Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
315-322, 1996
Copyright © 1996 Elsevier Science Ltd
Printed in Great Britain. All rights reserved
ELSEVIER 0142-0615(95)00075-5 0142-0615/96/$15.00 + 0.00
Y JwooHwu
Department of Electrical Engineering, Kung Shan
Institute of Technology and Commerce, Tainan,
Taiwan, Republic of China
315
31 6 Planning of distribution substations, feeders and sectionalizing switches; Y.- Y. Hsu and Y. Jwo-Hwu
L1 L2 LIO
i
v
LI1
,712
n
T1
reconfiguration in normal system operation. The overall L4 L5 L6 L7
distribution problem is divided into three subproblems,
i.e., the substation planning problem, the feeder planning ,74] ,95 $6 `77 `78]
TO
problem and the sectionalizing switch planning problem. 10 LO l L9 I
Heuristic algorithms based on operators' experience are
developed for each subproblem in order to reach the
desired planning results. In order to demonstrate the `72 l ~ ,7711 ,7/g
effectiveness of the proposed heuristic algorithms, dis-
tribution planning is conducted on a distribution system
(b) LI L2 LIO Lll n
T1
in Taipei, Taiwan. It is found that a proper distribution
L4 L5 L6 L7
plan can be achieved very efficiently by the proposed
algorithms. `75 $6 `77
`74 ,7~
TO S17'
~ro .. L3 .. L9 r8
II. Problem f o r m u l a t i o n ,715 ,713 $916,
Consider a distribution system with 12 load points ,710
`72 ,714 ,711 ,712r--- 3
L o , L 1 , . . . , L l l , as shown in Figure la. If the load
points are supplied with power from the two feeders f0 ~)[CX L1 L2 LIO LI1 n
T1
and fl as shown in Figure la, the network structure is
simple and radial. The investment cost is low in this case. L4 L5 L6 L7
However, reconfigurations for line loss reduction or
`74] `75 `76 ,77
voltage correction under normal system operation and
restoration after a fault are impossible.
The network in Figure lb is a loop-structure config-
uration. In normal operation, a certain tie switch such as
! 5
switch $6 is opened to make the system radial. To s2 s3 sn Sl41 Sl]
reconfigure the network, the open tie switch is moved to LI 1,2 L10 Lll 17
some other places such as $5 or $7. Only a small number (d) T/
of alternative configurations are possible for the network
in Figure 1b. To have more possible configurations, more Figure 1. A simple distribution system. (a) A radial
feeder sections and switches can be placed to form the network. (b) A simple loop-type network. (c) A net-
network of Figure lc. However, the investment cost may work with a great number of feeder sections and
be too high. As a trade-off between the investment cost switches. (d) A network with a reasonable number of
and the availability of feeder configurations, the network feeder sections and switches. Legend: [] Ti: main
in Figure ld may be a good choice. transformer Ti; Si: candidate switch position; ×:
From the simple distribution system in Figure 1, the
switch; fi: feeder i; • Li: load point Li
following observations are made. points are supplied power and no components are over-
(1) It is impossible to perform reconfiguration on a radial loaded. The investment cost must be minimized while
network. satisfactory feeder reconfiguration can be achieved in
(2) The network must be planned as a loop for the purpose future system operation.
of feeder reconfiguration in system operation.
(3) A network with a great number of feeder sections and
sectionalizing switches can offer more possible con- III. The proposed distribution planning
figurations in system operation. The operational cost algorithm
will be reduced. However, the investment cost is high Figure 2 depicts the block diagram of the proposed
in this case. A trade-off between the investment cost planning algorithm. The algorithm proceeds as follows.
and operation cost must be made.
Step 1. Specify the desired number of substations.
With these observations in mind, we can proceed to Step 2. Use the substation planning algorithm to be
give a definition of the distribution planning problem described in Section IV to determine the installed
under study. capacities and locations of substations.
Step 3. Use the feeder planning algorithm to be described
The distribution planning problem in Section V to determine the feeder network
Given the forecast loads, determine the locations, configurations.
installed capacities and total number of substations, the Step 4. Use the sectionalizing switch planning algorithm
feeder network structure and the locations and total to be described in Section VI to determine the
number of sectionalizing switches such that all load locations of sectionalizing switches.
Planning of distribution substations, feeders and sectionalizing switches." Y.- Y. Hsu and Y. Jwo-Hwu 317
$ number of blocks bi
to sobstBtion
No
T . No
STOP ]
Table 2. Summary of typical load patterns (A) and installed capacities (A) of load points in Figure lb
Year
~
load pattern ~
point
0 1 2 3 4 5 6 7 8 9 10 11
1st 0 50 30 20 15 5 10 10 10 15 30 45 35
1st 1 40 25 25 15 5 10 5 5 10 25 40 30
1st 2 30 20 10 10 5 5 5 10 10 20 35 25
2nd 3 40 30 25 15 10 10 5 5 15 30 30 30
2nd 4 50 30 15 20 5 10 10 10 20 30 45 35
2nd 5 45 40 30 20 10 10 5 10 20 35 50 35
Installed capacities 50 40 30 20 10 10 15 10 20 40 50 40
Planning of distribution substations, feeders and sectionalizing switches: K- K Hsu and Y. Jwo-Hwu 321
Example 2 Planning of sectionalizing switches using in system operation. The following procedures are recom-
the key position method mended in order to increase the possible configurations.
