SCOPE OF WORKS

Tree, bed & Lawn Planting Play equipment with rubberized matting Paved Pathways Fencing Irrigation system Seating walls and bins Park furniture and feature poles Water feature and Synthetic grass soccer field Consultant: Contractor: Status:

BUDGET: R 3M
Uys and White LA Top Turf Complete

Site Handover Date: 1 November 2010 Practical Completion: 16February 2011 Final Completion Date: 18 April 2011

SCOPE OF WORKS
Pathways Consultant:

BUDGET: R 3M
KHLA

Trees

Contractor: Servest

Ablution building

Status:

Maintenance Phase

Play equipment, Sand soccer area.

Site Handover Date: 03 March 2011

Irrigation

Practical Completion: 30 May 2011

Planting

Final Completion Date: 23.June 2011

Furniture and artworks.

SCOPE
Construction of 2.1km road Consultant:

BUDGET: R 5,1M
GMH Consulting Engineers

Construction of 500m storm-water drainage with Hyson cells

Contractor:

Maju Mafani Construction

Construction of paved area near the ablution

Status:

Complete

Construction of security structure

Site Handover Date: 13 August 2010

Landscaping of entrance

Practical Completion:

12 January 2011

Final Completion Date: 28th January 2011

SCOPE
Ablution facilities Green roof Tree & Lawn Planting Playground Equipment with Ruberized matting Irrigation System, Gabion basket planters and seating Laser cut Fencing, Solar lights and solar pathway lights Paved Pathway & Parking Soccer Field Multi Purpose Court Consultant: Contractor: Status:

BUDGET: R 3M
Blueprint N and H /Tswelopele JV Complete

Site Handover Date: 14 October 2010 Practical Completion: 28 February 2011 Maintenance Completion Date: 31 August 2011

SCOPE OF WORKS

BUDGET = R2M

Linear Park Development Paving with header course Play mounds and designed play features Manual irrigation System Street Furniture

Consultant: Contractor: Status:

Consortium -NLA Consortium Countryline Complete

Site Handover Date: 26th October 2010 Practical Completion: 21 December 2010

Hydro Seed along wetland Tree & Lawn Planting Flower beds

Maintenance Completion Date: 20th January 2011

SCOPE OF WORKS

BUDGET: R 5,9M

Multipurpose Court

Consultant:

Petra Scapes

Change Rooms and ablution block

Contractor:

Uhuru construction

Rubberized Running Track

Status:

Construction phase

Irrigation System and drainage around track

Site Handover Date: 08 October 2010

Lighting

Practical Completion: 04 February 2011

Soccer field

Final Completion Date: March 2011

SCOPE
Site Clearance & Rubble removal Top Soil Cut to fill material Import Fill Material Scarifying & Fine Grading Electrical Sleeving Turf Valve System Tree Planting Grass Planting Play Equipment Boundary Bollards Signage Bins

BUDGET: R 1,331M
Consultant: Insite Contractor: Classic Gardens Status: Complete

Site Handover Date: 17 Sept 2011 Practical Completion: June 2011 Maintenance Phase August 2011

SCOPE
Site Clearance & Rubble removal Top Soil for flowerbed area Planting of bed Trees Scarifying & Fine Grading Paving Electrical Sleeving Turf Valve System Braai stands 5-a side Soccer Parking Bays Boundary Fence Gate Boulards Feature Artwork Signage Bins

BUDGET: R 2,851 M
Consultant: Insite Contractor: Classic Gardens Status: Complete

Site Handover Date: 17 Sept 2011 Practical Completion: 24 February 2011

SCOPE
Site Clearance, Tree & Lawn planting

BUDGET: R 1,318 M
Consultant: Insite

Walkway & Parking bays paving

Contractor: Classic Gardens

Rubbish Bins Concrete Bollards& Benches

Status:

Construction phase

Site Handover Date: 3 March 2011

Braai Units Feature artwork Fencing Play Equipment & Multipurpose Court

Practical Completion: 06 May 2011

SCOPE OF WORKS
Tree & Lawn Planting Play equipment with rubberized matting Paved Pathways and Park entrance structures Fencing Irrigation system Seating walls Park furniture Water feature Drinking fountain Tar surface basketball court Benches and braai areas Ablution Consultant: Contractor: Status:

BUDGET: R 3M
Marian Louw Amaluba Construction

Site Handover Date: 22 /02/2011 Completion Date: 20/04/2011

SCOPE
Earthworks & Soil improvement Trees supplied by Huddle Park Trees supplied by contractor 20 litre trees Extra large trees Specimen plants, shrubs & groundcover planting Kikuyu Lawn Paved Pathways Kerbs for walkways & soccer field Entrance feature gabion columns Seating walls with indigenous games panels Paving around plays areas (2) Gabion seating walls with coping Walls for murals & blackboard Recycling centre Paving for Indaba Tree Place Recycling centre

BUDGET: R 2,200 M
Site handover 20 May 2011 Construction start 20 May 2011 Construction complete 21 June 2011

SCOPE
Forming of Berms

BUDGET: R 1 007M
Consultants name: Insite Landscape Architects

Grass Planting Lawn seeding Tree Planting Construction of a safety net area Irrigation System Contractor: Bergland Gardens Status: Construction phase 90% Site handover date: June 2011 Practical Completion date: 15 July 2011 Final Completion date: 30 July 2011