Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Project Name: Division/Office: Project Sponsor: IT Coordinator: Review Date: NOTE: Provide comments whenever the answer is other than YES.
Yes
No
N/A
3.
4.
5. 6.
7.
8.
9.
10. Are Planning Participants identified and categorized per the column information in the Proposal? Comments: 11. Has a Business Case document been completed and approved (if required by CIO)? Comments: 12. Does the Business Case document further detail and clarify high-level information from the Proposal? Comments: PLANNING Project Plan, Statement of Work (SOW), Project Schedule, etc. (NOTE: Consider the quality not just the actual documentation required) 1. Was the project scope clearly defined as to what was in and out of scope for this project? (i.e., was it detailed enough to minimize doubt about what constituted a scope change?) Comments:
Yes
No
N/A
4.
5. 6.
7. 8.
20. 21.
22.
Project Review Checklist Version 1.1 April 16, 2008 For PMO Internal Use
Page 2
Yes
No
N/A
Executing/Monitoring/Controlling
Scope Management 1. Were all scope changes managed, controlled and documented throughout the project? (Review all change requests). Comments: 2. 3. 4. Was the process for scope management and change, as defined in the project plan, followed? Comments: Was the number of scope change requests reasonable for the project size? Comments: Was a specified product development methodology followed (e.g., information systems development methodology, etc.)? If so, were all necessary deliverables generated? Comments: If a specified product development methodology was followed, were all required deliverables generated and were all required review steps followed? Compare the methodology requirements against actual deliverables. Comments: Were the deliverables as specified in the SOW/project plan actually generated? Comments:
5.
6.
Time/Schedule Management 1. Was the process for schedule management and change, as defined in the project plan, followed? Comments: 2. 3. Was the project schedule (with both actual and estimate to complete) on a regular basis (i.e. weekly, bi-weekly? Comments: If scope changes occurred, were the project schedule and costs re-baselined accordingly to reflect the changes, if schedule/costs were impacted? Comments:
Cost/Budget Management 1. How did the final project costs compare with initial estimates? Comments: 2. Was the process for cost/budget management and change, as defined in the project plan, followed? Comments:
Risk and Issue Management 1. Are risks and mitigating actions documented in a Risk Management Plan and PRAM (Project Risk Assessment Matrix)? Comments: 2. Is there evidence of a review and update of the PRAM? This includes prioritized risks with executable, proactive actions assigned to owners? Comments:
Project Review Checklist Version 1.1 April 16, 2008 For PMO Internal Use
Page 3
Yes
No
N/A
Resource Management 1. Was the process for resource management, as defined in the project plan, followed? Comments: 2. 3. 4. 5. Was the number of resources allocated to the project sufficient to successfully complete the project on time and within budget? Comments: Were the skill set(s) of the allocated resources sufficient to successfully complete the project on time and within budget? Comments: Were the resources assigned to the project consistently available? Comments: Were the skill set(s) of the allocated resources sufficient to successfully complete the project on time, and within documented scope and budget? Comments:
Quality Management 1. Was the process for quality management, as defined in the project plan, followed? Comments: 2. Were specific product quality control and assurances processes followed and documented? Please specify what these controls and processes were (e.g., system testing, code review, etc.) Comments: Were any interim project reviews conducted? Comments: Were any project review process conducted by the PM, team, sponsor or PMO? Project reviews can occur at the mid-point and/or end of a project. Comments: If any project reviews were conducted, were the review findings shared and discussed with the Project Sponsor and/or related project team members? Comments: Were all required product development standards followed (e.g., development standards, etc.) Comments:
3. 4. 5. 6.
Project Review Checklist Version 1.1 April 16, 2008 For PMO Internal Use
Page 4
Yes
No
N/A
4.
5.
6.
7.
8. 9.
10. Does the PSR include a Change and Acceptance section and if so, does it indicate status of pending approvals or approvals secured since last status? Comments: 11. Does the PSR include an issues section? If so does it include open issues and issues closed since last status? Do the issues presented include required information (such as owner and target date)? Comments: 12. Does project management meet with the appropriate Customer management routinely to review the Project Status Report? Comments: 13. Are minutes kept for the Customer status review of the PSR with minutes noting, at a minimum, who attended, decisions made or communicated and action items (with owner and target dates)? Comments: 14. Did the project stakeholders (sponsor, customer, team, etc.) receive adequate and timely communications from the project manager (as needed)? Comments
Project Review Checklist Version 1.1 April 16, 2008 For PMO Internal Use
Page 5
Yes
No
N/A
Change Management 1. Were change requests generated when criteria for change occur and submitted on a timely basis (by next Customer status review)? Comments: 2. 3. Were change requests approved by the authorized person(s) within the timeframe defined in the Change Management section? Comments: Is the budget variance (activity to date plus estimate to complete vs. original budget plus approved change requests) acceptable? Acceptable is defined as 10% above approved baseline. Comments: Is the schedule variance (completion earlier or later than approved) acceptable (Ex. the only acceptable change in schedule would require a change request approval to therefore readjust the original schedule baseline)? Comments: Was the process for change management, as defined in the project plan, followed? Comments:
4.
5.
Acceptance Management 1. Was the process for acceptance management, as defined in the project plan, followed? Comments: 2. 3. Did the Customer approve the contract (if applicable)? Note: If yes, please note date and person(s) who signed. Comments: Were deliverables approved by the authorized person(s) within the timeframe defined in the Acceptance Management section? Comments:
CLOSING
1. Was a formal Project Closing session conducted to gather and share feedback on the project with the team, customer and project sponsor? Comments:
Project Review Checklist Version 1.1 April 16, 2008 For PMO Internal Use
Page 6
Yes
No
N/A
10. Is the project free from serious Customer issues or concerns? Comments: 11. Was the Project Manager responsive to issues escalated for their attention and resolution (if needed)? Comments:
Range)
$ 0 % Complete
$ 0
Range)
*NOTE: The Customer must have approved Baseline Value and Baseline Completion Date. Indicate if interim and approved estimates are also available. Attach additional work sheet as needed.
Project Review Checklist Version 1.1 April 16, 2008 For PMO Internal Use
Page 7
Additional Finding and Recommendations: This Project Review Checklist focuses on the review of Project Management Processes, not on any specific Product Management Processes (e.g., no on the quality or existence of any information systems deliverables). If , however, through the course of this project review the review team identifies issues that suggest a comprehensive Product Quality Review is needed, please provide details below with recommendations:
Please note the name and title of the people (Sponsor, Project Manager, project team members, SMEs, etc.) interviewed as part of this Review, as well as the members of the Project Review Team. Project Review Team Reviewer: Reviewer: Reviewer: Individuals Interviewed: Name: Name: Name: Name: Name: Name: Title/Project Role: Title/Project Role: Title/Project Role: Title/Project Role: Title/Project Role: Title/Project Role: Title: Title: Title:
Project Review Checklist Version 1.1 April 16, 2008 For PMO Internal Use
Page 8
Project Review Checklist Version 1.1 April 16, 2008 For PMO Internal Use
Page 9