operation final users and free market costs are a source of serious
will prevent prices from being under- or over-estimated. risk as well (IEEE Energy Trading Task Force, 2001).
In the process of fixing rates, today hydraulic energy Care must be taken that, in the process of fixing
expectancies are based on statistics and sometimes differ regulated rates, they are consistent.
significantly from the actual water inflows. Energy bids The short term market developed in the PE may not
by participants by considering other variables will lead favour large investments. Long term bilateral contracts
prices to an equilibrium and the generators, who are are relevant in stabilising prices in time.
directly affected by wrong decisions, instead of the
regulator, will assume risks. 8.3. Possible way for problem solutions
Marginal costs can be interpreted in different ways. In
the pool operation, there will be a uniquely defined (1) Ambiguity in definition of transmission influence
clearing price at each time. Transfers among generators area for cost allocation purposes: Transmission legisla-
will be subject then to prices known in real-time. tion considering experienced difficulties must be inte-
The ISO must solve the problems related to reli- grated into the deregulation process. A clear definition
ability according to standards. Generator dispatch will of transmission cost allocation is necessary with the
be his responsibility and then all precautions to degree of regulation required to guarantee open access
avoid important risks should be taken care. The so that transmission does not constitute a barrier to
feedback to PE will allow that prices are adapted to competition.
real conditions and so transfers will be paid according to (2) Marginal cost distortions due to several non-energy
explicit rules. attributes: Here, the market prices may reflect in a better
Specifically the transmission problem will be reflected way the different effects involved instead of a centrally
in congestion prices: these are expected to encourage marginal cost calculation.
transfers from generators to users located close to each The ancillary service market can manage the resources
other. On the other hand, transmission rights are linked with all type of reserves and voltage regulation.
expected to be linked with bilateral contracts or PE Separation of energy and ancillary services markets can
transfers, which should make transmission lines installa- avoid cross effects that introduce distortions to energy
tion more attractive in places where they are most marginal costs.
needed by the market. (3) Ambiguity in the responsibility for energy shortages:
Reliability requirements may be recognised by custo- The market clearing prices should reflect the risks faced
mers, including distributors, and thus pricing will show by generators according to their contracts and short-
the implicancies openly. The same idea stands for term bidding. Power shortages, either due to droughts,
generators that will be paid back according to their generator forced outages or line faults, will have an
contributions. economic effect for energy market players. All actors
An important challenge common to many countries must make their own provisions, such as emergency
nowadays is the environmental issue. In Chile, all equipment, backup contracts, insurance policies, etc.
industrial, building development and mining projects (4) Lack of security and power quality equipment
must approve an environmental impact study. There has incentives: The ancillary service market can manage the
been a growing concern about emissions by thermal resources linked with all type of reserves and voltage
plants and hydrostations projects face the opposition of regulation. Reactive static compensators, capacitor,
local population because they flood extensive surfaces. reactors, transformers, phase-shifters, etc. will be
Right solutions are one of the major challenges for the installed according to requirements. The ISO must state
future development of the power sector, irrespective of clearly the accountancy of cost and benefits of
the market approaches adopted. participants during operation.
582 O.E. Moya / Energy Policy 30 (2002) 575–582

(5) Reliability problems and several firm power inter- probably make provisions for eventual energy shortages
pretation problems: Firm power concept, with authority and suitable bids of power reserves can be expected.
intervention in the interpretation and in fixing its price, Energy traders and a completely ISO can contribute
is not necessary in an ancillary service market. to providing economic signals for economic operation.
Ancillary services, separated from energy market, A suitable and uniquely defined form of transmission
should reflect the need of each complementary resource. cost allocation is the main step to stabilise this market
It is observed that just splitting ancillary services and with well-known rules for new projects and entrants to
energy prices may solve several problems. This is the generation market. Risk of market power is
apparently the most effective change that may be identified as the main uncertainty that can threaten the
introduced, in terms of reducing or removing practical proper working of the electrical sector.
difficulties.
(6) Regulated rates sometimes differ from market
prices: This problem should be faced in a more realistic Acknowledgements
way, such as linking more closely the final value to the
market average trend. Other policies to avoid high This paper was prepared within research project 199-
energy rates, without interfering with the energy market, 0599, FONDECYT, Chile.
may consist in providing subsidies to some consumers.

9. Conclusions References

Bernstein, S., 1988. Competition, marginal cost tariffs and spot pricing
The first generation deregulation applied in Chile
in the Chilean electric power sector. Energy Policy 16(4), 369–377.
since 1982 has experienced several achievements, but Billinton, R., Allan, R.N., 1984. Reliability Evaluation of Power
also has faced several difficulties of technical, commer- Systems. Plenum Press, New York.
cial and legal aspects. Hao, S., 2000. A study of basic bidding strategy in clearing price
From that experience, a good number of improve- options. IEEE Transactions on Power Systems 15(3), 975–980.
ments can be expected when the new stage of deregula- IEEE Energy Trading Task Force, 2001. IEEE PES energy trading
task force: the California energy crisis. IEEE Summer Power
tion is implemented. Introduction of ancillary service Meeting, Vancouver, July.
market can relieve a number of distortions existing Oren, S., Smith, S., Wilson, R., 1985. Capacity pricing. Econometrica.
during the first stage and thus is identified as one of the 53 (3), 545–566.
most effective actions to improve competition, transpar- Rudnick, H., Palma, R., Fernandez, J.E., 1995. Marginal pricing and
ency and the right type of economic signals to market supplement cost allocation in transmission open access. IEEE
Transactions on Power Systems 10 (2), 1125–1142.
participants. A market opening can be helpful in Vieira Filho X., et al., 2000. Economic efficiency and market power
defining market prices, which will be used for transfers issues in bid-based hydro dispatch. Session 200, CIGRE, Paper 38-
among different companies. The involved agents would 203, Paris, August.

Potrebbero piacerti anche