Consider the distribution system in Figure lb. The rated Step 1. Designate the longest edge as the candidate edge.
capacities for main transformers and feeders are assumed Step 2. Select a load point in the middle of the candidate
to be 600 A and 300 A, respectively. The installed capa- edge as the candidate load point.
cities and six typical load patterns are summarized in Step 3. Connect the candidate load point to a load point
Table 2. on another edge which is closer to the candidate
Note that only six load patterns are considered in the load point.
example for convenience of demonstration. In addition,
only the first three typical load patterns appear in the first The above procedures are repeated until the number of
year. And the last three typical load patterns are assumed configurations is enough.
to appear in the second year.
In step 1, place 13 switches at 13 candidate switch
positions. In step 2, the near-optimal feeder configuration VIII. Applications of the proposed method
for each typical load pattern is as follows. The proposed heuristic search algorithms have been
applied to plan a distribution system as shown in
SET0 = (57) , SET l =-- (56) , SET2 = ($8), Figure 4. The estimated cost for constructing a distri-
bution substation is $200000. The estimated cost for
SET3 = ($5), SET4 = (57), SET5 = (56). constructing a 500kVA main transformer is $370000.
So, SETopen = ($5, S6, 57, 58) The cost of constructing a primary feeder (336kCmil
There is only one switchable region AREAl in this aluminum conductors) is estimated at $40 000/km. The
example. cost of each remotely controlled switch is estimated at
$2000. It is assumed that the operators are satisfied with
AREAl = (Ls, L6, LT, $5, S6, 57, $8) the performance of reconfiguration if there are more than
100 possible configurations. The total number of sub-
The maximum load of switchable region AREA l is stations, NsuB, main transformers, NTR, feeders, N F E ,
LOADmax(AREA1) -= max[30, 20, 20, 20, 30, 35] = 30 and sectionalizing switches, Nsw, feeder length, Lf, and
total investment cost, Ct, of the distribution plans
As no transformer or feeder is overloaded, it is not obtained by applying the proposed algorithms are
necessary to narrow down AREA1. summarized in Table 3. It is observed from the results
In step 3, the performance of reconfiguration is satis- in Table 3 that the distribution plan with two substations
factory because there are four feeder configurations. is superior to the other plans because it has the lowest
In step 4, Nsw = 13 > S W m i n = 2. Therefore, we go to investment cost.
step 5 to decrease the', total number of switches. As
switches $1, $2, $3, $4, $9, S10 and Sll never appear in
SET/ (i = 0, 1 , . . . , 5), they can be removed. Note that IX. Conclusions
switches (circuit breakers) So and S12 cannot be removed In this paper, the distribution planning problem is
because we need a circuit breaker at the head of a feeder. divided into three subproblems: the substation planning
In step 3, the performance of reconfiguration is satis- problem, the feeder planning problem and the sec-
factory and Nsw = 6 > S~Vmi n • 2 in step 4. tionalizing switch planning problem. Heuristic search
In step 5, switch $8 is selected as the switch to be algorithms are developed for the three subproblems. A
removed as switch $8 appears only in SET2. Note that the major feature of the proposed planning algorithm is that
near-optimal feeder configuration SET2 = ($8) for load the need for network reconfiguration in future system
pattern 2 is lost because there is no switch placed at the operation is taken into account. From the results of this
candidate switch position $8. work, it is concluded that proper distribution plans can be
In step 3, the perforraance of reconfiguration is satis- obtained in a very efficient manner by the proposed
factory and Nsw = 5 > S W m i n = 2 in step 4. algorithms. The following specific conclusions can be
In step 5, switch S5 is selected as the switch to be made based on the results from this work.
removed.
In step 3, the performance of reconfiguration is not
satisfactory as there are only 2 feeder configurations (1) Several substation plans with different numbers of
which can be used. Therefore, we go to step 6. substations are recommended by the proposed algo-
In step 6, Nsw = 4 < S W m a x - - 13. Therefore, we go to rithm. The system planner can choose one among the
step 7 to restore switch $5 and stop. The result is various substation plans based on his own need.
summarized in Figure lb. (2) For the purpose of feeder reconfiguration, the feeder
network must be planned as a loop-type structure. In 9 Grawford, D M and Holt, Jr S B 'A mathematical optimiza-
system operation, some tie switches in the loop-type tion technique for locating and sizing distribution sub-
network are opened in order to make the system station and deriving their optimal service areas' IEEE
radial. Trans. Power Appar. Syst. Vol 94 (1975) pp 230-235
(3) In the planning of the feeder network and sectionaliz- 10 EI-Kady, M A 'Computer-aided planning of distribution
ing switch, the principal objective is to minimize the substation and primary feeders' IEEE Trans. Power Appar.
