Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Presented by
Raymond W M Wong Division of Building Science & Technology City University of Hong Kong
Prefabricated Construction
Prefabricated construction refers to construction making use of readily-assemble components which are prefabricated off site and to connect them on site into a permanent structure in a convenient and structurally strong manner. Materials suitable for prefabricated construction mainly include concrete, steel and timber. Out of the three named, prefabrication using precast concrete is the most popular in Hong Kong.
Prefabricated Construction
The basic principle of using prefabrication in construction is to take the advantage of allowing some of the major building elements being produced off-site in a prefabrication yard or factory where productivity, quality and cost of works can be better controlled. The finished elements can then be transported to the site for assembly and connection.
Prefabricated Construction
The Construction using precast concrete has the following advantages. a) Precast elements produced in factory environment can be worked to a very high structural or architectural standards. b) Precast elements is more durable when compare to structure constructed in in-situ concrete. c) Elements can be stressed to produce structures of higher performance.
Prefabricated Construction
Continue - advantages of precast concrete d) Productivity is much higher than cast in-situ works especially when standardized design is adopted. e) Assembly & installation process carried out on site can save up significant amount of formwork & falsework especially when the structure is of very high headroom. f) Construction can normally be done in higher speed with easier supervision and reduced cost.
The insufficient rigidity mainly originated from the joints of the major elements, such as in joints between columns and columns, beams and columns, or beams to paneled walls etc. Sometimes, rigid joint design can be made to improve the performance, but this will, again, complicate the connection and increase the time and cost of work. Furthermore, prefabricated construction also inherits with the following drawbacks.
Drawback:
TTighter and longer period of coordination are required to allow for structural design, construction planning, procurements and approval procedures MMore time required in advance for production of precast elements until they can be accumulated to sufficient numbers for delivery to site to start installation. Huge working space is required for the carrying out of fabrication works. This is particularly critical under Hong Kong situation. Though most of the fabrication works are recently carried out in casting yards in China, this will increase the transportation cost by sea or on land.
Precast elements required huge amount of space as handling and storage area
d) SStorage and pre-installation handling, again, requires extra working space. e) IInstallation of precast elements on site requires careful planning and extra cranage provisions. f) HHandling and assembly of heavy precast members, poses certain safety problems and increase risk both to human operatives or to the semi-completed structure itself. g) TThe structure under assembly in its semi-completed state may cause difficulties in making access into the work spot. h) DDefective connections may result to cracks and water leakage which will create further maintenance problems.
2. Connecting beam to column Precast beam is connected to column in a variety of ways. For non-rigid jointing, corbel is usually formed on the column to support the precast beam. However, anchorage provision should be provided to secure the members from seismic or wind action. Rigid joint (moment resisting) is common for building requiring stronger performance. In this case, haunching arrangement by inserting link bars between the column and beam members and infill the joint afterward with concrete can often produce an acceptable joining result. It should be noted that suitable propping support should be provided before the final setting of the joint.
Beams rest on corbel of column (with tie bolt to secure beams from movement)
3. Topping to form the deck/slab Deck or slab of precast structure often appears in the form of a RC topping, placed on top of the precast beam and semi-slab (precast floor plank).
Case Examples
Later version of Harmony Block using inisitu faade cast at the same time with structural walls
Precasting yard was set up to produce precast elements for public housing projects in early to mid 1990
After-fix faade system required the formation of small amount of in-situ joint and grouting that easily caused leaking problem
Detail of faade installation using in-situ jointing arrangement in the later version of Harmony Block Construction
Forming the floor slab in the Harmony Block construction using semi-slab (right) and aluminium formwork (above)
Introduction of mechanical formwork systems incorporating the standard precast elements in the construction of latest version of public houses in the late 1990
Public houses using Concord design with special emphasis on the use of mechanicalised construction system
Layout of the Concord Block showing the position of the cast-insitu core wall, shear walls and precast faade
Other pioneered projects in the early 1990 constructed using semi-prefabricated concept
The construction of the Headquarter and Members Facilities Complex for the Hong Kong Jockey Club
Forming the floor slab using precast secondary beams and semi-slab for the main building (above) and members complex (right)
Detail of the floor system with the cast in-situ main beams and the place-in precast secondary beams
Features in the construction extensive use of precast faade and lintel beams, precast cast-in-situ internal partitions are also introduced
Construction of the Kowloon Canton Rail podium deck cargo handling bay on the ground level and on top for a large-scale residential development afterward
Connecting the precast column to the foundation cap with a base plate
Connecting beams to columns by stitching, a means to provide an in-situ joints with rigid RC links
Features in the construction large amount of external walls are constructed in precast faade untis, with major structural links tie back to the inner shear walls and floor slab
Incorporation of other sophisticated formwork in construction steel gang form for walls and table form for floor
Features in construction precast beam trough and precast sub-slab with RC topping forming the floor system
Practical Constraints
1. Tighter coordination to allow for structural design, construction planning, procurement & approval procedure 2. Required a critical amount of precast items before work can be economically used 3. Huge work space for handling precast elements especially in congested urban environment in Hong Kong 4. Congested site environment makes access and delivery of heavy precast units to the work spot becomes difficult 5. Quality assurance become critical especially where large amount of precast components are used as structural nature
Building Section
Close up look of the modulated dwelling units and the linking structure in the form of a access corridor
Building Section
Floor plan
Prefabricated Construction
Application in Civil Works
Precast girder erected on top of the piers to form the main span of the footbridge
Precast V-shape beam for the Route 3 elevated expressway at Kwai Chung
West Kowloon Expressway installing the precast box girder using balanced cantilever method with the help of track mounted gantry crane
Forming the elevated track of the West Rail using the slung launching girder
Forming the elevated track of the West Rail using the longitudinal steel support beam
Forming the elevated track of the KCR Ma On Shan Line by precast girder and lifted to deck level for erection using mobile crane
Early stage of the project formation and forming the piers for the viaduct
Precast parapet unit for the highway and railway road/track way
Forming the station platform using precast curb and plank (KCR Tsim Sha Tsui Station)
Forming the deck of the berth for the Container Terminal No. 9
Forming the deck of the Ting Kau Bridge using precast concrete plank
Precast units to form the 4m high 5-cell culvert system in Tseung Kwan O
Precast culvert in the form of semi-submerged tube Tsuen Wan West Reclamation as advanced work for the West Rail Tsuen Wan Station
Connecting the culvert from the precast section to the in-situ section
Precast box as footing to bridge tower Tsing Ma Bridge tower on Ma Wan side
Precast box as pump house for water cooling system in the Central Reclamation
http://personal.cityu.edu.hk/~bswmwong/