investment cost. In addition, the number of possible Syst. Vol 103 (1984)pp 1183-1189
configurations must be as large as possible as we need 11 Wall, D L, Thompson, G L and Northcote-Green, J E D
to perform feeder reconfiguration in future system 'An optimization model for planning radial distribution
operation for the purposes of load balancing and loss network' IEEE Trans. Power Appar. Syst. Vol 98 (1979)
reduction under ever-changing loading conditions. pp 1061-1067
(4) In the case of a fault event, sectionalizing switches can 12 Sun, D I, Farris, D R, Cote, P J, Shoults, R R and Chen, M S
be used to locate the fault, to isolate the faulted 'Optimal distribution substation and primary feeder plan-
section and then to restore the electricity service to ning via the fixed charge network formulation' IEEE Trans.
unfaulted sections. In the present work, we try to Power Appar. Syst. Vol 101 (1982) pp 602-609
make the number of possible configurations as large 13 Mikic, O M 'Mathematical dynamic model for long-term
as possible. In this way, we are able to restore the distribution system planning' IEEE Trans. Power Syst.
electricity service to unfaulted sections from neigh- Vol 1 (1986) pp 34-40
bouring feeders through the switching operations of
14 Ramirez-Rosado, I J and Gonen, T 'Pseudodynamic plan-
the sectionalizing switches. ning for expansion of power distribution systems' IEEE
Trans. Power Syst. Vol 6 (1991) pp 245-254
15 Willis, H L, Tram, H N and Powell, R W 'Substation siting
X. Acknowledgement and capacity selection based on diversity maximization'
Financial support given to this work by the National IEEE Trans. Power Syst. Vol 2 (1987) pp 692-699
Science Council of R.O.C. under contract number 16 Nara, K, Satoh, T, Aoki, K and Kitagawa, M 'Multi-year
NSC82-0404-E002-098 is appreciated. expansion planning for distribution systems' IEEE Trans.
Power Syst. Vol 6 (1991) pp 952-958
17 Aoki, K, Kuwabara, H, Satoh, T and Kanezashi, M 'An
Xl. References efficient algorithm for load balancing of transformers and
1 Gonen, T Electric power distribution system engineering feeders by switch operations in large scale distribution
McGraw-Hill (1986) systems' IEEE Trans. Power Deriv. Vol PWRD-3 (1988)
pp 1865-1872
2 Gonen, T and Ramirez-Rosado, I J 'Optimal multi-stage
planning of power distribution systems' IEEE Trans. Power 18 Hsu, Y Y, Jwo-Hwu, Y, Liu, S S, Chen Y W, Feng, H C and
Deriv. Vol PWRD-2 (1987) pp 512-519 Lee, Y M 'Transformer and feeder load balancing using a
heuristic search approach' IEEE Trans. Power Syst. Vol 8
3 Hsu, Y Y and Chen, J L 'Distribution planning using a (1993) pp 184-190
knowledge-based expert system' IEEE Trans. Power Deriv.
Vol 5 No 3 (1990) pp 1514-1519 19 Wagner, T P, Chikhani, A Y and Hackam, R 'Feeder
reconfiguration for loss reduction: an application of dis-
4 Youssef, H F and Hackam, R 'Dynamic solution of dis- tribution automation' lEE Trans. Power Deriv. Vol 6 (1991)
tribution planning in intermediate time range' IEEE Trans. pp 1922-1933
Power Deriv. Vol 3 No 1 (1988) pp 341-348
20 Broadwater, R P, Khan, A H, Shaalan, H E and Lee, R E
5 Youssef, H K, Hackam, R and Abn-EI-Magd, M A 'Novel 'Time varying load analysis to reduce distribution losses
optimization model for long range distribution planning' through reconfiguration' IEEE Trans. Power Deriv. Vol 8
IEEE Trans. Power Appar. Syst. Vol PAS-104 (1985) pp
(1993) pp 294-300
3195-3202
21 Shirmohammadi, D 'Service restoration in distribution net-
6 Quintana, V H, Temraz, H K and Hipel, K W 'Two-stage works via network reconfiguration' IEEE Trans. Power
power system distribution planning algorithm' IEE Proc. C Deriv. Vol 7 (1992) pp 952-958
Vol 140 (1993) pp 17-29
22 Hsu, Y Y, Huang, H M, Kuo, H C, Peng, S K, Chang, C W,
7 Partanen, J 'A modified dynamic programming algorithm Chang, K J, Yn, H S, Chow, C E and Kuo, R T 'Distribution
for sizing, locating, and timing of feeder reinforcements' system service restoration using a heuristic search approach'
IEEE Trans. Power Deliv. Vol 5 (1990) pp 277-283 IEEE Trans. Power Deliv. Vol 7, (1992) pp 734-740
8 Chen, J L and Hsu, Y Y 'An expert system for load 23 Hsu, Y Y and Jwo-Hwu, Y 'Planning of distribution feeder
allocation in distribution expansion planning' IEEE reconfiguration with protective device coordination' IEEE
Trans. Power Deriv. Vol 4 (1989) pp 1910-1918 Trans. Power Deriv. Vol 8 No 3 (1993) pp 1340-1347